2445 N MARIONDALE AVE 90032

Certificate Information: 2445 N MARIONDALE AVE 90032

Application / Permit
19014-10001-04561
Plan Check / Job No.
B20LA17977
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
Supplemental to 19014-10000-04561 for revised to arch, and structual plans Green and DAS revision.
Permit Issued
Issued on 4/15/2021
Issuing Office
Current Status
Permit Finaled on 5/26/2022

Permit Application Status History

Submitted 9/30/2020 APPLICANT
Assigned to Plan Check Engineer 10/8/2020 JOE VO
Corrections Issued 10/11/2020 JOE VO
Quality Review Completed 10/29/2020 MINYE PAK
Green Plans Picked Up 3/3/2021 APPLICANT
Plan Check Approved 3/22/2021 JOE VO
Issued 4/15/2021 APPLICANT
Building Plans Picked Up 5/13/2021 APPLICANT
Permit Finaled 5/26/2022 MARK FERRARI

Permit Application Clearance Information

DAS Clearance Cleared 1/7/2021 JOE VO
Green Code Cleared 3/3/2021 AARON COSTA

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Truedge Builds Inc; Lic. No.: 1035194-B 2600 E BIDWELL STREET STE 202      FOLSOM, CA 95630
Engineer Thompson,, John Mark; Lic. No.: C82557 6355 GRANBY AVE      ALTA LOMA, CA 91737

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/4/2021 Approved DANIEL COLLINS
Wood Frame 5/7/2021 Partial Approval LANNY MERRICK
Interior/Exterior Lathing 5/11/2021 Approved LANNY MERRICK
Wood Frame 5/18/2021 Not Ready for Inspection LANNY MERRICK
Interior/Exterior Lathing 5/19/2021 Not Ready for Inspection DANIEL COLLINS
Wood Frame 5/20/2021 Partial Approval RAFAEL ESPINOZA
Footing/Foundation/Slab 5/28/2021 Approved LANNY MERRICK
Interior/Exterior Lathing 6/2/2021 Approved LANNY MERRICK
Interior/Exterior Lathing 6/3/2021 Approved DANIEL COLLINS
Final 6/9/2021 Partial Inspection LANNY MERRICK
Green Building Final 6/9/2021 Approved LANNY MERRICK
Final 9/1/2021 Not Ready for Inspection LANNY MERRICK
Final 5/6/2022 Conditional Approval MARK FERRARI
Final 5/26/2022 Permit Finaled MARK FERRARI