1418 N NORTH SPRING ST 90012
Certificate Information: 1418 N NORTH SPRING ST 90012
- Application / Permit
- 19014-10001-02145
- Plan Check / Job No.
- B20LA05710
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- Early Start Permit for Foundation Only.
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- Issued on 12/21/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 3/26/2020 | SALVADOR QUINTANILLA |
| Corrections Issued | 3/26/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/12/2020 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/13/2020 | SALVADOR QUINTANILLA |
| Plan Check Approved | 12/21/2020 | SALVADOR QUINTANILLA |
| Issued | 12/21/2020 | APPLICANT |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/17/2020 | DENZEL HENDERSON |
| DAS Clearance | Cleared | 4/23/2020 | ELIZABETH TOMS |
| Sewer availability | Cleared | 4/27/2020 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2020 | WALLIE JONG |
| Specific Plan | Cleared | 6/4/2020 | OSVALDO GARCIA |
| Green Code | Cleared | 6/10/2020 | SALVADOR QUINTANILLA |
| Fire Marshall Fire Life Safety | Cleared | 8/19/2020 | MENOA AGHAJANI |
| Low Impact Development | Cleared | 10/14/2020 | MARTIN FRAGOSO |
| ZA Case | Cleared | 10/22/2020 | RUBEN VASQUEZ |
| Food establishment approval | Cleared | 11/12/2020 | LACDHS APPROVED |
| Food Service Establishment | Cleared | 12/4/2020 | RAMESHBHAIR PATEL |
Contact Information
| Contractor | Prieto J F Engineering Construction Inc; Lic. No.: 525452-B | 2026 GLENDALE BLVD LOS ANGELES, CA 90039 |
| Engineer | Daniel,, Nergal; Lic. No.: C77699 | 4504 FALCON CREST WAY TURLOCK, CA 95382 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/5/2021 | Partial Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 3/5/2021 | Conditional Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 3/10/2021 | Not Ready for Inspection | RONALD PACHECO |
| Footing/Foundation/Slab | 3/11/2021 | Partial Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 3/12/2021 | Conditional Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 10/18/2021 | Partial Inspection | DANIEL COLLINS |