24 E DUDLEY AVE 90291
Certificate Information: 24 E DUDLEY AVE 90291
- Application / Permit
- 19014-10001-01637
- Plan Check / Job No.
- B24LA07572
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN***Supplemental to 19014-10000-01637 Revision work includes: Interior layout modifications Minor revisions to window and door sizes including additional replacement windows Additional replacement siding and sheathing as required by existing conditions. Additional laundry No change to building size, footprint, floor area or occupancy.
- Permit Issued
- Issued on 10/14/2024
- Issuing Office
- Current Status
- Permit Finaled on 9/4/2025
Permit Application Status History
| Submitted | 5/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2024 | SINA KHOSRAVI |
| Corrections Issued | 5/22/2024 | SINA KHOSRAVI |
| Quality Review Completed | 6/18/2024 | CAROLYNN NEPOMUCENO |
| Plan Check Approved | 8/23/2024 | SINA KHOSRAVI |
| No Progress | 10/9/2024 | SINA KHOSRAVI |
| Plan Check Approved | 10/9/2024 | SINA KHOSRAVI |
| Issued | 10/14/2024 | APPLICANT |
| Permit Finaled | 9/3/2025 | JESUS RODRIGUEZ |
Permit Application Clearance Information
| Coastal Zone | Cleared | 8/8/2024 | MATHEW QUAN |
| Specific Plan | Cleared | 8/8/2024 | MATHEW QUAN |
| ZI | Cleared | 8/8/2024 | MATHEW QUAN |
Contact Information
| Architect | Ginter,, Gregory Hopkins; Lic. No.: C30686 | 1525 PEARL STREET SANTA MONICA, CA 90405 |
| Contractor | Owner-Builder | , |
| Engineer | Trevellin,, Maurizio; Lic. No.: C71368 | 707 ASHLAND AVE 2 SANTA MONICA, CA 90405 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| HVAC-Rough | 10/30/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 10/30/2024 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 10/30/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 10/31/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2024 | Partial Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 11/5/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 11/12/2024 | Not Ready for Inspection | HERBERT GIRON |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | HERBERT GIRON |
| PLUMBING-Final | 11/12/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 11/12/2024 | Approved | HERBERT GIRON |
| Shower Pan | 11/12/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 12/4/2024 | Approved | HERBERT GIRON |
| Final | 12/4/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 12/4/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 12/4/2024 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 12/4/2024 | Approved | HERBERT GIRON |
| Insulation | 12/23/2024 | Approved | KENNETH NAGLE |
| Drywall Nailing | 1/15/2025 | Approved | MICHAEL ALLEN |
| Interior/Exterior Lathing | 1/15/2025 | Approved | MICHAEL ALLEN |
| Final | 6/10/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Smoke Detectors | 6/10/2025 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 6/18/2025 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 8/28/2025 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 8/28/2025 | Approved | JESUS RODRIGUEZ |
| Final | 9/3/2025 | Permit Finaled | JESUS RODRIGUEZ |