1237 N COMMONWEALTH AVE 90029

Certificate Information: 1237 N COMMONWEALTH AVE 90029

Application / Permit
19014-10001-00217
Plan Check / Job No.
B19LA08826
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO PERMIT #19014-10000-00217 TO CAPTURE DWELLING UNIT AND RESIDENTIAL TAX.
Permit Issued
Issued on 5/24/2019
Issuing Office
Metro
Current Status
Permit Finaled on 2/7/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/1/2019 APPLICANT
Assigned to Plan Check Engineer 5/1/2019 EMMANUEL MARTINEZ
Plan Check Approved 5/1/2019 EMMANUEL MARTINEZ
Issued 5/24/2019 LADBS
Permit Finaled 2/7/2020 PATRICK QUALEY

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 7/1/2019 Approved PATRICK QUALEY
Wood Frame 7/1/2019 Corrections Issued PATRICK QUALEY
Wood Frame 7/8/2019 Corrections Issued PATRICK QUALEY
Insulation 7/15/2019 Corrections Issued PATRICK QUALEY
Interior/Exterior Lathing 7/15/2019 Corrections Issued PATRICK QUALEY
Interior/Exterior Lathing 7/16/2019 Corrections Issued PATRICK QUALEY
Insulation 7/29/2019 Not Ready for Inspection PATRICK QUALEY
Interior/Exterior Lathing 7/29/2019 Not Ready for Inspection PATRICK QUALEY
Interior/Exterior Lathing 8/5/2019 Not Ready for Inspection PATRICK QUALEY
Interior/Exterior Lathing 8/8/2019 Approved PATRICK QUALEY
Drywall Nailing 8/12/2019 Approved PATRICK QUALEY
Final 11/4/2019 Corrections Issued PATRICK QUALEY
Final 2/7/2020 Permit Finaled PATRICK QUALEY