5538 N HAZELTINE AVE 91401
Certificate Information: 5538 N HAZELTINE AVE 91401
- Application / Permit
- 19014-10001-00123
- Plan Check / Job No.
- B21LA20483
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL TO PERMIT # 19014-20000-00123: TO ENLARGE ADDITION
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/6/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 1/14/2022 | RACHEL BEYENE |
| Applicant returned to address corrections | 1/19/2022 | RACHEL BEYENE |
| Plan Check Approved | 3/9/2022 | RICARDO RAMIREZ |
| Building Plans Picked Up | 3/10/2022 | APPLICANT |
| Issued | 5/20/2022 | APPLICANT |
| Permit Finaled-Status Void | 2/23/2023 | RYAN SALAZAR |
| Re-Activate Permit | 3/9/2023 | RYAN SALAZAR |
| Permit Finaled | 3/17/2023 | RYAN SALAZAR |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/19/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 3/3/2022 | ROGELIO CORTES |
Contact Information
| Contractor | Yourico Construction Inc; Lic. No.: 594159-B | 1241 N THOMPSON AVENUE GLENDALE, CA 91201 |
| Engineer | Tan,, Charles; Lic. No.: S4758 | 3161 DRIGGS AVENUE ROSEMEAD, CA 91770 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 7/1/2022 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 7/8/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 9/7/2022 | Corrections Issued | RICHARD DOCKUS |
| PLUMBING-Rough | 9/7/2022 | Corrections Issued | RICHARD DOCKUS |
| HVAC-Rough | 9/8/2022 | Off-Hour Fees Due | |
| Wood Frame | 9/8/2022 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 9/15/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 9/15/2022 | Approved | RICHARD DOCKUS |
| Wood Frame | 9/15/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/21/2022 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 9/21/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/27/2022 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/4/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 10/4/2022 | Approved | RICHARD DOCKUS |
| Insulation | 10/12/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 10/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Sewer | 10/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Shower Pan | 10/21/2022 | Approved | KATHRYN BUTTERWORTH |
| Final | 1/18/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Final | 1/18/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Pre-Inspection | 1/18/2023 | Partial Approval | RYAN SALAZAR |
| Final | 2/23/2023 | Conditional Approval | RYAN SALAZAR |
| Green Building Final | 2/23/2023 | Approved | RYAN SALAZAR |