4456 E YELLOWSTONE ST 90032
Certificate Information: 4456 E YELLOWSTONE ST 90032
- Application / Permit
- 19014-10000-07216
- Plan Check / Job No.
- B19LA27576
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ALTERATION/ADDITION to existing single-story two car garage and patio cover to remove the existing patio cover and to add an enclosed irregular 23'x17.83' ( 391 SF) ground floor enclosed patio cover and a second story 23'x36' ( 774 SF) attached Accessory Dwelling Unit.
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- Valley
- Current Status
- CofO Corrected on 8/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/14/2020 | LUIS RINCON |
| Corrections Issued | 2/28/2020 | LUIS RINCON |
| Quality Review Completed | 3/5/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 3/10/2020 | APPLICANT |
| Applicant returned to address corrections | 8/12/2020 | LUIS RINCON |
| Applicant returned to address corrections | 8/19/2020 | LUIS RINCON |
| Applicant returned to address corrections | 9/10/2020 | LUIS RINCON |
| Applicant returned to address corrections | 10/30/2020 | LUIS RINCON |
| Green Plans Picked Up | 11/24/2020 | APPLICANT |
| Plan Check Approved | 1/6/2021 | LUIS RINCON |
| Issued | 1/29/2021 | APPLICANT |
| Re-Activate Permit | 8/9/2023 | RONALD MYRICK |
| CofO in Progress | 8/9/2023 | AMY COLIN |
| CofO Issued-Status Void | 8/9/2023 | RONALD MYRICK |
| Permit Finaled-Status Void | 8/9/2023 | RONALD MYRICK |
| Permit Finaled | 8/9/2023 | RONALD MYRICK |
| CofO Corrected | 8/9/2023 | RONALD MYRICK |
| Permit Finaled | 8/9/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Green Code | Cleared | 7/6/2020 | LUIS RINCON |
| Address approval | Cleared | 7/24/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/24/2020 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 12/7/2020 | JORGE MEJIA LEMUS |
| Construction near power lines | Cleared | 12/10/2020 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 12/15/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/17/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 1/6/2021 | LUIS RINCON |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2021 | Corrections Issued | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Partial Approval | COREY HUPP |
| Deputy Drilled-In Anchors | 6/29/2021 | Conditional Approval | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 7/14/2021 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/14/2021 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 7/14/2021 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2021 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 9/10/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/27/2021 | Corrections Issued | COREY HUPP |
| Gas Test | 10/27/2021 | Not Ready for Inspection | COREY HUPP |
| BUILDING-Rough-Frame | 11/17/2021 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 11/17/2021 | Approved | COREY HUPP |
| Gas Test | 11/17/2021 | Not Ready for Inspection | COREY HUPP |
| Green Building Rough | 11/17/2021 | Approved | COREY HUPP |
| HVAC-Rough | 11/17/2021 | Approved | COREY HUPP |
| PLUMBING-Rough | 11/17/2021 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 12/2/2021 | Partial Approval | COREY HUPP |
| Insulation | 12/9/2021 | Not Ready for Inspection | RUBEN SALAS |
| Insulation | 12/14/2021 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 12/15/2021 | Not Ready for Inspection | COREY HUPP |
| Drywall Nailing | 1/6/2022 | Approved | JOSEPH MCGARRY |
| Insulation | 1/6/2022 | Approved | JOSEPH MCGARRY |
| Sewer | 5/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 5/6/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Gas Test | 5/12/2022 | Approved | AMY COLIN |
| Service/Power Release | 5/12/2022 | Not Ready for Inspection | AMY COLIN |
| ELECTRICAL-Final | 5/19/2022 | Approved | AMY COLIN |
| Final | 5/19/2022 | Partial Inspection | AMY COLIN |
| Green Building Final | 5/19/2022 | Not Ready for Inspection | AMY COLIN |
| HVAC-Final | 5/19/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 5/19/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 5/19/2022 | Not Ready for Inspection | AMY COLIN |
| Smoke Detectors | 5/19/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 12/13/2022 | Corrections Issued | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 12/13/2022 | Corrections Issued | AMY COLIN |
| BUILDING-Rough-Frame | 1/13/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 1/13/2023 | Approved | AMY COLIN |
| HVAC-Rough | 1/13/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 1/13/2023 | Partial Approval | AMY COLIN |
| Insulation | 1/20/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 2/3/2023 | Approved | AMY COLIN |
| Shower Pan | 2/3/2023 | Approved | AMY COLIN |
| Wood Frame | 2/3/2023 | Approved | AMY COLIN |
| Drywall Nailing | 2/7/2023 | Approved | RUBEN SALAS |
| Final | 6/8/2023 | Corrections Issued | AMY COLIN |
| Green Building Final | 6/8/2023 | Approved | AMY COLIN |
| Final | 8/3/2023 | Partial Inspection | AMY COLIN |
| Final | 8/9/2023 | OK to Issue CofO | AMY COLIN |