827-831 N MICHELTORENA ST 90026

Certificate Information: 827-831 N MICHELTORENA ST 90026

Application / Permit
19014-10000-07203
Plan Check / Job No.
B19LA27537
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING CRAWL SPACE TO 733 SF ADU ACCESSORY DWELLING UNIT PER ORD NO 186481.COMPLY WITH DEPARTMENT ORDER effective date 09/23/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 6/30/2022
Issuing Office
Current Status
CofO Issued on 3/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 ARSALAN SHABESTARI
Corrections Issued 2/4/2020 ARSALAN SHABESTARI
Quality Review Completed 2/24/2020 HERNAN ARREOLA
Green Plans Picked Up 2/28/2020 APPLICANT
Building Plans Picked Up 3/2/2020 APPLICANT
Applicant returned to address corrections 12/15/2020 ARSALAN SHABESTARI
Plan Check Approved 6/3/2021 ARSALAN SHABESTARI
Issued 6/30/2022 APPLICANT
CofO in Progress 2/29/2024 COREY HUPP
CofO in Progress 3/5/2024 COREY HUPP
CofO in Progress 3/5/2024 COREY HUPP
Permit Finaled 3/27/2024 DANIEL SANCHEZ
CofO Issued 3/27/2024 DANIEL SANCHEZ
Permit Finaled 3/27/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 5/27/2020 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 5/27/2020 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 5/27/2020 EMIL KYUPELYAN
BHO/Hillside ordinance Cleared 5/27/2020 EMIL KYUPELYAN
Sewer availability Cleared 5/27/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 6/22/2020 EMIL KYUPELYAN
Green Code Cleared 4/7/2021 DONALD CRICHLOW

Contact Information

Architect Cambianica,, John; Lic. No.: C14824 1018 SOUTH SANTA ANITA, SUITE 1      ARCADIA, CA 91006
Contractor O Malley Jim Services; Lic. No.: 980528-B 432 WEST 3RD STREET      AZUSA, CA 91702
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/20/2022 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 11/16/2022 Partial Approval ANDEY CHAPARRO
PLUMBING-Rough 12/13/2022 Partial Approval COREY HUPP
Footing/Foundation/Slab 12/16/2022 Approved COREY HUPP
Pre-Inspection 1/24/2023 Approved COREY HUPP
Pre-Inspection 3/8/2023 Partial Approval COREY HUPP
Drywall Nailing 3/14/2023 Partial Approval COREY HUPP
BUILDING-Rough-Frame 4/19/2023 Approved COREY HUPP
Green Building Rough 4/19/2023 Approved COREY HUPP
Interior/Exterior Lathing 4/26/2023 Partial Approval COREY HUPP
Drywall Nailing 5/2/2023 Approved COREY HUPP
Shower Pan 5/2/2023 Approved COREY HUPP
Interior/Exterior Lathing 5/17/2023 Approved COREY HUPP
Final 7/26/2023 Corrections Issued COREY HUPP
Green Building Final 7/26/2023 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 7/26/2023 SGSOV Approved COREY HUPP
Smoke Detectors 7/26/2023 Approved COREY HUPP
Service/Power Release 8/2/2023 Approved COREY HUPP
Final 12/6/2023 Corrections Issued COREY HUPP
Green Building Final 12/6/2023 Conditional Approval COREY HUPP
Final 2/29/2024 OK to Issue CofO COREY HUPP
Green Building Final 2/29/2024 Approved COREY HUPP