3810 S RIDGELEY DR 90008

Certificate Information: 3810 S RIDGELEY DR 90008

Application / Permit
19014-10000-07162
Plan Check / Job No.
B19LA27486
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition to rear of (E) SFD and interior remodel.
Permit Issued
Issued on 6/17/2020
Issuing Office
Current Status
CofO Issued on 3/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/2/2020 HELEN NGUYEN
Corrections Issued 1/8/2020 HELEN NGUYEN
Applicant returned to address corrections 3/16/2020 HELEN NGUYEN
Plan Check Approved 5/18/2020 HELEN NGUYEN
Building Plans Picked Up 5/22/2020 APPLICANT
Issued 6/17/2020 APPLICANT
CofO in Progress 3/8/2021 DAVID FEILER
Permit Finaled 3/17/2021 DEROLD HAUFF
CofO Issued 3/17/2021 DEROLD HAUFF
Permit Finaled 3/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Drainage to Storm Drain Cleared 2/26/2020 TERRY PHAN
Eng Process Fee Ord 176,300 Cleared 2/26/2020 EMIL KYUPELYAN
GPI Written Notices Cleared 2/26/2020 HELEN NGUYEN
Grading Pre-Inspection Cleared 2/26/2020 PATRICK MISCHLICH

Contact Information

Contractor Molinar Construction; Lic. No.: 1024641-B 1132 SPENCE STREET      LOS ANGELES, CA 90023
Engineer Sarrami,, Gholamali F; Lic. No.: C43720 4942 HIGHLAND VIEW AVENUE      LOS ANGELES, CA 90041

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/18/2020 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 6/22/2020 Approved COREY HUPP
PLUMBING-Rough 6/29/2020 Partial Approval COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 7/20/2020 Partial Approval COREY HUPP
ELECTRICAL-Rough 7/29/2020 Partial Approval COREY HUPP
PLUMBING-Rough 7/29/2020 Partial Approval COREY HUPP
Shower Pan 8/3/2020 Approved SABAS ALONSO
BUILDING-Rough-Frame 8/7/2020 Approved COREY HUPP
Green Building Rough 8/7/2020 Approved COREY HUPP
Interior/Exterior Lathing 8/12/2020 Approved SABAS ALONSO
Insulation 8/18/2020 Approved COREY HUPP
Drywall Nailing 8/24/2020 Approved SABAS ALONSO
Final 10/30/2020 Partial Inspection DAVID FEILER
Green Building Final 10/30/2020 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 10/30/2020 SGSOV Approved DAVID FEILER
Smoke Detectors 10/30/2020 Corrections Issued DAVID FEILER
Final 12/2/2020 OK to Issue CofO DAVID FEILER
Smoke Detectors 12/2/2020 Approved DAVID FEILER