3810 S RIDGELEY DR 90008
Certificate Information: 3810 S RIDGELEY DR 90008
- Application / Permit
- 19014-10000-07162
- Plan Check / Job No.
- B19LA27486
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to rear of (E) SFD and interior remodel.
- Permit Issued
- Issued on 6/17/2020
- Issuing Office
- Current Status
- CofO Issued on 3/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | HELEN NGUYEN |
| Corrections Issued | 1/8/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 3/16/2020 | HELEN NGUYEN |
| Plan Check Approved | 5/18/2020 | HELEN NGUYEN |
| Building Plans Picked Up | 5/22/2020 | APPLICANT |
| Issued | 6/17/2020 | APPLICANT |
| CofO in Progress | 3/8/2021 | DAVID FEILER |
| Permit Finaled | 3/17/2021 | DEROLD HAUFF |
| CofO Issued | 3/17/2021 | DEROLD HAUFF |
| Permit Finaled | 3/17/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Drainage to Storm Drain | Cleared | 2/26/2020 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | EMIL KYUPELYAN |
| GPI Written Notices | Cleared | 2/26/2020 | HELEN NGUYEN |
| Grading Pre-Inspection | Cleared | 2/26/2020 | PATRICK MISCHLICH |
Contact Information
| Contractor | Molinar Construction; Lic. No.: 1024641-B | 1132 SPENCE STREET LOS ANGELES, CA 90023 |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/18/2020 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 6/22/2020 | Approved | COREY HUPP |
| PLUMBING-Rough | 6/29/2020 | Partial Approval | COREY HUPP |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2020 | Partial Approval | COREY HUPP |
| ELECTRICAL-Rough | 7/29/2020 | Partial Approval | COREY HUPP |
| PLUMBING-Rough | 7/29/2020 | Partial Approval | COREY HUPP |
| Shower Pan | 8/3/2020 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/7/2020 | Approved | COREY HUPP |
| Green Building Rough | 8/7/2020 | Approved | COREY HUPP |
| Interior/Exterior Lathing | 8/12/2020 | Approved | SABAS ALONSO |
| Insulation | 8/18/2020 | Approved | COREY HUPP |
| Drywall Nailing | 8/24/2020 | Approved | SABAS ALONSO |
| Final | 10/30/2020 | Partial Inspection | DAVID FEILER |
| Green Building Final | 10/30/2020 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 10/30/2020 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 10/30/2020 | Corrections Issued | DAVID FEILER |
| Final | 12/2/2020 | OK to Issue CofO | DAVID FEILER |
| Smoke Detectors | 12/2/2020 | Approved | DAVID FEILER |