8618 S SEPULVEDA BLVD 90045

Certificate Information: 8618 S SEPULVEDA BLVD 90045

Application / Permit
19014-10000-07143
Plan Check / Job No.
B19LA27427
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
ADD 4TH FLOOR (1840 SQFT/OFFICE ) AND CONVERT (E) ROOF TO OCCUPANCY ROOF DECK (735 SQFT), CORE + SHELL FOR 3 STORY MEDICAL OFFICE BUILDING. DEMO ON FLOORS 1-3 WITH NEW RESTROOMS. FACADE REMODEL. STRUCTURAL RETROFIT WITH NEW PILES, SLAB REPAIR, NEW PLANTERS AND CANOPIES AT GROUND FLOOR. EXTEND STAIR AND ELEVATOR SHAFTS TO NEW ROOF DECK (4TH FLOOR ). No change of use, Change type of construction from VB to IIB. see comment.
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 1/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 TSE MING HUANG
Corrections Issued 2/21/2020 TSE MING HUANG
Quality Review Completed 3/8/2020 STANLEY RAAP
Building Plans Picked Up 3/11/2020 APPLICANT
Disabled Access Plans Picked Up 3/13/2020 APPLICANT
Applicant returned to address corrections 10/6/2020 TSE MING HUANG
Applicant returned to address corrections 11/2/2020 TSE MING HUANG
Applicant returned to address corrections 3/19/2021 TSE MING HUANG
Green Plans Picked Up 3/23/2021 APPLICANT
Applicant returned to address corrections 4/22/2021 TSE MING HUANG
Applicant returned to address corrections 4/29/2021 TSE MING HUANG
Applicant returned to address corrections 5/4/2021 TSE MING HUANG
Applicant returned to address corrections 5/5/2021 TSE MING HUANG
Applicant returned to address corrections 5/14/2021 TSE MING HUANG
Applicant returned to address corrections 5/20/2021 TSE MING HUANG
Applicant returned to address corrections 5/26/2021 TSE MING HUANG
Applicant returned to address corrections 6/16/2021 TSE MING HUANG
Applicant returned to address corrections 8/4/2021 TSE MING HUANG
Plan Check Approved 8/24/2021 TSE MING HUANG
Issued 8/24/2021 APPLICANT
TCO Issued (Expire Date: 04-15-2026) 10/17/2025 DAVID TSAU
CofO in Progress 1/15/2026 DERRICK SPENCER
Permit Finaled 1/23/2026 DAVID TSAU
CofO Issued 1/23/2026 DAVID TSAU
Permit Finaled 1/23/2026 DAVID TSAU

Permit Application Clearance Information

Encroachment in public way Cleared 3/16/2020 ELENA LOPEZ
Permit Cleared 3/16/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 3/16/2020 JEANIE LAM
"D" conditions Cleared 3/18/2020 MAXFIELD VERMY
Specific Plan Cleared 7/2/2020 PETE EYRE
Hydrant and Access approval Cleared 7/6/2020 MATTHEW CRAIG
Green Code Cleared 3/23/2021 TSE MING HUANG
Sewer availability Cleared 5/7/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 5/11/2021 DENNIS BRAGIN
Work Adjacent to Public Way Cleared 5/12/2021 SAUL GARCIA
Low Impact Development Cleared 7/14/2021 ORVAL HERNANDEZ-MARCI
Building over 3-story or 36-ft Cleared 8/2/2021 CALOSHA APPROVED
DAS Clearance Cleared 8/17/2021 TSE MING HUANG
"Q" conditions Cleared 8/20/2021 DENZEL HENDERSON
Supp. Use District POD/CDO/TDO Cleared 8/20/2021 DENZEL HENDERSON

Contact Information

Architect , ; Lic. No.: C38840 750 VINE STREET      DENVER, CO 80206
Contractor K B White Construction; Lic. No.: 915958-B 17037 CHATSWORTH STREET   SUITE 203    GRANADA HILLS, CA 91344
Engineer Chakar,, Jean-Pierre M; Lic. No.: S6213 2011 OCEAN PARK BLVD APT B      SANTA MONICA, CA 90405
Engineer Vicente,, Ernesto Edgardo; Lic. No.: GE2302 17582 BRENT LANE      TUSTIN, CA 927801905

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/10/2021 Not Ready for Inspection GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/15/2021 Partial Approval GRANT WOODS
Footing/Foundation/Slab 9/15/2021 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 9/16/2021 Approved GRANT WOODS
Deputy Reinf. Concrete 9/17/2021 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 9/20/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 9/20/2021 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 9/21/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/21/2021 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/22/2021 Approved GRANT WOODS
Deputy Reinf. Concrete 9/22/2021 Approved GRANT WOODS
Deputy Drilled-In Anchors 9/23/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/23/2021 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 9/24/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/24/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 9/27/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 9/28/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 9/29/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 9/30/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 10/1/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 10/4/2021 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 10/5/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 10/5/2021 Conditional Approval GRANT WOODS
Deputy Drilled-In Anchors 10/6/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 10/6/2021 Conditional Approval TED RIES
Deputy Drilled-In Anchors 10/7/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 10/7/2021 Conditional Approval TED RIES
Deputy Drilled-In Anchors 10/8/2021 Conditional Approval TED RIES
Deputy Reinf. Concrete 10/8/2021 Conditional Approval TED RIES
Deputy Drilled-In Anchors 10/12/2021 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 10/12/2021 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 10/19/2021 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 10/20/2021 Conditional Approval TED RIES
Excavation/Setback/Form/Re-Bar 11/4/2021 Partial Approval GRANT WOODS
Footing/Foundation/Slab 11/4/2021 Partial Approval GRANT WOODS
Footing/Foundation/Slab 11/16/2021 Partial Approval NICK LAROCCA
Footing/Foundation/Slab 11/24/2021 Partial Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 12/6/2021 Not Ready for Inspection GRANT WOODS
Footing/Foundation/Slab 12/6/2021 Not Ready for Inspection GRANT WOODS
Footing/Foundation/Slab 12/17/2021 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 12/29/2021 Partial Approval GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Partial Approval GRANT WOODS
Footing/Foundation/Slab 1/5/2022 Partial Approval GRANT WOODS
Footing/Foundation/Slab 1/19/2022 Partial Approval GRANT WOODS
Footing/Foundation/Slab 1/26/2022 Partial Approval GRANT WOODS
Deputy Reinf. Concrete 1/28/2022 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 2/7/2022 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 2/11/2022 Not Ready for Inspection JOEY BUCHANAN
Footing/Foundation/Slab 2/17/2022 Partial Approval JOEY BUCHANAN
Footing/Foundation/Slab 3/4/2022 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 4/22/2022 Partial Approval JOEY BUCHANAN
Green Building Rough 5/4/2022 Approved DAVID TSAU
Reinforced Concrete Frame 5/4/2022 Partial Approval DAVID TSAU
Light Gage Steel Frame 5/26/2022 Corrections Issued JOEY BUCHANAN
Excavation/Setback/Form/Re-Bar 7/18/2022 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 7/29/2022 Not Ready for Inspection GRANT WOODS
Footing/Foundation/Slab 7/30/2022 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 8/11/2022 Conditional Approval GRANT WOODS
Footing/Foundation/Slab 8/12/2022 Approved DERRICK SPENCER
Pre-Inspection 8/29/2022 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/6/2022 Partial Approval ALAN NOVAK
Excavation/Setback/Form/Re-Bar 9/7/2022 Off-Hour Fees Due
Drywall Nailing 9/8/2022 Partial Approval GRANT WOODS
Light Gage Steel Frame 9/8/2022 Partial Approval GRANT WOODS
Excavation/Setback/Form/Re-Bar 9/12/2022 Partial Approval GRANT WOODS
Interior/Exterior Lathing 10/6/2022 Partial Approval GRANT WOODS
Deputy Steel/Welding 10/12/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 10/14/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 10/19/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 10/28/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 10/31/2022 Conditional Approval GRANT WOODS
Deputy Steel/Welding 11/4/2022 Conditional Approval GRANT WOODS
Structural Steel Frame 5/30/2023 Not Ready for Inspection GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 6/2/2023 Partial Approval GRANT WOODS
Light Gage Steel Frame 7/27/2023 Partial Inspection GRANT WOODS
Light Gage Steel Frame 7/28/2023 Partial Inspection GRANT WOODS
Drywall Nailing 12/5/2023 Not Ready for Inspection DAVID TSAU
Insulation 12/5/2023 Not Ready for Inspection DAVID TSAU
Light Gage Steel Frame 12/5/2023 Partial Inspection DAVID TSAU
Insulation 12/6/2023 Not Ready for Inspection DAVID TSAU
Drywall Nailing 2/16/2024 Not Ready for Inspection GRANT WOODS
Insulation 2/16/2024 Partial Approval GRANT WOODS
Pre-Inspection 2/16/2024 Not Ready for Inspection GRANT WOODS
Deputy Steel/Welding 3/4/2024 Partial Approval GRANT WOODS
Special/Order Compliance 3/11/2024 Partial Inspection GRANT WOODS
Special/Order Compliance 3/27/2024 Partial Approval GRANT WOODS
T-Bar Ceiling 4/15/2024 Not Ready for Inspection GRANT WOODS
T-Bar Ceiling 5/20/2024 Not Ready for Inspection GRANT WOODS
Special/Order Compliance 8/16/2024 Partial Inspection GRANT WOODS
Special/Order Compliance 9/10/2024 Corrections Issued GRANT WOODS
Special/Order Compliance 10/10/2024 Partial Approval GRANT WOODS
Special/Order Compliance 12/11/2024 Partial Inspection GRANT WOODS
Special/Order Compliance 12/26/2024 Partial Inspection GRANT WOODS
Special/Order Compliance 1/3/2025 Partial Approval GRANT WOODS
Grading Pre-Inspection 7/1/2025 Approved DERRICK SPENCER
Drywall Nailing 7/25/2025 Approved DERRICK SPENCER
Final 7/25/2025 Not Ready for Inspection DERRICK SPENCER
Green Building Final 7/25/2025 Approved DERRICK SPENCER
Reinforced Concrete Frame 7/25/2025 Approved DERRICK SPENCER
Reinforced Masonry Frame 7/25/2025 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 7/25/2025 SGSOV Approved DERRICK SPENCER
Smoke Detectors 7/25/2025 Approved DERRICK SPENCER
Final 8/8/2025 Not Ready for Inspection DERRICK SPENCER
Final 12/30/2025 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 12/30/2025 Partial Approval SCOTT SOBEL
Deputy Grading 1/7/2026 Approved DERRICK SPENCER
Final 1/15/2026 OK to Issue CofO DERRICK SPENCER