Footing/Foundation/Slab
|
9/10/2021
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
9/15/2021
|
Partial Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
9/15/2021
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
9/16/2021
|
Approved
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
9/17/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Drilled-In Anchors
|
9/20/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
9/20/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Drilled-In Anchors
|
9/21/2021
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
9/21/2021
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
9/22/2021
|
Approved
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
9/22/2021
|
Approved
|
GRANT WOODS
|
|
Deputy Drilled-In Anchors
|
9/23/2021
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
9/23/2021
|
Approved
|
DERRICK SPENCER
|
|
Deputy Drilled-In Anchors
|
9/24/2021
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
9/24/2021
|
Approved
|
DERRICK SPENCER
|
|
Deputy Reinf. Concrete
|
9/27/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
9/28/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
9/29/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
9/30/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
10/1/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
10/4/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Drilled-In Anchors
|
10/5/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
10/5/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Drilled-In Anchors
|
10/6/2021
|
Conditional Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
10/6/2021
|
Conditional Approval
|
TED RIES
|
|
Deputy Drilled-In Anchors
|
10/7/2021
|
Conditional Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
10/7/2021
|
Conditional Approval
|
TED RIES
|
|
Deputy Drilled-In Anchors
|
10/8/2021
|
Conditional Approval
|
TED RIES
|
|
Deputy Reinf. Concrete
|
10/8/2021
|
Conditional Approval
|
TED RIES
|
|
Deputy Drilled-In Anchors
|
10/12/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
10/12/2021
|
Conditional Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
10/19/2021
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
10/20/2021
|
Conditional Approval
|
TED RIES
|
|
Excavation/Setback/Form/Re-Bar
|
11/4/2021
|
Partial Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
11/4/2021
|
Partial Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
11/16/2021
|
Partial Approval
|
NICK LAROCCA
|
|
Footing/Foundation/Slab
|
11/24/2021
|
Partial Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/6/2021
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
12/6/2021
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
12/17/2021
|
Partial Approval
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
12/29/2021
|
Partial Approval
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/5/2022
|
Partial Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
1/5/2022
|
Partial Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
1/19/2022
|
Partial Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
1/26/2022
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Reinf. Concrete
|
1/28/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
2/7/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
2/11/2022
|
Not Ready for Inspection
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
2/17/2022
|
Partial Approval
|
JOEY BUCHANAN
|
|
Footing/Foundation/Slab
|
3/4/2022
|
Partial Approval
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
4/22/2022
|
Partial Approval
|
JOEY BUCHANAN
|
|
Green Building Rough
|
5/4/2022
|
Approved
|
DAVID TSAU
|
|
Reinforced Concrete Frame
|
5/4/2022
|
Partial Approval
|
DAVID TSAU
|
|
Light Gage Steel Frame
|
5/26/2022
|
Corrections Issued
|
JOEY BUCHANAN
|
|
Excavation/Setback/Form/Re-Bar
|
7/18/2022
|
Partial Approval
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
7/29/2022
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
7/30/2022
|
Partial Approval
|
DERRICK SPENCER
|
|
Deputy Steel/Welding
|
8/11/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Footing/Foundation/Slab
|
8/12/2022
|
Approved
|
DERRICK SPENCER
|
|
Pre-Inspection
|
8/29/2022
|
Partial Approval
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
9/6/2022
|
Partial Approval
|
ALAN NOVAK
|
|
Excavation/Setback/Form/Re-Bar
|
9/7/2022
|
Off-Hour Fees Due
|
|
|
Drywall Nailing
|
9/8/2022
|
Partial Approval
|
GRANT WOODS
|
|
Light Gage Steel Frame
|
9/8/2022
|
Partial Approval
|
GRANT WOODS
|
|
Excavation/Setback/Form/Re-Bar
|
9/12/2022
|
Partial Approval
|
GRANT WOODS
|
|
Interior/Exterior Lathing
|
10/6/2022
|
Partial Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/12/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/14/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/19/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/28/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
10/31/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
11/4/2022
|
Conditional Approval
|
GRANT WOODS
|
|
Structural Steel Frame
|
5/30/2023
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/2/2023
|
Partial Approval
|
GRANT WOODS
|
|
Light Gage Steel Frame
|
7/27/2023
|
Partial Inspection
|
GRANT WOODS
|
|
Light Gage Steel Frame
|
7/28/2023
|
Partial Inspection
|
GRANT WOODS
|
|
Drywall Nailing
|
12/5/2023
|
Not Ready for Inspection
|
DAVID TSAU
|
|
Insulation
|
12/5/2023
|
Not Ready for Inspection
|
DAVID TSAU
|
|
Light Gage Steel Frame
|
12/5/2023
|
Partial Inspection
|
DAVID TSAU
|
|
Insulation
|
12/6/2023
|
Not Ready for Inspection
|
DAVID TSAU
|
|
Drywall Nailing
|
2/16/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Insulation
|
2/16/2024
|
Partial Approval
|
GRANT WOODS
|
|
Pre-Inspection
|
2/16/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Deputy Steel/Welding
|
3/4/2024
|
Partial Approval
|
GRANT WOODS
|
|
Special/Order Compliance
|
3/11/2024
|
Partial Inspection
|
GRANT WOODS
|
|
Special/Order Compliance
|
3/27/2024
|
Partial Approval
|
GRANT WOODS
|
|
T-Bar Ceiling
|
4/15/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
T-Bar Ceiling
|
5/20/2024
|
Not Ready for Inspection
|
GRANT WOODS
|
|
Special/Order Compliance
|
8/16/2024
|
Partial Inspection
|
GRANT WOODS
|
|
Special/Order Compliance
|
9/10/2024
|
Corrections Issued
|
GRANT WOODS
|
|
Special/Order Compliance
|
10/10/2024
|
Partial Approval
|
GRANT WOODS
|
|
Special/Order Compliance
|
12/11/2024
|
Partial Inspection
|
GRANT WOODS
|
|
Special/Order Compliance
|
12/26/2024
|
Partial Inspection
|
GRANT WOODS
|
|
Special/Order Compliance
|
1/3/2025
|
Partial Approval
|
GRANT WOODS
|
|
Grading Pre-Inspection
|
7/1/2025
|
Approved
|
DERRICK SPENCER
|
|
Drywall Nailing
|
7/25/2025
|
Approved
|
DERRICK SPENCER
|
|
Final
|
7/25/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Green Building Final
|
7/25/2025
|
Approved
|
DERRICK SPENCER
|
|
Reinforced Concrete Frame
|
7/25/2025
|
Approved
|
DERRICK SPENCER
|
|
Reinforced Masonry Frame
|
7/25/2025
|
Approved
|
DERRICK SPENCER
|
|
SGSOV-Seismic Gas S/O Valve
|
7/25/2025
|
SGSOV Approved
|
DERRICK SPENCER
|
|
Smoke Detectors
|
7/25/2025
|
Approved
|
DERRICK SPENCER
|
|
Final
|
8/8/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Final
|
12/30/2025
|
Not Ready for Inspection
|
DERRICK SPENCER
|
|
Special/Order Compliance
|
12/30/2025
|
Partial Approval
|
SCOTT SOBEL
|
|
Deputy Grading
|
1/7/2026
|
Approved
|
DERRICK SPENCER
|
|
Final
|
1/15/2026
|
OK to Issue CofO
|
DERRICK SPENCER
|