2614 S CLYDE AVE 90016

Certificate Information: 2614 S CLYDE AVE 90016

Application / Permit
19014-10000-07116
Plan Check / Job No.
B19LA27351
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1.) INTERIOR REMODEL & 2ND STORY ADDITON TO AN (E) 1,282 SF S.F.D. 1 OF 2
Permit Issued
Issued on 8/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2020 ZAW HAN
Corrections Issued 2/3/2020 ZAW HAN
Quality Review Completed 2/18/2020 HERNAN ARREOLA
Building Plans Picked Up 2/21/2020 APPLICANT
Green Plans Picked Up 5/4/2020 APPLICANT
Applicant returned to address corrections 6/8/2020 ZAW HAN
Applicant returned to address corrections 6/12/2020 ZAW HAN
Plan Check Approved 6/23/2020 ZAW HAN
Issued 8/6/2020 APPLICANT
CofO in Progress 8/21/2021 SCOTT FINNILA
No Progress 9/8/2021 RUBEN SALAS
CofO in Progress 9/16/2021 RUBEN SALAS
Permit Finaled 9/21/2021 DEROLD HAUFF
CofO Issued 9/21/2021 DEROLD HAUFF
Permit Finaled 9/21/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/12/2020 EMIL KYUPELYAN
Permit Cleared 3/12/2020 EMIL KYUPELYAN
Sewer availability Cleared 3/12/2020 EMIL KYUPELYAN
Green Code Cleared 4/17/2020 DONALD CRICHLOW
Low Impact Development Cleared 5/21/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 5/27/2020 RENZ SORIANO

Contact Information

Contractor Primary Homes; Lic. No.: 805314-B 13351 RIVERSIDE DRIVE UNIT 473      SHERMAN OAKS, CA 91423
Engineer Darvasan-Stanciu,, George; Lic. No.: L7884 825 E COLTON AVE      REDLANDS, CA 92374
Engineer Durand,, Paul Henri; Lic. No.: S4222 611 N G ST      OXNARD, CA 93030

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/18/2020 Partial Inspection DAVID CHAN
Sewer 8/26/2020 Partial Approval DAVID CHAN
Underground Mechanical 8/26/2020 Approved DAVID CHAN
Footing/Foundation/Slab 9/2/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 9/29/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 11/12/2020 Approved DAVID CHAN
ELECTRICAL-Rough 11/18/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 11/23/2020 Corrections Issued DAVID CHAN
Green Building Rough 11/23/2020 Approved DAVID CHAN
HVAC-Rough 11/23/2020 Approved DAVID CHAN
MERV13>=Rough 11/23/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 12/8/2020 Conditional Approval DAVID CHAN
Interior/Exterior Lathing 12/8/2020 Conditional Approval DAVID CHAN
Shower Pan 12/8/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 12/15/2020 Approved DAVID CHAN
Insulation 12/21/2020 Approved DAVID CHAN
Drywall Nailing 12/28/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 1/12/2021 Partial Approval DAVID CHAN
ELECTRICAL-Final 7/12/2021 Corrections Issued STUART CHAPMAN
HVAC-Final 7/12/2021 Corrections Issued STUART CHAPMAN
PLUMBING-Final 7/12/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 7/16/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 7/16/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 7/16/2021 Approved CHRISTOPHER DELLEFIELD
Service/Power Release 7/16/2021 Approved CHRISTOPHER DELLEFIELD
Final 7/28/2021 Partial Approval SCOTT FINNILA
Green Building Final 7/28/2021 Approved SCOTT FINNILA
HVAC-Final 7/28/2021 Approved SCOTT FINNILA
MERV13>=Final 7/28/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 7/28/2021 SGSOV Approved SCOTT FINNILA
Smoke Detectors 7/28/2021 Approved SCOTT FINNILA
Final 8/6/2021 Corrections Issued SCOTT FINNILA
Final 8/20/2021 OK to Issue CofO SCOTT FINNILA