1631 S DURANGO AVE 90035

Certificate Information: 1631 S DURANGO AVE 90035

Application / Permit
19014-10000-07111
Plan Check / Job No.
B19LA27333
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SINGLE FAMILY DWELLING WITH DETACHED 2 CAR GARAGE
Permit Issued
Issued on 8/14/2020
Issuing Office
Current Status
CofO Issued on 11/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/23/2020 HANS SANTIAGO
Corrections Issued 1/28/2020 HANS SANTIAGO
Quality Review Completed 1/30/2020 JASON HEALEY
Applicant returned to address corrections 3/20/2020 HANS SANTIAGO
Building Plans Picked Up 3/25/2020 APPLICANT
Applicant returned to address corrections 5/7/2020 HANS SANTIAGO
Green Plans Picked Up 5/7/2020 APPLICANT
Applicant returned to address corrections 5/12/2020 HANS SANTIAGO
Applicant returned to address corrections 6/22/2020 HANS SANTIAGO
Plan Check Approved 6/24/2020 ANDREW SANTIAGO
Issued 8/14/2020 APPLICANT
CofO in Progress 11/23/2021 EVAN COOPER
Permit Finaled 11/30/2021 KENNETH NAGLE
CofO Issued 11/30/2021 KENNETH NAGLE
Permit Finaled 11/30/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/2/2020 JAMES MORALEZ
Hydrant and Access approval Cleared 3/2/2020 JEREMY CARTER
Low Impact Development Cleared 3/2/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 3/2/2020 JAMES MORALEZ
Green Code Cleared 3/3/2020 VIVIAN LAO
Work Adjacent to Public Way Cleared 5/6/2020 SAUL GARCIA
Address approval Cleared 6/4/2020 DINAH GARIN
Permit Cleared 6/4/2020 DINAH GARIN
Sewer availability Cleared 6/4/2020 DINAH GARIN
GPI Written Notices Cleared 6/22/2020 ANDREW SANTIAGO
Grading Pre-Inspection Cleared 6/22/2020 ANDREW SANTIAGO

Contact Information

Architect Leishman,, Thomas Edward; Lic. No.: C15059 326 PASEO DE LA PLAYA UNIT B      REDONDO BEACH, CA 90277
Contractor Refined Projects Construction & Design; Lic. No.: 1033436-B 3626 8TH AVENUE      LOS ANGELES, CA 90018
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/18/2020 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 8/25/2020 Approved EVAN COOPER
Deputy Reinf. Concrete 8/27/2020 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 9/8/2020 Partial Approval EVAN COOPER
METHANE-Barrier 9/8/2020 Approved EVAN COOPER
METHANE-Subgrade 9/8/2020 Approved EVAN COOPER
BUILDING-Rough-Frame 9/24/2020 Partial Approval EVAN COOPER
Green Building Rough 9/24/2020 Not Ready for Inspection EVAN COOPER
METHANE-Rough 9/24/2020 Approved EVAN COOPER
Verify Sprinkler Sign Off 9/24/2020 Not Ready for Inspection EVAN COOPER
Footing/Foundation/Slab 11/12/2020 Partial Approval EVAN COOPER
Footing/Foundation/Slab 11/30/2020 Approved EVAN COOPER
HVAC-Rough 12/15/2020 Corrections Issued EVAN COOPER
PLUMBING-Rough 12/15/2020 Corrections Issued EVAN COOPER
Deputy Wood Construction 12/21/2020 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 1/11/2021 Approved EVAN COOPER
HVAC-Rough 1/11/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 1/11/2021 Approved EVAN COOPER
Shower Pan 1/11/2021 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Approved EVAN COOPER
Wood Frame 1/21/2021 Corrections Issued EVAN COOPER
Insulation 2/9/2021 Approved EVAN COOPER
Interior/Exterior Lathing 2/9/2021 Approved EVAN COOPER
Drywall Nailing 2/22/2021 Approved EVAN COOPER
Green Building Rough 2/22/2021 Approved EVAN COOPER
Gas Test 6/3/2021 Approved EVAN COOPER
ELECTRICAL-Final 9/15/2021 Approved EVAN COOPER
Final 9/15/2021 Corrections Issued EVAN COOPER
HVAC-Final 9/15/2021 Approved EVAN COOPER
PLUMBING-Final 9/15/2021 Approved EVAN COOPER
BUILDING-Rough-Frame 10/14/2021 Approved EVAN COOPER
Final 10/14/2021 Corrections Issued EVAN COOPER
Green Building Final 10/14/2021 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Approved EVAN COOPER
Service/Power Release 10/14/2021 Not Ready for Inspection EVAN COOPER
Smoke Detectors 10/14/2021 Approved EVAN COOPER
Verify Sprinkler Sign Off 10/14/2021 Approved EVAN COOPER
Final 11/10/2021 Corrections Issued EVAN COOPER
Service/Power Release 11/10/2021 Not Ready for Inspection EVAN COOPER
Final 11/23/2021 OK to Issue CofO EVAN COOPER
Service/Power Release 11/23/2021 Approved EVAN COOPER