609 S SANTA FE AVE 90021
Certificate Information: 609 S SANTA FE AVE 90021
- Application / Permit
- 19014-10000-07098
- Plan Check / Job No.
- B19LA27305
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- ADD MECHANICAL EQUIPMENT STORAGE MEZZANINE AND TENANT IMPROVEMENT/ CHANGE OF USE FROM FOOD PRODUCT MANUFACTURING TO WAREHOUSE/OFFICE . URM BUILDING. RE-STUCCO THE EXTERIOR
- Permit Issued
- Issued on 8/3/2020
- Issuing Office
- Current Status
- CofO Issued on 5/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 1/28/2020 | ARSALAN SHABESTARI |
| Disabled Access Plans Picked Up | 1/28/2020 | APPLICANT |
| Quality Review Completed | 2/7/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 2/14/2020 | APPLICANT |
| Applicant returned to address corrections | 4/16/2020 | HERNAN ARREOLA |
| Applicant returned to address corrections | 5/18/2020 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 7/10/2020 | APPLICANT |
| Plan Check Approved | 7/16/2020 | ARSALAN SHABESTARI |
| Issued | 8/3/2020 | APPLICANT |
| CofO in Progress | 4/29/2021 | KATY RAMIREZ |
| CofO in Progress | 4/29/2021 | KATY RAMIREZ |
| Permit Finaled | 5/3/2021 | DAVID TSAU |
| CofO Issued | 5/3/2021 | DAVID TSAU |
| Permit Finaled | 5/3/2021 | DAVID TSAU |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/4/2020 | THOMAS LANG |
| Sewer availability | Cleared | 3/4/2020 | THOMAS LANG |
| ZA Case | Cleared | 3/4/2020 | RICHARD REASER |
| ZA Case | Cleared | 3/4/2020 | RICHARD REASER |
| ZI | Cleared | 3/4/2020 | RICHARD REASER |
| Green Code | Cleared | 3/12/2020 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 7/2/2020 | RONALD ALLEN |
Contact Information
| Architect | Sullivan,, Scott Bernard; Lic. No.: C33139 | 828 11TH STREET # 5 SANTA MONICA, CA 90403 |
| Contractor | A G & B Construction Inc; Lic. No.: 891681-B | 923 BALDWIN PARK BLVD BALDWIN PARK, CA 91706 |
| Engineer | Cosentino,, Joseph; Lic. No.: C53176 | 820 ISABELLA MONTEREY PARK, CA 91754 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 8/20/2020 | Not Ready for Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 8/20/2020 | Not Ready for Inspection | LANNY MERRICK |
| METHANE-Barrier | 8/20/2020 | Not Ready for Inspection | LANNY MERRICK |
| METHANE-Subgrade | 8/20/2020 | Not Ready for Inspection | LANNY MERRICK |
| Wall Anchors | 8/20/2020 | Not Ready for Inspection | LANNY MERRICK |
| Drywall Nailing | 10/14/2020 | Not Ready for Inspection | LANNY MERRICK |
| Light Gage Steel Frame | 10/14/2020 | Partial Approval | LANNY MERRICK |
| Drywall Nailing | 10/16/2020 | Partial Approval | RONALD PACHECO |
| Final | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| Footing/Foundation/Slab | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Final | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| Green Building Rough | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Barrier | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Final | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Rough | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| METHANE-Subgrade | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| Reinforced Masonry Frame | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| SGSOV-Seismic Gas S/O Valve | 3/4/2021 | SGSOV Not Ready | RONALD PACHECO |
| Smoke Detectors | 3/4/2021 | Not Ready for Inspection | RONALD PACHECO |
| Final | 4/19/2021 | Corrections Issued | KATY RAMIREZ |
| Footing/Foundation/Slab | 4/19/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Final | 4/19/2021 | Not Ready for Inspection | KATY RAMIREZ |
| Green Building Rough | 4/19/2021 | Approved | KATY RAMIREZ |
| METHANE-Barrier | 4/19/2021 | Approved | KATY RAMIREZ |
| METHANE-Final | 4/19/2021 | Approved | KATY RAMIREZ |
| METHANE-Rough | 4/19/2021 | Approved | KATY RAMIREZ |
| METHANE-Subgrade | 4/19/2021 | Approved | KATY RAMIREZ |
| Reinforced Masonry Frame | 4/19/2021 | Not Ready for Inspection | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/19/2021 | SGSOV Not Ready | KATY RAMIREZ |
| Smoke Detectors | 4/19/2021 | Approved | KATY RAMIREZ |
| Wood Frame | 4/21/2021 | Approved | KATY RAMIREZ |
| Final | 4/23/2021 | Partial Approval | KATY RAMIREZ |
| Footing/Foundation/Slab | 4/23/2021 | Approved | KATY RAMIREZ |
| Green Building Final | 4/23/2021 | Approved | KATY RAMIREZ |
| Reinforced Masonry Frame | 4/23/2021 | Approved | KATY RAMIREZ |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV No Gas | KATY RAMIREZ |
| Final | 4/29/2021 | OK to Issue CofO | KATY RAMIREZ |