609 S SANTA FE AVE 90021

Certificate Information: 609 S SANTA FE AVE 90021

Application / Permit
19014-10000-07098
Plan Check / Job No.
B19LA27305
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
ADD MECHANICAL EQUIPMENT STORAGE MEZZANINE AND TENANT IMPROVEMENT/ CHANGE OF USE FROM FOOD PRODUCT MANUFACTURING TO WAREHOUSE/OFFICE . URM BUILDING. RE-STUCCO THE EXTERIOR
Permit Issued
Issued on 8/3/2020
Issuing Office
Current Status
CofO Issued on 5/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/24/2020 ARSALAN SHABESTARI
Corrections Issued 1/28/2020 ARSALAN SHABESTARI
Disabled Access Plans Picked Up 1/28/2020 APPLICANT
Quality Review Completed 2/7/2020 HERNAN ARREOLA
Building Plans Picked Up 2/14/2020 APPLICANT
Applicant returned to address corrections 4/16/2020 HERNAN ARREOLA
Applicant returned to address corrections 5/18/2020 ARSALAN SHABESTARI
Green Plans Picked Up 7/10/2020 APPLICANT
Plan Check Approved 7/16/2020 ARSALAN SHABESTARI
Issued 8/3/2020 APPLICANT
CofO in Progress 4/29/2021 KATY RAMIREZ
CofO in Progress 4/29/2021 KATY RAMIREZ
Permit Finaled 5/3/2021 DAVID TSAU
CofO Issued 5/3/2021 DAVID TSAU
Permit Finaled 5/3/2021 DAVID TSAU

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/4/2020 THOMAS LANG
Sewer availability Cleared 3/4/2020 THOMAS LANG
ZA Case Cleared 3/4/2020 RICHARD REASER
ZA Case Cleared 3/4/2020 RICHARD REASER
ZI Cleared 3/4/2020 RICHARD REASER
Green Code Cleared 3/12/2020 DONALD CRICHLOW
DAS Clearance Cleared 7/2/2020 RONALD ALLEN

Contact Information

Architect Sullivan,, Scott Bernard; Lic. No.: C33139 828 11TH STREET # 5      SANTA MONICA, CA 90403
Contractor A G & B Construction Inc; Lic. No.: 891681-B 923 BALDWIN PARK BLVD      BALDWIN PARK, CA 91706
Engineer Cosentino,, Joseph; Lic. No.: C53176 820 ISABELLA      MONTEREY PARK, CA 91754

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 8/20/2020 Not Ready for Inspection LANNY MERRICK
Footing/Foundation/Slab 8/20/2020 Not Ready for Inspection LANNY MERRICK
METHANE-Barrier 8/20/2020 Not Ready for Inspection LANNY MERRICK
METHANE-Subgrade 8/20/2020 Not Ready for Inspection LANNY MERRICK
Wall Anchors 8/20/2020 Not Ready for Inspection LANNY MERRICK
Drywall Nailing 10/14/2020 Not Ready for Inspection LANNY MERRICK
Light Gage Steel Frame 10/14/2020 Partial Approval LANNY MERRICK
Drywall Nailing 10/16/2020 Partial Approval RONALD PACHECO
Final 3/4/2021 Not Ready for Inspection RONALD PACHECO
Footing/Foundation/Slab 3/4/2021 Not Ready for Inspection RONALD PACHECO
Green Building Final 3/4/2021 Not Ready for Inspection RONALD PACHECO
Green Building Rough 3/4/2021 Not Ready for Inspection RONALD PACHECO
METHANE-Barrier 3/4/2021 Not Ready for Inspection RONALD PACHECO
METHANE-Final 3/4/2021 Not Ready for Inspection RONALD PACHECO
METHANE-Rough 3/4/2021 Not Ready for Inspection RONALD PACHECO
METHANE-Subgrade 3/4/2021 Not Ready for Inspection RONALD PACHECO
Reinforced Masonry Frame 3/4/2021 Not Ready for Inspection RONALD PACHECO
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Not Ready RONALD PACHECO
Smoke Detectors 3/4/2021 Not Ready for Inspection RONALD PACHECO
Final 4/19/2021 Corrections Issued KATY RAMIREZ
Footing/Foundation/Slab 4/19/2021 Not Ready for Inspection KATY RAMIREZ
Green Building Final 4/19/2021 Not Ready for Inspection KATY RAMIREZ
Green Building Rough 4/19/2021 Approved KATY RAMIREZ
METHANE-Barrier 4/19/2021 Approved KATY RAMIREZ
METHANE-Final 4/19/2021 Approved KATY RAMIREZ
METHANE-Rough 4/19/2021 Approved KATY RAMIREZ
METHANE-Subgrade 4/19/2021 Approved KATY RAMIREZ
Reinforced Masonry Frame 4/19/2021 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 4/19/2021 Approved KATY RAMIREZ
Wood Frame 4/21/2021 Approved KATY RAMIREZ
Final 4/23/2021 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 4/23/2021 Approved KATY RAMIREZ
Green Building Final 4/23/2021 Approved KATY RAMIREZ
Reinforced Masonry Frame 4/23/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 4/23/2021 SGSOV No Gas KATY RAMIREZ
Final 4/29/2021 OK to Issue CofO KATY RAMIREZ