551 N BUNDY DR 90049
Certificate Information: 551 N BUNDY DR 90049
- Application / Permit
- 19014-10000-07093
- Plan Check / Job No.
- B19LA27290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO AND REMODEL OF EXISTING SINGLE FAMILY DWELLING W/ATT GARAGE.
- Permit Issued
- Issued on 4/12/2021
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/14/2020 | MANUEL MONTUFAR |
| Corrections Issued | 1/27/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 1/28/2020 | JASON HEALEY |
| Building Plans Picked Up | 1/30/2020 | APPLICANT |
| Green Plans Picked Up | 8/4/2020 | APPLICANT |
| Applicant returned to address corrections | 8/26/2020 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 10/15/2020 | MANUEL MONTUFAR |
| Applicant returned to address corrections | 12/28/2020 | MANUEL MONTUFAR |
| Plan Check Approved | 3/26/2021 | MANUEL MONTUFAR |
| No Progress | 3/26/2021 | MANUEL MONTUFAR |
| Plan Check Approved | 3/26/2021 | MANUEL MONTUFAR |
| Issued | 4/12/2021 | APPLICANT |
| CofO in Progress | 3/17/2023 | CARLOS MATAMOROS |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
| CofO Issued | 3/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 2/3/2020 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 2/3/2020 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 2/3/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 2/3/2020 | ERIK BEASLEY |
| Low Impact Development | Cleared | 3/17/2020 | MITESH PATEL |
| Green Code | Cleared | 4/1/2020 | VIVIAN LAO |
| GPI Written Notices | Cleared | 8/26/2020 | JASON HEALEY |
| Grading Pre-Inspection | Cleared | 8/26/2020 | JASON HEALEY |
| Miscellaneous | Cleared | 3/22/2021 | MAHELET GEBEYHU |
| Roof/Waste drainage to street | Cleared | 3/22/2021 | MAHELET GEBEYHU |
| Miscellaneous | Cleared | 3/24/2021 | MAHELET GEBEYHU |
Contact Information
| Architect | Diaz,, Arminda C; Lic. No.: C28977 | 5027 ALMADEN DR LOS ANGELES, CA 90042 |
| Contractor | Owner-Builder | , |
| Engineer | Kevin, Mitchell Towers; Lic. No.: S6625 | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/15/2021 | Approved | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 7/15/2021 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/16/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 8/16/2021 | Partial Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 12/15/2021 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2022 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 1/6/2022 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 1/13/2022 | Partial Approval | CARLOS MATAMOROS |
| Gas Test | 1/13/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 1/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/13/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 1/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Wood Frame | 1/13/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/4/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 2/4/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/4/2022 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 2/4/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 2/28/2022 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 2/28/2022 | Partial Approval | CARLOS MATAMOROS |
| Structural Steel Frame | 2/28/2022 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 2/28/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 3/4/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 3/4/2022 | Approved | CARLOS MATAMOROS |
| Insulation | 3/4/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 4/11/2022 | Approved | CARLOS MATAMOROS |
| Shower Pan | 4/11/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 4/18/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 6/15/2022 | Approved | CARLOS MATAMOROS |
| Gas Test | 9/8/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/8/2022 | Approved | CARLOS MATAMOROS |
| Underground Mechanical | 9/8/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 11/10/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 11/14/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 11/29/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 11/29/2022 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 11/29/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 11/29/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 11/29/2022 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 11/29/2022 | Approved | CARLOS MATAMOROS |
| Final | 3/17/2023 | OK to Issue CofO | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 3/17/2023 | Approved | CARLOS MATAMOROS |
| Green Building Final | 3/17/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 3/17/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 3/17/2023 | Approved | CARLOS MATAMOROS |