2725 S STONER AVE 90064

Certificate Information: 2725 S STONER AVE 90064

Application / Permit
19014-10000-07076
Plan Check / Job No.
B19LA27255
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRST & SECOND STORY ADDTION AND INTERIOR REMODEL TO THE EXISTING 29'X37' ONE STORY, TYPE V SINGLE FAMILY DWELLING.
Permit Issued
Issued on 11/5/2020
Issuing Office
Current Status
CofO Issued on 6/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/26/2019 APPLICANT
Assigned to Plan Check Engineer 1/14/2020 DANIEL SANJUAN
Corrections Issued 1/22/2020 DANIEL SANJUAN
Green Plans Picked Up 1/22/2020 APPLICANT
Quality Review Completed 1/23/2020 JASON HEALEY
Building Plans Picked Up 1/28/2020 APPLICANT
Plan Check Approved 9/30/2020 DANIEL SANJUAN
Issued 11/5/2020 APPLICANT
CofO in Progress 5/30/2023 KENNETH NAGLE
Permit Finaled 6/1/2023 DANIEL ORRANTE
CofO Issued 6/1/2023 DANIEL ORRANTE
Permit Finaled 6/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/20/2020 JUAN ASHTON
Sewer availability Cleared 2/20/2020 JUAN ASHTON
Low Impact Development Cleared 5/27/2020 MARTIN FRAGOSO
Green Code Cleared 6/25/2020 JASON HEALEY
Roof/Waste drainage to street Cleared 7/15/2020 DINAH GARIN
Hydrant and Access approval Cleared 9/24/2020 KURT CORRAL

Contact Information

Architect Adams,, Lauren Amanda; Lic. No.: C30146 8695 WASHINGTON BLVD SUITE 205      CULVER CITY, CA 90232
Contractor Letter Four Inc; Lic. No.: 1028949-B 8695 WASHINGTON BLVD      CULVER CITY, CA 90232
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/10/2020 Approved EVAN COOPER
Wood Frame 11/24/2020 Partial Approval RICHARD ROBLES
PLUMBING-Rough 12/1/2020 Corrections Issued RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Approved RICHARD ROBLES
PLUMBING-Rough 12/3/2020 Approved RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 12/14/2020 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/23/2020 Corrections Issued RICHARD ROBLES
Deputy Wood Construction 1/5/2021 Conditional Approval RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 1/5/2021 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 1/15/2021 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/20/2021 Corrections Issued EVAN COOPER
PLUMBING-Rough 1/20/2021 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 1/26/2021 Approved RICHARD ROBLES
HVAC-Rough 1/26/2021 Corrections Issued RICHARD ROBLES
BUILDING-Rough-Frame 2/4/2021 Not Ready for Inspection KENNETH NAGLE
Green Building Rough 2/4/2021 Not Ready for Inspection KENNETH NAGLE
Rough-Elec/Plmb/HVAC 2/4/2021 Not Ready for Inspection KENNETH NAGLE
Rough-Elec/Plmb/HVAC 2/8/2021 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 2/10/2021 Approved RICHARD ROBLES
Green Building Rough 2/10/2021 Approved RICHARD ROBLES
Rough-Elec/Plmb/HVAC 2/10/2021 Approved RICHARD ROBLES
Gas Test 2/26/2021 Approved RICHARD ROBLES
Interior/Exterior Lathing 2/26/2021 Not Ready for Inspection RICHARD ROBLES
Shower Pan 2/26/2021 Approved RICHARD ROBLES
Interior/Exterior Lathing 3/3/2021 Approved RICHARD ROBLES
Insulation 4/7/2021 Approved OGANES TARAKHCHYAN
Drywall Nailing 4/19/2021 Approved ASHLEY THOMPSON
Pre-Inspection 4/19/2021 Approved RYAN SALAZAR
Final 12/8/2021 Corrections Issued JOHNNY MIRANDA
Green Building Final 12/8/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 12/8/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 12/8/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 3/8/2023 SGSOV Not Ready JOHNNY MIRANDA
Final 5/8/2023 Conditional Approval JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/8/2023 SGSOV Approved JOHNNY MIRANDA