7438 W 81ST ST 90045

Certificate Information: 7438 W 81ST ST 90045

Application / Permit
19014-10000-07066
Plan Check / Job No.
B19LA27195
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Garage conversion to 27.4' X 18.8' IRR SHAPED 2-STORY ADU per AB 494 and SB 229. INCLUDES GYM AND OFFICE SPACE.
Permit Issued
Issued on 2/25/2021
Issuing Office
Current Status
CofO Issued on 1/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/14/2020 CRYSTEL MAALOUF
Corrections Issued 1/17/2020 CRYSTEL MAALOUF
Quality Review Completed 1/23/2020 JASON HEALEY
Building Plans Picked Up 1/28/2020 APPLICANT
Green Plans Picked Up 7/17/2020 APPLICANT
Applicant returned to address corrections 7/27/2020 CRYSTEL MAALOUF
Plan Check Approved 9/2/2020 CRYSTEL MAALOUF
Issued 2/25/2021 APPLICANT
CofO in Progress 12/30/2021 BOBBY KEY
Permit Finaled 1/4/2022 DANIEL ORRANTE
CofO Issued 1/4/2022 DANIEL ORRANTE
Permit Finaled 1/4/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/13/2020 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 3/13/2020 ROSA SILVA
Sewer availability Cleared 3/13/2020 ROSA SILVA
Specific Plan Cleared 4/1/2020 PEDRO AYALA
Construction near power lines Cleared 5/7/2020 RIDWAN HARDY
Construction within easement Cleared 5/7/2020 RIDWAN HARDY
Green Code Cleared 7/16/2020 CRYSTEL MAALOUF
Low Impact Development Cleared 8/10/2020 ROBIN YAMADA
Stormwater Pollution Mitigatn Cleared 8/10/2020 ROBIN YAMADA
GPI Written Notices Cleared 8/13/2020 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 8/13/2020 CRYSTEL MAALOUF
Roof/Waste drainage to street Cleared 8/26/2020 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Azarbin,, Hamid Reza; Lic. No.: C64515 22655 COVELLO ST      WEST HILLS, CA 91307

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/3/2021 Conditional Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 3/4/2021 Corrections Issued JUAN VALENZUELA
Footing/Foundation/Slab 3/4/2021 Not Ready for Inspection JUAN VALENZUELA
METHANE-Barrier 3/4/2021 Not Ready for Inspection JUAN VALENZUELA
METHANE-Subgrade 3/4/2021 Corrections Issued JUAN VALENZUELA
Underground Mechanical 3/4/2021 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/12/2021 Approved BRENDAN LOONEY
Footing/Foundation/Slab 4/12/2021 Approved BRENDAN LOONEY
METHANE-Barrier 4/12/2021 Approved BRENDAN LOONEY
METHANE-Subgrade 4/12/2021 Approved BRENDAN LOONEY
Structural Steel Frame 6/25/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 6/25/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 7/12/2021 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 7/20/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 7/30/2021 Conditional Approval BRENDAN LOONEY
Service/Power Release 8/3/2021 Not Ready for Inspection BRENDAN LOONEY
Service/Power Release 8/10/2021 Partial Inspection BRENDAN LOONEY
BUILDING-Rough-Frame 8/13/2021 Corrections Issued BRENDAN LOONEY
Green Building Rough 8/13/2021 Not Ready for Inspection BRENDAN LOONEY
METHANE-Rough 8/13/2021 Approved BRENDAN LOONEY
Gas Test 8/30/2021 Approved SHAVONNE ESPINOZA
HVAC-Rough 9/14/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 9/16/2021 Conditional Approval JAVIER RAMOS JR
ELECTRICAL-Rough 9/16/2021 Approved JAVIER RAMOS JR
HVAC-Rough 9/16/2021 Approved JAVIER RAMOS JR
PLUMBING-Rough 9/16/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 9/24/2021 Approved JESUS RODRIGUEZ
Insulation 9/29/2021 Approved JOHNNY MIRANDA
Drywall Nailing 10/4/2021 Approved RICHARD STEINBACH
ELECTRICAL-Final 11/29/2021 Not Ready for Inspection DAVID FEILER
HVAC-Final 11/29/2021 Not Ready for Inspection DAVID FEILER
PLUMBING-Final 11/29/2021 Corrections Issued DAVID FEILER
ELECTRICAL-Final 12/8/2021 Approved BOBBY KEY
HVAC-Final 12/8/2021 Conditional Approval BOBBY KEY
PLUMBING-Final 12/8/2021 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/13/2021 SGSOV Not Ready DAVID FEILER
Final 12/15/2021 Corrections Issued BOBBY KEY
Service/Power Release 12/15/2021 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 12/30/2021 Approved BOBBY KEY
Final 12/30/2021 OK to Issue CofO BOBBY KEY
Green Building Final 12/30/2021 Approved BOBBY KEY
Green Building Rough 12/30/2021 Approved BOBBY KEY
HVAC-Final 12/30/2021 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/30/2021 SGSOV Approved BOBBY KEY
Smoke Detectors 12/30/2021 Approved BOBBY KEY