15824 W SEPTO ST 91343

Certificate Information: 15824 W SEPTO ST 91343

Application / Permit
19014-10000-07064
Plan Check / Job No.
B19LA27184
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE WITH (N) ADDITION INTO ADU PER AB 494 AND SB 229
Permit Issued
Issued on 1/22/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/24/2019 APPLICANT
Assigned to Plan Check Engineer 12/30/2019 MONICA RAMIREZ
Corrections Issued 12/30/2019 MONICA RAMIREZ
Plan Check Approved 1/10/2020 KEVIN MORALES
Issued 1/22/2020 LADBS
CofO in Progress 12/3/2020 MARK JOHNSON
CofO Issued 1/5/2021 MICHAEL SMITH
Permit Finaled 1/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/7/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/7/2020 EMIL KYUPELYAN
Grading Pre-Inspection Cleared 1/7/2020 KIRK LINKLATER
Roof/Waste drainage to street Cleared 1/7/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/7/2020 EMIL KYUPELYAN

Contact Information

Contractor Levet Inc; Lic. No.: 1027447-B 1110 SONORA AVE #101      GLENDALE, CA 91201
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/21/2020 Partial Approval MARK JOHNSON
PLUMBING-Rough 2/25/2020 Partial Approval MARK JOHNSON
Excavation/Setback/Form/Re-Bar 2/27/2020 Approved MARK JOHNSON
Underground Mechanical 2/27/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Partial Approval MARK JOHNSON
PLUMBING-Rough 4/8/2020 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 4/20/2020 Approved MARK JOHNSON
PLUMBING-Rough 4/20/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 6/3/2020 Partial Approval MARK JOHNSON
Green Building Rough 6/3/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 6/9/2020 Approved MARK JOHNSON
Green Building Rough 6/9/2020 Approved MARK JOHNSON
HVAC-Rough 6/9/2020 Approved MARK JOHNSON
Insulation 6/10/2020 Approved MARK JOHNSON
Drywall Nailing 6/29/2020 Approved MARK JOHNSON
Final 11/16/2020 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 11/16/2020 Approved MARK JOHNSON
Green Building Final 11/16/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 11/16/2020 SGSOV Approved MARK JOHNSON
Smoke Detectors 11/16/2020 Approved MARK JOHNSON
Final 11/23/2020 Not Ready for Inspection MARK JOHNSON
Final 12/2/2020 OK to Issue CofO MARK JOHNSON