2143 W ADDISON WAY 90041
Certificate Information: 2143 W ADDISON WAY 90041
- Application / Permit
- 19014-10000-07052
- Plan Check / Job No.
- B19LA27172
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL TO EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/19/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2020 | FERNANDO FLORES |
| Corrections Issued | 1/13/2020 | FERNANDO FLORES |
| Green Plans Picked Up | 1/27/2020 | APPLICANT |
| Quality Review Completed | 1/29/2020 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 1/30/2020 | APPLICANT |
| Plan Check Approved | 3/6/2020 | FERNANDO FLORES |
| Issued | 3/6/2020 | LADBS |
| CofO in Progress | 7/1/2020 | CRAIG VAUGHAN |
| Permit Finaled | 8/19/2020 | DEROLD HAUFF |
| CofO Issued | 8/19/2020 | DEROLD HAUFF |
| Permit Finaled | 8/19/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/14/2020 | KIRK LINKLATER |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2020 | ELAINE LEI |
| Green Code | Cleared | 3/4/2020 | FERNANDO FLORES |
| Low Impact Development | Cleared | 3/4/2020 | JORGE MEJIA LEMUS |
| GPI Written Notices | Cleared | 3/5/2020 | FERNANDO FLORES |
| Roof/Waste drainage to street | Cleared | 3/5/2020 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/11/2020 | Corrections Issued | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/20/2020 | Approved | CRAIG VAUGHAN |
| METHANE-Barrier | 3/20/2020 | Approved | CRAIG VAUGHAN |
| METHANE-Subgrade | 3/20/2020 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 3/23/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 3/24/2020 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/6/2020 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 4/6/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| METHANE-Rough | 4/6/2020 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/15/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 4/30/2020 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/4/2020 | Partial Approval | CRAIG VAUGHAN |
| HVAC-Rough | 5/4/2020 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/4/2020 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/5/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 5/5/2020 | Approved | CRAIG VAUGHAN |
| Shower Pan | 5/6/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/7/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/11/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/11/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/11/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/15/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 6/3/2020 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 6/3/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/10/2020 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 6/10/2020 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/10/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 6/10/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Final | 6/10/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2020 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 6/10/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 6/10/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/12/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 6/12/2020 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 6/12/2020 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Final | 6/12/2020 | Corrections Issued | CRAIG VAUGHAN |
| Final | 6/19/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 6/19/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 6/19/2020 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 6/19/2020 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 6/19/2020 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 6/19/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 6/23/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 6/30/2020 | Approved | CRAIG VAUGHAN |
| Final | 6/30/2020 | OK to Issue CofO | CRAIG VAUGHAN |
| Smoke Detectors | 6/30/2020 | Approved | CRAIG VAUGHAN |