10584 W ASHTON AVE 90024
Certificate Information: 10584 W ASHTON AVE 90024
- Application / Permit
- 19014-10000-07034
- Plan Check / Job No.
- B19LA27126
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION AND ADDITION OF EXISTING GARAGE TO A 2-STORY ADU AB 494 & SB 229 AND ROOF DECK.
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | JESSE ARELLANO |
| Corrections Issued | 2/29/2020 | JESSE ARELLANO |
| Quality Review Completed | 3/12/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 9/30/2020 | APPLICANT |
| Applicant returned to address corrections | 10/5/2020 | JESSE ARELLANO |
| Plan Check Approved | 12/2/2020 | JESSE ARELLANO |
| No Progress | 12/2/2020 | JESSE ARELLANO |
| Plan Check Approved | 12/3/2020 | JESSE ARELLANO |
| Issued | 12/23/2020 | APPLICANT |
| Building Plans Picked Up | 12/28/2020 | APPLICANT |
| CofO in Progress | 2/1/2024 | BEN MOLSTAD |
| CofO in Progress | 2/1/2024 | BEN MOLSTAD |
| Permit Finaled | 2/5/2024 | DANIEL ORRANTE |
| CofO Issued | 2/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/28/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2020 | DINAH GARIN |
| Sewer availability | Cleared | 5/6/2020 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 6/3/2020 | KURT CORRAL |
| Green Code | Cleared | 9/25/2020 | VIVIAN LAO |
| Construction near power lines | Cleared | 10/14/2020 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 10/21/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/29/2020 | DINAH GARIN |
Contact Information
| Contractor | Coastal Construction And Design; Lic. No.: 982183-B | P O BOX 5733 SANTA MONICA, CA 90409 |
| Engineer | Lau,, David Harkwong; Lic. No.: C34961 | 12467 W WASHINGTON BLVD LOS ANGELES, CA 90066 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 4/14/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 5/19/2021 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 5/20/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Underground Mechanical | 5/20/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 6/8/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Barrier | 6/8/2021 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 6/8/2021 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 6/9/2021 | Approved | OGANES TARAKHCHYAN |
| Deputy Methane Barrier | 6/9/2021 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Reinf. Concrete | 6/10/2021 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/3/2022 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| METHANE-Rough | 10/3/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Special/Order Compliance | 10/3/2022 | Partial Inspection | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Approved | ANDREW NAVE |
| Green Building Rough | 10/6/2022 | Not Ready for Inspection | ANDREW NAVE |
| METHANE-Rough | 10/6/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 10/13/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 10/21/2022 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 11/1/2022 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 11/1/2022 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 11/1/2022 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 11/3/2022 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 11/3/2022 | Conditional Approval | ASHLEY THOMPSON |
| Final | 11/3/2022 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 11/3/2022 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 11/3/2022 | Corrections Issued | ASHLEY THOMPSON |
| Insulation | 11/10/2022 | Corrections Issued | ASHLEY THOMPSON |
| Drywall Nailing | 12/5/2022 | Approved | CHRISTOPHER WILSON |
| Sewer | 4/24/2023 | Approved | JESUS PINEDA |
| Underground Mechanical | 4/24/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 6/9/2023 | Partial Approval | JESUS PINEDA |
| METHANE-Barrier | 6/9/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 6/9/2023 | Approved | JESUS PINEDA |
| HVAC-Final | 7/11/2023 | Corrections Issued | JEREMY TODD |
| HVAC-Final | 7/26/2023 | Corrections Issued | DAVID FEILER |
| HVAC-Final | 8/21/2023 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/13/2023 | Approved | BEN MOLSTAD |
| Final | 12/13/2023 | Corrections Issued | BEN MOLSTAD |
| Footing/Foundation/Slab | 12/13/2023 | Approved | BEN MOLSTAD |
| Green Building Final | 12/13/2023 | Approved | BEN MOLSTAD |
| METHANE-Subgrade | 12/13/2023 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 12/13/2023 | SGSOV Approved | BEN MOLSTAD |
| Smoke Detectors | 12/13/2023 | Approved | BEN MOLSTAD |
| Structural Steel Frame | 12/13/2023 | Approved | BEN MOLSTAD |
| Final | 12/20/2023 | Partial Approval | BEN MOLSTAD |
| Final | 2/1/2024 | OK to Issue CofO | BEN MOLSTAD |