6813 W LEXINGTON AVE 90038

Certificate Information: 6813 W LEXINGTON AVE 90038

Application / Permit
19014-10000-07033
Plan Check / Job No.
B19LA25967
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Permit for conversion from an unpermitted dwelling (was a detached garage and unpermitted addition) to a new detached ADU per GCS 65852.23. Total of 609 SF **affordable unit no longer required**
Permit Issued
Issued on 7/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 5/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/9/2019 APPLICANT
Assigned to Plan Check Engineer 12/20/2019 LAURA DUONG
Corrections Issued 12/24/2019 LAURA DUONG
Quality Review Completed 12/30/2019 KEN GILL
Building Plans Picked Up 1/2/2020 APPLICANT
Applicant returned to address corrections 3/2/2020 LAURA DUONG
Applicant returned to address corrections 9/1/2022 LAURA DUONG
Applicant returned to address corrections 9/7/2022 LAURA DUONG
Applicant returned to address corrections 4/18/2023 LAURA DUONG
Applicant returned to address corrections 6/15/2023 LAURA DUONG
Plan Check Approved 7/17/2023 LAURA DUONG
Issued 7/21/2023 APPLICANT
CofO in Progress 5/10/2024 BRIAN SULLIVAN
Permit Finaled 5/13/2024 RONALD MYRICK
CofO Issued 5/13/2024 RONALD MYRICK
Permit Finaled 5/13/2024 RONALD MYRICK

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/9/2021 JEANIE LAM
Sewer availability Cleared 8/23/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/24/2021 JEANIE LAM
Tenant Habitability Plan Cleared 12/13/2021 ISMAEL HERNANDEZ
Address approval Cleared 6/21/2023 JEANIE LAM

Contact Information

Contractor Ravello Construction; Lic. No.: 1068657-B 8322 BEVERLY BLVD STE 301      LOS ANGELES, CA 90048
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/1/2023 Partial Inspection BRIAN SULLIVAN
Pre-Inspection 8/28/2023 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 9/26/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 12/11/2023 Partial Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 1/2/2024 Corrections Issued ROY SPAULDING
Green Building Rough 1/2/2024 Not Ready for Inspection ROY SPAULDING
Wood Frame 1/26/2024 Partial Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 3/4/2024 Partial Inspection BRIAN SULLIVAN
PLUMBING-Rough 3/4/2024 Corrections Issued BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 3/12/2024 Approved BRIAN SULLIVAN
Insulation 3/22/2024 Not Ready for Inspection BRIAN SULLIVAN
Interior/Exterior Lathing 3/22/2024 Approved BRIAN SULLIVAN
Shower Pan 3/22/2024 Not Ready for Inspection BRIAN SULLIVAN
Insulation 3/27/2024 Corrections Issued BRIAN SULLIVAN
BUILDING-Rough-Frame 4/22/2024 Approved BRIAN SULLIVAN
Drywall Nailing 4/22/2024 Approved BRIAN SULLIVAN
Final 4/22/2024 Partial Inspection BRIAN SULLIVAN
Footing/Foundation/Slab 4/22/2024 Approved BRIAN SULLIVAN
Green Building Final 4/22/2024 Approved BRIAN SULLIVAN
Green Building Rough 4/22/2024 Approved BRIAN SULLIVAN
Service/Power Release 4/22/2024 Approved BRIAN SULLIVAN
Smoke Detectors 4/22/2024 Not Ready for Inspection BRIAN SULLIVAN
Final 5/6/2024 Corrections Issued BRIAN SULLIVAN
Smoke Detectors 5/6/2024 Approved BRIAN SULLIVAN
Final 5/10/2024 OK to Issue CofO BRIAN SULLIVAN