4342-4346 E SARDONYX ST 90032
Certificate Information: 4342-4346 E SARDONYX ST 90032
- Application / Permit
- 19014-10000-07013
- Plan Check / Job No.
- B19LA27077
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED CONVERSION A PORTION OF EXISTING UTILITY AND STORAGE ROOMS WITH 1/2 BATH TO ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 3/2/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/4/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/27/2019 | SINA KHOSRAVI |
| Corrections Issued | 1/2/2020 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/12/2020 | SINA KHOSRAVI |
| Plan Check Approved | 2/28/2020 | SINA KHOSRAVI |
| Issued | 3/2/2020 | LADBS |
| CofO in Progress | 10/15/2020 | OSVALDO PARAMO |
| CofO in Progress | 10/15/2020 | OSVALDO PARAMO |
| CofO in Progress | 10/15/2020 | OSVALDO PARAMO |
| Permit Finaled | 11/4/2020 | DEROLD HAUFF |
| CofO Issued | 11/4/2020 | DEROLD HAUFF |
| Permit Finaled | 11/4/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/5/2020 | JASON CHAN |
| "Q" conditions | Cleared | 2/5/2020 | JASON CHAN |
| Address approval | Cleared | 2/5/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2020 | THOMAS LANG |
| Sewer availability | Cleared | 2/5/2020 | THOMAS LANG |
| ZI | Cleared | 2/5/2020 | JASON CHAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 6/11/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 6/11/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 6/11/2020 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 6/12/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/16/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 6/24/2020 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 6/24/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/2/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 7/8/2020 | Approved | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 7/14/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 7/14/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 7/14/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 7/15/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 7/15/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 7/17/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/22/2020 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 10/1/2020 | Approved | OSVALDO PARAMO |
| HVAC-Final | 10/1/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 10/1/2020 | Approved | OSVALDO PARAMO |
| Final | 10/9/2020 | OK to Issue CofO | OSVALDO PARAMO |
| Green Building Final | 10/9/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 10/9/2020 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 10/9/2020 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 10/9/2020 | Approved | OSVALDO PARAMO |