1444-1446 W 184TH ST 90248

Certificate Information: 1444-1446 W 184TH ST 90248

Application / Permit
19014-10000-07002
Plan Check / Job No.
B19LA27063
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
-CONVERTING AND ADDING TO AN (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 -ADDING AND REMODELING EXISTING HOUSE -NEW TRELLIS
Permit Issued
Issued on 1/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 5/19/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 1/3/2020 MONICA RAMIREZ
Corrections Issued 1/3/2020 MONICA RAMIREZ
Plan Check Approved 1/7/2020 MONICA RAMIREZ
Issued 1/13/2020 LADBS
CofO in Progress 10/24/2020 EUGENE CASSIDY
Permit Finaled 5/19/2021 DEROLD HAUFF
CofO Issued 5/19/2021 DEROLD HAUFF
Permit Finaled 5/19/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/7/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 1/7/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 1/7/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/7/2020 EMIL KYUPELYAN

Contact Information

Contractor Levet Inc; Lic. No.: 1027447-B 1110 SONORA AVE #101      GLENDALE, CA 91201
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/6/2020 Approved EUGENE CASSIDY
Footing/Foundation/Slab 2/14/2020 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Partial Approval JOHN KLARIN
Green Building Rough 3/23/2020 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 4/9/2020 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 4/9/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/17/2020 Not Ready for Inspection BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2020 Partial Approval BRIAN CHRISTIAN
ELECTRICAL-Rough 4/21/2020 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/23/2020 Approved EUGENE CASSIDY
Green Building Rough 4/23/2020 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/1/2020 Partial Approval BRIAN CHRISTIAN
Insulation 5/12/2020 Corrections Issued BRIAN CHRISTIAN
Insulation 5/18/2020 Partial Approval BRIAN CHRISTIAN
Drywall Nailing 5/22/2020 Partial Approval SABAS ALONSO
Insulation 5/22/2020 Approved SABAS ALONSO
Drywall Nailing 6/3/2020 Approved BRIAN CHRISTIAN
Final 9/14/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 9/14/2020 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 9/14/2020 Approved EUGENE CASSIDY
Final 9/24/2020 Corrections Issued EUGENE CASSIDY
Green Building Final 9/24/2020 Approved EUGENE CASSIDY
Final 10/8/2020 Corrections Issued EUGENE CASSIDY
Final 10/21/2020 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 10/23/2020 Approved EUGENE CASSIDY
Final 10/23/2020 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 10/23/2020 Approved EUGENE CASSIDY
PLUMBING-Final 10/23/2020 Approved EUGENE CASSIDY