1444-1446 W 184TH ST 90248
Certificate Information: 1444-1446 W 184TH ST 90248
- Application / Permit
- 19014-10000-07002
- Plan Check / Job No.
- B19LA27063
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- -CONVERTING AND ADDING TO AN (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 -ADDING AND REMODELING EXISTING HOUSE -NEW TRELLIS
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2020 | MONICA RAMIREZ |
| Corrections Issued | 1/3/2020 | MONICA RAMIREZ |
| Plan Check Approved | 1/7/2020 | MONICA RAMIREZ |
| Issued | 1/13/2020 | LADBS |
| CofO in Progress | 10/24/2020 | EUGENE CASSIDY |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
| CofO Issued | 5/19/2021 | DEROLD HAUFF |
| Permit Finaled | 5/19/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 1/7/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/7/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Levet Inc; Lic. No.: 1027447-B | 1110 SONORA AVE #101 GLENDALE, CA 91201 |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/6/2020 | Approved | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/14/2020 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2020 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 3/23/2020 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 4/9/2020 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 4/9/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/17/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2020 | Partial Approval | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 4/21/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/23/2020 | Approved | EUGENE CASSIDY |
| Green Building Rough | 4/23/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/1/2020 | Partial Approval | BRIAN CHRISTIAN |
| Insulation | 5/12/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Insulation | 5/18/2020 | Partial Approval | BRIAN CHRISTIAN |
| Drywall Nailing | 5/22/2020 | Partial Approval | SABAS ALONSO |
| Insulation | 5/22/2020 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/3/2020 | Approved | BRIAN CHRISTIAN |
| Final | 9/14/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/14/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/14/2020 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 9/14/2020 | Approved | EUGENE CASSIDY |
| Final | 9/24/2020 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/24/2020 | Approved | EUGENE CASSIDY |
| Final | 10/8/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 10/21/2020 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/23/2020 | Approved | EUGENE CASSIDY |
| Final | 10/23/2020 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/23/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/23/2020 | Approved | EUGENE CASSIDY |