1923 W 66TH ST 90047

Certificate Information: 1923 W 66TH ST 90047

Application / Permit
19014-10000-06995
Plan Check / Job No.
B19LA27050
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK PER PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 7/2/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2019 APPLICANT
Assigned to Plan Check Engineer 12/23/2019 GEORGE ALVAREZ
Corrections Issued 12/23/2019 GEORGE ALVAREZ
Applicant returned to address corrections 12/27/2019 SHANGQIN XIE
Plan Check Approved 3/3/2020 MONICA RAMIREZ
Issued 7/2/2020 APPLICANT
Building Plans Picked Up 7/7/2020 APPLICANT
CofO in Progress 6/10/2021 FREDDIE RIVERA
Permit Finaled 6/17/2021 DEROLD HAUFF
CofO Issued 6/17/2021 DEROLD HAUFF
Permit Finaled 6/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/23/2019 JAMES MORALEZ
Community Plan Implem. Overlay Cleared 12/23/2019 JASON CHAN
Eng Process Fee Ord 176,300 Cleared 12/23/2019 JAMES MORALEZ
Roof/Waste drainage to street Cleared 12/23/2019 JAMES MORALEZ
Sewer availability Cleared 12/23/2019 JAMES MORALEZ
Construction near power lines Cleared 2/26/2020 ERNEST FRESQUEZ
Construction within easement Cleared 2/26/2020 ERNEST FRESQUEZ

Contact Information

No Data Available.

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/20/2020 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/27/2020 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 7/29/2020 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 8/4/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 8/31/2020 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 8/31/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/9/2020 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 9/9/2020 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/9/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 9/9/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 9/30/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Rough 9/30/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 9/30/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 10/23/2020 Approved FREDDIE RIVERA
Green Building Rough 10/23/2020 Approved FREDDIE RIVERA
HVAC-Rough 10/23/2020 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 10/23/2020 Partial Approval FREDDIE RIVERA
Drywall Nailing 11/5/2020 Approved FREDDIE RIVERA
Gas Test 11/5/2020 Approved FREDDIE RIVERA
Final 5/5/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 5/5/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 5/5/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 5/5/2021 Not Ready for Inspection FREDDIE RIVERA
Final 5/19/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 5/19/2021 SGSOV Not Ready DAVID FEILER
Smoke Detectors 5/19/2021 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 5/26/2021 SGSOV Not Ready FREDDIE RIVERA
Gas Test 6/2/2021 Not Ready for Inspection SABAS ALONSO
Final 6/10/2021 OK to Issue CofO FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved FREDDIE RIVERA