4400 W SLAUSON AVE 90043

Certificate Information: 4400 W SLAUSON AVE 90043

Application / Permit
19014-10000-06976
Plan Check / Job No.
B19LA26977
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
TENANT IMPROVEMENT TO (E) RESTAURANT/TAKE-OUR BAKERY WITH TRELLIS ADDITION FOR NEW OURDOOR EATING AREA.
Permit Issued
Issued on 8/18/2020
Issuing Office
Current Status
CofO Issued on 10/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 FARSHAD ALIMOHAMADI
Corrections Issued 1/15/2020 FARSHAD ALIMOHAMADI
Quality Review Completed 1/19/2020 YOUNG KIM
Disabled Access Plans Picked Up 2/7/2020 APPLICANT
Green Plans Picked Up 4/28/2020 APPLICANT
Applicant returned to address corrections 7/14/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/16/2020 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/23/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 8/5/2020 FARSHAD ALIMOHAMADI
Building Plans Picked Up 8/7/2020 APPLICANT
Issued 8/18/2020 APPLICANT
CofO in Progress 10/1/2021 LEOPOLDO MENDOZA
CofO in Progress 10/1/2021 LEOPOLDO MENDOZA
CofO Issued 10/4/2021 DAVID TSAU
Permit Finaled 10/4/2021 DAVID TSAU

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/31/2020 RENZ SORIANO
Sewer availability Cleared 3/31/2020 RENZ SORIANO
Green Code Cleared 4/2/2020 FARSHAD ALIMOHAMADI
DAS Clearance Cleared 5/5/2020 FARSHAD ALIMOHAMADI
Eng Process Fee Ord 176,300 Cleared 5/6/2020 PAMELA TENEZA
Community Plan Implem. Overlay Cleared 5/29/2020 KYLE WINSTON
Miscellaneous Cleared 6/5/2020 RUBEN VASQUEZ
Food Service Establishment Cleared 7/13/2020 KENNETH BROWNE
ZA Case Cleared 8/3/2020 CLAUDE GOODING
Food establishment approval Cleared 8/5/2020 LACDHS APPROVED
Grading Pre-Inspection Cleared 8/5/2020 FARSHAD ALIMOHAMADI

Contact Information

Architect Guga,, Jeff; Lic. No.: C36577 3448 ASHWOOD AVENUE      LOS ANGELES, CA 90066
Contractor Miller Kirk Construction; Lic. No.: 377173-B 1072 CASITAS PASS RD #288      CARPINTERIA, CA 93013
Engineer Howe,, Carl William; Lic. No.: C44773 4358 SEPULVEDA BLVD      CULVER CITY, CA 90230

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/2/2020 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 11/4/2020 Not Ready for Inspection KATY RAMIREZ
METHANE-Barrier 11/4/2020 Corrections Issued KATY RAMIREZ
METHANE-Subgrade 11/4/2020 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/12/2020 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 1/4/2021 Partial Inspection LEOPOLDO MENDOZA
METHANE-Barrier 1/4/2021 Not Ready for Inspection LEOPOLDO MENDOZA
METHANE-Subgrade 1/4/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Deputy Reinf. Concrete 1/5/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 1/7/2021 Conditional Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 1/8/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 1/11/2021 Conditional Approval LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 1/20/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 1/20/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 1/22/2021 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 1/22/2021 Partial Approval LANNY MERRICK
METHANE-Barrier 1/22/2021 Partial Approval LANNY MERRICK
METHANE-Subgrade 1/22/2021 Partial Approval LANNY MERRICK
Floor/Roof Diaphrgm/Shear Wall 2/4/2021 Approved LANNY MERRICK
Deputy Drilled-In Anchors 2/5/2021 Conditional Approval LANNY MERRICK
Deputy Reinf. Concrete 2/5/2021 Conditional Approval LANNY MERRICK
Footing/Foundation/Slab 2/5/2021 Partial Approval LANNY MERRICK
METHANE-Barrier 2/5/2021 Not Ready for Inspection LANNY MERRICK
METHANE-Subgrade 2/5/2021 Not Ready for Inspection LANNY MERRICK
Deputy Reinf. Concrete 2/8/2021 Conditional Approval LANNY MERRICK
Pre-Inspection 3/15/2021 Not Ready for Inspection LANNY MERRICK
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval LANNY MERRICK
Interior/Exterior Lathing 4/12/2021 Approved LANNY MERRICK
Green Building Rough 4/26/2021 Approved LEOPOLDO MENDOZA
METHANE-Rough 4/26/2021 Approved LEOPOLDO MENDOZA
Wood Frame 4/26/2021 Approved LEOPOLDO MENDOZA
Insulation 5/5/2021 Partial Approval LEOPOLDO MENDOZA
Insulation 5/10/2021 Approved LEOPOLDO MENDOZA
Drywall Nailing 5/13/2021 Approved LEOPOLDO MENDOZA
Footing/Foundation/Slab 5/13/2021 Partial Approval LEOPOLDO MENDOZA
METHANE-Barrier 5/13/2021 Not Ready for Inspection LEOPOLDO MENDOZA
METHANE-Subgrade 5/13/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Footing/Foundation/Slab 6/10/2021 Conditional Approval LEOPOLDO MENDOZA
METHANE-Barrier 6/10/2021 Approved LEOPOLDO MENDOZA
METHANE-Subgrade 6/10/2021 Approved LEOPOLDO MENDOZA
Deputy Drilled-In Anchors 6/17/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 6/18/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 6/21/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 6/29/2021 Partial Approval LEOPOLDO MENDOZA
Deputy Reinf. Concrete 6/30/2021 Conditional Approval LEOPOLDO MENDOZA
Excavation/Setback/Form/Re-Bar 6/30/2021 Partial Approval LEOPOLDO MENDOZA
T-Bar Ceiling 7/21/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Deputy Reinf. Concrete 7/28/2021 Conditional Approval LEOPOLDO MENDOZA
Footing/Foundation/Slab 8/3/2021 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 8/5/2021 Conditional Approval LEOPOLDO MENDOZA
T-Bar Ceiling 8/9/2021 Conditional Approval DARRYL ARNOLD
Final 9/2/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Footing/Foundation/Slab 9/2/2021 Approved LEOPOLDO MENDOZA
Green Building Final 9/2/2021 Not Ready for Inspection LEOPOLDO MENDOZA
SGSOV-Seismic Gas S/O Valve 9/2/2021 SGSOV Approved LEOPOLDO MENDOZA
Smoke Detectors 9/2/2021 Approved LEOPOLDO MENDOZA
Final 9/27/2021 Not Ready for Inspection LEOPOLDO MENDOZA
Green Building Final 9/27/2021 Approved LEOPOLDO MENDOZA
Final 9/30/2021 OK to Issue CofO LEOPOLDO MENDOZA