3338 E CAZADOR ST 90065

Certificate Information: 3338 E CAZADOR ST 90065

Application / Permit
19014-10000-06955
Plan Check / Job No.
B19LA26909
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Residential addtion & remodel (N) bedroom, bathroom, deck and rooftop balcony.
Permit Issued
Issued on 8/24/2021
Issuing Office
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 JESSE ARELLANO
Corrections Issued 2/20/2020 JESSE ARELLANO
Quality Review Completed 2/26/2020 BILL STUTSMAN
Green Plans Picked Up 6/15/2020 APPLICANT
Applicant returned to address corrections 12/2/2020 JESSE ARELLANO
Applicant returned to address corrections 1/15/2021 JESSE ARELLANO
Applicant returned to address corrections 1/20/2021 JESSE ARELLANO
Applicant returned to address corrections 4/5/2021 JESSE ARELLANO
Plan Check Approved 4/6/2021 JESSE ARELLANO
Issued 8/24/2021 APPLICANT
Building Plans Picked Up 8/26/2021 APPLICANT
CofO in Progress 3/23/2022 HAMIK HARTOUNIAN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/22/2021 CELINA MORENO
Sewer availability Cleared 2/22/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/23/2021 CELINA MORENO
Specific Plan Cleared 3/11/2021 NASHYA JENSEN
GPI Written Notices Cleared 4/5/2021 JESSE ARELLANO
Grading Pre-Inspection Cleared 4/5/2021 JESSE ARELLANO
Green Code Cleared 4/5/2021 KHEDER ALRAZAA

Contact Information

Contractor Ksj Design Build; Lic. No.: 997235-B 13337 SOUTH ST #266      CERRITOS, CA 90703
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/1/2021 Conditional Approval HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/3/2021 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 9/21/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 9/21/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/23/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 9/23/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Insulation 9/23/2021 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/27/2021 Approved CHARLES BOGHOSKHAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 10/22/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/1/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 11/1/2021 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/5/2021 Approved HAMIK HARTOUNIAN
Special/Order Compliance 11/5/2021 Partial Inspection ALIZAH MAYAGOITIA
Special/Order Compliance 11/5/2021 Partial Inspection AMY COLIN
Wood Frame 11/5/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/9/2021 Approved HAMIK HARTOUNIAN
Insulation 11/12/2021 Approved HAMIK HARTOUNIAN
Drywall Nailing 11/23/2021 Approved HAMIK HARTOUNIAN
Green Building Rough 11/23/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/27/2022 Approved HAMIK HARTOUNIAN
Final 1/27/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 1/27/2022 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 1/27/2022 Approved HAMIK HARTOUNIAN
Final 3/1/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 3/1/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/1/2022 SGSOV Not Ready HAMIK HARTOUNIAN
Final 3/17/2022 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 3/17/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Approved HAMIK HARTOUNIAN