1727 1/2 W 58TH ST 90062
Certificate Information: 1727 1/2 W 58TH ST 90062
- Application / Permit
- 19014-10000-06954
- Plan Check / Job No.
- B19LA26908
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 12'X 18' ONE CAR GARAGE TO 1 STORY ADU WITH ADDITION PER WFPP
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 1/14/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/15/2020 | JASON HEALEY |
| Building Plans Picked Up | 1/24/2020 | APPLICANT |
| Green Plans Picked Up | 12/21/2021 | APPLICANT |
| Plan Check Approved | 2/22/2023 | CRYSTEL MAALOUF |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 7/3/2024 | CRAIG DAVIS |
| CofO Issued | 7/9/2024 | DEROLD HAUFF |
| Permit Finaled | 7/9/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/22/2021 | CELINA MORENO |
| Construction near power lines | Cleared | 6/26/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | CELINA MORENO |
| Sewer availability | Cleared | 1/26/2022 | CELINA MORENO |
| Low Impact Development | Cleared | 9/13/2022 | ROGELIO CORTES |
| Stormwater Pollution Mitigatn | Cleared | 9/19/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 10/20/2022 | CHRISTOPHER ROCHA |
| Community Plan Implem. Overlay | Cleared | 2/6/2023 | RAFAEL FONTES |
| Green Code | Cleared | 2/16/2023 | KHEDER ALRAZAA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/19/2023 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 4/26/2023 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 4/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 5/2/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 5/2/2023 | Approved | SABAS ALONSO |
| Underground Mechanical | 5/2/2023 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/22/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 6/22/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Rough | 6/22/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 6/22/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/28/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 6/28/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 6/28/2023 | Approved | SABAS ALONSO |
| Insulation | 7/5/2023 | Corrections Issued | SABAS ALONSO |
| Interior/Exterior Lathing | 7/5/2023 | Partial Approval | SABAS ALONSO |
| Insulation | 7/11/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 7/17/2023 | No Access for Inspection | CHARLES BOGHOSKHAN |
| Drywall Nailing | 7/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 7/31/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| Underground Mechanical | 7/31/2023 | Approved | MICHAEL LEWIS |
| Sewer | 8/4/2023 | Approved | CHARLES BOGHOSKHAN |
| ELECTRICAL-Final | 10/10/2023 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 10/23/2023 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 10/23/2023 | Not Ready for Inspection | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 10/23/2023 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 10/23/2023 | Approved | JUSTIN HAWLEY |
| Underground Mechanical | 10/23/2023 | Approved | JUSTIN HAWLEY |
| Final | 11/2/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 11/2/2023 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 11/2/2023 | SGSOV Approved | CRAIG DAVIS |
| Final | 11/14/2023 | Partial Inspection | CRAIG DAVIS |
| Green Building Final | 11/14/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 12/5/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 12/5/2023 | Approved | CRAIG DAVIS |
| Final | 4/24/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 6/3/2024 | No Access for Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 6/4/2024 | Partial Inspection | CRAIG DAVIS |
| Final | 6/4/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 6/4/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 6/4/2024 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 7/2/2024 | Approved | CRAIG DAVIS |
| Final | 7/2/2024 | OK to Issue CofO | CRAIG DAVIS |
| Service/Power Release | 7/2/2024 | Approved | CRAIG DAVIS |