12417 W VERDI ST 90066
Certificate Information: 12417 W VERDI ST 90066
- Application / Permit
- 19014-10000-06923
- Plan Check / Job No.
- B19LA26830
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO MASTER BEDROOM AT REAR AND NEW ADDITION TO LIVING ROOM AT FRONT OF (E) SFD. CONVERTING (E) ATTACHED GARAGE TO CARPORT. REMOVE EXISTING ROOF FRAMING AND CONSTUCT NEW ROF WITH WALKING DECK AND REPLACE WINDOWS. BUILIDNG TO BE FULLY SPRINKLERED WITH NFPA 13D.
- Permit Issued
- Issued on 1/26/2021
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 9/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2020 | JESSE ARELLANO |
| Corrections Issued | 1/29/2020 | MIGUEL JIMENEZ |
| Quality Review Completed | 2/7/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 2/11/2020 | APPLICANT |
| Applicant returned to address corrections | 4/1/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 4/3/2020 | JESSE ARELLANO |
| Green Plans Picked Up | 5/18/2020 | APPLICANT |
| Applicant returned to address corrections | 8/1/2020 | JESSE ARELLANO |
| Applicant returned to address corrections | 12/15/2020 | JESSE ARELLANO |
| Plan Check Approved | 1/15/2021 | JESSE ARELLANO |
| Issued | 1/26/2021 | APPLICANT |
| CofO in Progress | 9/13/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 9/17/2024 | RICHARD STEINBACH |
| CofO Issued | 9/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 9/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/10/2020 | CELINA MORENO |
| Green Code | Cleared | 3/10/2020 | KHEDER ALRAZAA |
| Specific Plan | Cleared | 3/23/2020 | VALERIA CEJA |
| Roof/Waste drainage to street | Cleared | 7/21/2020 | DINAH GARIN |
| Low Impact Development | Cleared | 9/23/2020 | MARTIN FRAGOSO |
| Hold | Cleared | 2/11/2021 | JASON SHEETS |
Contact Information
| Contractor | Goliath Construction; Lic. No.: 1056541-B | 6914 RADFORD AVE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | 1898 WILDROSE AVE POMONA, CA 91767 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2021 | Approved | DAVID HEINE |
| Footing/Foundation/Slab | 2/16/2021 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 2/22/2021 | Partial Approval | DAVID HEINE |
| ELECTRICAL-Rough | 4/8/2021 | Corrections Issued | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Corrections Issued | KENNETH NAGLE |
| ELECTRICAL-Rough | 4/30/2021 | Approved | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Rough | 4/30/2021 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Rough | 5/3/2021 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2021 | Approved | ENRIQUE MIRELES |
| Gas Test | 5/6/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/6/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/4/2021 | Not Ready for Inspection | PIERRE VEGA |
| Green Building Rough | 6/4/2021 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 7/9/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 7/9/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 7/9/2021 | Partial Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 7/9/2021 | Approved | JUAN VALENZUELA |
| Insulation | 7/14/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/16/2021 | Approved | ENRIQUE MIRELES |
| Shower Pan | 7/16/2021 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/27/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 2/2/2022 | No Access for Inspection | DAVID FEILER |
| HVAC-Final | 2/2/2022 | No Access for Inspection | DAVID FEILER |
| PLUMBING-Final | 2/2/2022 | No Access for Inspection | DAVID FEILER |
| ELECTRICAL-Final | 2/4/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 2/4/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Final | 2/4/2022 | Corrections Issued | DAVID FEILER |
| Service/Power Release | 2/4/2022 | Approved | DAVID FEILER |
| ELECTRICAL-Final | 2/8/2022 | Approved | DAVID FEILER |
| Gas Test | 2/8/2022 | Approved | DAVID FEILER |
| HVAC-Final | 2/8/2022 | Approved | DAVID FEILER |
| PLUMBING-Final | 2/8/2022 | Approved | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 2/8/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 2/8/2022 | Approved | DAVID FEILER |
| Final | 9/12/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Green Building Final | 9/12/2024 | Approved | TEMISTOCLES CAAL |