2817 S ORCHARD AVE 90007
Certificate Information: 2817 S ORCHARD AVE 90007
- Application / Permit
- 19014-10000-06894
- Plan Check / Job No.
- B19LA26773
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (18' X 12'-2") ADDIITON TO THE REAR OF AN EXISTING SINGLE FAMILY DWELLING TO CREATE AN ATTACHED ACCESSORY DWELLING UNIT PER AB494 AND SB 229 AND A ROOF TOP DECK. SCOPE OF WORK WILL ALSO INCLUDE A (13' x 18') CONVERSION OF THE SINGLE FAMILY TO THE PROPSOED ADU.
- Permit Issued
- Issued on 2/18/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | MICHAEL LOPEZ |
| Green Plans Picked Up | 1/7/2020 | APPLICANT |
| Corrections Issued | 1/8/2020 | MICHAEL LOPEZ |
| Quality Review Completed | 1/11/2020 | STANLEY RAAP |
| Building Plans Picked Up | 1/21/2020 | APPLICANT |
| Applicant returned to address corrections | 2/12/2020 | MICHAEL LOPEZ |
| Plan Check Approved | 2/14/2020 | MICHAEL LOPEZ |
| Issued | 2/18/2020 | LADBS |
| CofO in Progress | 2/25/2021 | KATHRYN BUTTERWORTH |
| Permit Finaled | 3/16/2021 | DEROLD HAUFF |
| CofO Issued | 3/16/2021 | DEROLD HAUFF |
| Permit Finaled | 3/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/22/2020 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/22/2020 | ANTHONY MAINEZ |
| Green Code | Cleared | 1/29/2020 | KHEDER ALRAZAA |
| Permit | Cleared | 2/11/2020 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | EMIL KYUPELYAN |
| Specific Plan | Cleared | 2/12/2020 | DANIEL MATA |
| Specific Plan | Cleared | 2/14/2020 | EDUARDO HERMOSO |
Contact Information
| Architect | Zbikowski,, Jeffrey; Lic. No.: C35389 | 5919 S CROSFT AVENUE LOS ANGELES, CA 90056 |
| Contractor | Owner-Builder | , |
| Engineer | Kang,, Danniel; Lic. No.: S6242 | 633 E 223RD ST B CARSON, CA 90745 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/24/2020 | Conditional Approval | DAVID CHAN |
| METHANE-Barrier | 2/24/2020 | Approved | DAVID CHAN |
| METHANE-Subgrade | 2/24/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 2/27/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/27/2020 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2020 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/18/2020 | Partial Approval | SCOTT FINNILA |
| Green Building Rough | 3/18/2020 | Partial Approval | SCOTT FINNILA |
| METHANE-Rough | 3/18/2020 | Approved | SCOTT FINNILA |
| ELECTRICAL-Rough | 3/24/2020 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/24/2020 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 3/24/2020 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 3/24/2020 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/27/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/4/2020 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/4/2020 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 6/4/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 6/4/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 6/4/2020 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/4/2020 | SGSOV Not Ready | KATHRYN BUTTERWORTH |
| Smoke Detectors | 6/4/2020 | Approved | KATHRYN BUTTERWORTH |
| Final | 6/10/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/10/2020 | SGSOV Not Ready | ENRIQUE MIRELES |
| Final | 6/17/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 6/17/2020 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Final | 10/29/2020 | No Access for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 12/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |