6015 1/2 S 7TH AVE 90043

Certificate Information: 6015 1/2 S 7TH AVE 90043

Application / Permit
19014-10000-06837
Plan Check / Job No.
B19LA26581
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW REAR ADDITION TO (E) SFD AND CONVERSION TO ACCESSORY DWELLING UNIT PER AB494 AND SB229. ALL WORK PER WOOD FRAME PRESCRIPTIVE PROVISION.
Permit Issued
Issued on 1/15/2020
Issuing Office
Metro
Current Status
CofO Issued on 10/20/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/17/2019 KEVIN MORALES
Corrections Issued 12/17/2019 KEVIN MORALES
Issued 1/15/2020 LADBS
CofO in Progress 10/1/2020 FREDDIE RIVERA
Permit Finaled 10/20/2020 DEROLD HAUFF
CofO Issued 10/20/2020 DEROLD HAUFF
Permit Finaled 10/20/2020 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/27/2019 CELINA MORENO
Roof/Waste drainage to street Cleared 12/27/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/15/2020 CELINA MORENO
Sewer availability Cleared 1/15/2020 CELINA MORENO

Contact Information

Contractor Green'S Construction & Home Repair Co; Lic. No.: 654859-B 10408 SO VAN NESS AVENUE      LOS ANGELES, CA 90047

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/27/2020 Approved HORACE FULTZ
Insulation 2/27/2020 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 5/12/2020 No Access for Inspection FREDDIE RIVERA
PLUMBING-Rough 5/12/2020 No Access for Inspection FREDDIE RIVERA
Green Building Rough 6/12/2020 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/29/2020 Not Ready for Inspection FREDDIE RIVERA
Drywall Nailing 6/29/2020 Not Ready for Inspection FREDDIE RIVERA
ELECTRICAL-Final 6/29/2020 Approved FREDDIE RIVERA
Final 6/29/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 6/29/2020 Not Ready for Inspection FREDDIE RIVERA
Insulation 6/29/2020 Not Ready for Inspection FREDDIE RIVERA
PLUMBING-Final 6/29/2020 Corrections Issued FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/29/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 6/29/2020 Not Ready for Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 7/22/2020 Partial Approval ROBERT MCDOWELL
ELECTRICAL-Rough 7/22/2020 Approved ROBERT MCDOWELL
PLUMBING-Rough 7/22/2020 Corrections Issued ROBERT MCDOWELL
BUILDING-Rough-Frame 8/3/2020 Conditional Approval FREDDIE RIVERA
Insulation 8/3/2020 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 8/24/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 8/24/2020 Approved FREDDIE RIVERA
Drywall Nailing 8/31/2020 Not Ready for Inspection FREDDIE RIVERA
Final 8/31/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 8/31/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 8/31/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 8/31/2020 Not Ready for Inspection FREDDIE RIVERA
Drywall Nailing 9/23/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 9/23/2020 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 9/23/2020 Not Ready for Inspection JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 9/23/2020 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 9/23/2020 Not Ready for Inspection JOSEPH MCGARRY
Special/Order Compliance 9/28/2020 Corrections Issued FREDDIE RIVERA
Drywall Nailing 10/1/2020 Approved FREDDIE RIVERA
Final 10/1/2020 OK to Issue CofO FREDDIE RIVERA
Green Building Final 10/1/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 10/1/2020 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 10/1/2020 Approved FREDDIE RIVERA