4131 E MONTEREY ST 90065
Certificate Information: 4131 E MONTEREY ST 90065
- Application / Permit
- 19014-10000-06828
- Plan Check / Job No.
- B19LA26545
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 story addition to the front of an existing SFD.
- Permit Issued
- Issued on 5/4/2020
- Issuing Office
- Metro
- Current Status
- Issued on 5/4/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2019 | HELEN NGUYEN |
| Corrections Issued | 12/30/2019 | HELEN NGUYEN |
| Plan Check Approved | 2/7/2020 | HELEN NGUYEN |
| Issued | 5/4/2020 | LADBS |
| Building Plans Picked Up | 5/4/2020 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2020 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 1/7/2020 | KIRK LINKLATER |
| Roof/Waste drainage to street | Cleared | 1/7/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/7/2020 | ERIK BEASLEY |
| Specific Plan | Cleared | 1/9/2020 | RICHARD REASER |
| GPI Written Notices | Cleared | 2/7/2020 | HELEN NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Song,, Zhenyu Michael; Lic. No.: S5266 | 12540 DESTINO ST CERRITOS, CA 90703 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/4/2020 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/24/2020 | Partial Approval | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/26/2020 | Approved | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 7/1/2020 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 7/15/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2020 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 7/17/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 10/2/2020 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 10/2/2020 | Corrections Issued | OSVALDO PARAMO |
| Rough-Elec/Plmb/HVAC | 10/16/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/21/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 10/21/2020 | Approved | OSVALDO PARAMO |
| Wood Frame | 10/21/2020 | Approved | OSVALDO PARAMO |
| Insulation | 10/23/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/23/2020 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/28/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/28/2020 | Approved | OSVALDO PARAMO |
| Shower Pan | 11/2/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 11/4/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 11/4/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 5/21/2021 | Approved | CRAIG VAUGHAN |
| Final | 5/21/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 5/21/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 5/21/2021 | Corrections Issued | CRAIG VAUGHAN |
| HVAC-Final | 5/21/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/21/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 5/21/2021 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/21/2021 | Approved | CRAIG VAUGHAN |
| Final | 6/1/2021 | Conditional Approval | OSVALDO PARAMO |
| Green Building Final | 6/1/2021 | Approved | OSVALDO PARAMO |