4131 E MONTEREY ST 90065

Certificate Information: 4131 E MONTEREY ST 90065

Application / Permit
19014-10000-06828
Plan Check / Job No.
B19LA26545
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story addition to the front of an existing SFD.
Permit Issued
Issued on 5/4/2020
Issuing Office
Metro
Current Status
Issued on 5/4/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/17/2019 APPLICANT
Assigned to Plan Check Engineer 12/20/2019 HELEN NGUYEN
Corrections Issued 12/30/2019 HELEN NGUYEN
Plan Check Approved 2/7/2020 HELEN NGUYEN
Issued 5/4/2020 LADBS
Building Plans Picked Up 5/4/2020 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/7/2020 ERIK BEASLEY
Grading Pre-Inspection Cleared 1/7/2020 KIRK LINKLATER
Roof/Waste drainage to street Cleared 1/7/2020 ERIK BEASLEY
Sewer availability Cleared 1/7/2020 ERIK BEASLEY
Specific Plan Cleared 1/9/2020 RICHARD REASER
GPI Written Notices Cleared 2/7/2020 HELEN NGUYEN

Contact Information

Contractor Owner-Builder       ,
Engineer Song,, Zhenyu Michael; Lic. No.: S5266 12540 DESTINO ST      CERRITOS, CA 90703

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/4/2020 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 6/24/2020 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/26/2020 Approved OSVALDO PARAMO
Deputy Drilled-In Anchors 7/1/2020 Partial Approval OSVALDO PARAMO
Wood Frame 7/15/2020 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Partial Approval OSVALDO PARAMO
Green Building Rough 7/17/2020 Not Ready for Inspection OSVALDO PARAMO
ELECTRICAL-Rough 10/2/2020 Corrections Issued OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 10/2/2020 Approved OSVALDO PARAMO
PLUMBING-Rough 10/2/2020 Corrections Issued OSVALDO PARAMO
Rough-Elec/Plmb/HVAC 10/16/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/21/2020 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 10/21/2020 Approved OSVALDO PARAMO
Wood Frame 10/21/2020 Approved OSVALDO PARAMO
Insulation 10/23/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 10/23/2020 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 10/28/2020 Approved OSVALDO PARAMO
Green Building Rough 10/28/2020 Approved OSVALDO PARAMO
Shower Pan 11/2/2020 Approved OSVALDO PARAMO
Drywall Nailing 11/4/2020 Approved OSVALDO PARAMO
Interior/Exterior Lathing 11/4/2020 Approved OSVALDO PARAMO
ELECTRICAL-Final 5/21/2021 Approved CRAIG VAUGHAN
Final 5/21/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 5/21/2021 Approved CRAIG VAUGHAN
Green Building Final 5/21/2021 Corrections Issued CRAIG VAUGHAN
HVAC-Final 5/21/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 5/21/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/21/2021 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 5/21/2021 Approved CRAIG VAUGHAN
Smoke Detectors 5/21/2021 Approved CRAIG VAUGHAN
Final 6/1/2021 Conditional Approval OSVALDO PARAMO
Green Building Final 6/1/2021 Approved OSVALDO PARAMO