1122 1/2 S 5TH AVE 90019

Certificate Information: 1122 1/2 S 5TH AVE 90019

Application / Permit
19014-10000-06799
Plan Check / Job No.
B19LA26443
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE FOR NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 9/30/2020
Issuing Office
Current Status
CofO Issued on 10/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 FARSHAD ALIMOHAMADI
Corrections Issued 12/26/2019 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 6/9/2020 LUKE GONZALES
Applicant returned to address corrections 8/4/2020 LUKE GONZALES
Plan Check Approved 8/20/2020 RICARDO RAMIREZ
Issued 9/30/2020 APPLICANT
Building Plans Picked Up 10/2/2020 APPLICANT
CofO in Progress 10/6/2021 KATHRYN BUTTERWORTH
Permit Finaled 10/16/2021 DEROLD HAUFF
CofO Issued 10/16/2021 DEROLD HAUFF
Permit Finaled 10/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 1/30/2020 RIDWAN HARDY
Address approval Cleared 4/13/2020 CELINA MORENO
HPOZ Cleared 4/21/2020 AMANDA KAINER
Eng Process Fee Ord 176,300 Cleared 4/28/2020 CELINA MORENO
Sewer availability Cleared 4/28/2020 CELINA MORENO
Low Impact Development Cleared 7/24/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/6/2020 JAMES KHO

Contact Information

Contractor Simcity Construction Inc; Lic. No.: 1027407-B 1458 S SAN PEDRO ST #312      LOS ANGELES, CA 90019
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/22/2020 Approved KATHRYN BUTTERWORTH
Excavation/Setback/Form/Re-Bar 1/6/2021 Approved KATHRYN BUTTERWORTH
Footing/Foundation/Slab 1/6/2021 Approved KATHRYN BUTTERWORTH
METHANE-Barrier 1/6/2021 Approved KATHRYN BUTTERWORTH
METHANE-Subgrade 1/6/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 1/19/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 1/19/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 1/21/2021 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 1/21/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Partial Approval KATHRYN BUTTERWORTH
HVAC-Rough 3/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 3/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Wood Frame 3/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Deputy Wood Construction 3/9/2021 No Access for Inspection ELMER BLAND
Floor/Roof Diaphrgm/Shear Wall 3/11/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 3/11/2021 Approved KATHRYN BUTTERWORTH
Wood Frame 3/11/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 3/16/2021 Approved OSVALDO PARAMO
HVAC-Rough 3/16/2021 Approved OSVALDO PARAMO
Interior/Exterior Lathing 3/16/2021 Not Ready for Inspection OSVALDO PARAMO
Wood Frame 3/16/2021 Corrections Issued OSVALDO PARAMO
Interior/Exterior Lathing 3/18/2021 Corrections Issued DAVID FEILER
Pre-Inspection 3/18/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 3/19/2021 Approved FREDDIE RIVERA
Interior/Exterior Lathing 3/19/2021 Not Ready for Inspection FREDDIE RIVERA
Wood Frame 3/19/2021 Approved FREDDIE RIVERA
Insulation 3/22/2021 Approved KATHRYN BUTTERWORTH
Drywall Nailing 4/6/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 4/6/2021 Corrections Issued KATHRYN BUTTERWORTH
Shower Pan 4/6/2021 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 4/15/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/27/2021 Partial Approval STUART CHAPMAN
Sewer 4/27/2021 Partial Approval STUART CHAPMAN
Sewer 5/6/2021 Approved KATHRYN BUTTERWORTH
Underground Mechanical 5/6/2021 Partial Approval KATHRYN BUTTERWORTH
Underground Mechanical 6/8/2021 Approved KATHRYN BUTTERWORTH
Gas Test 7/14/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 7/14/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Service/Power Release 7/14/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 8/16/2021 Approved KATHRYN BUTTERWORTH
Final 8/16/2021 Corrections Issued KATHRYN BUTTERWORTH
Green Building Final 8/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
METHANE-Final 8/16/2021 Approved KATHRYN BUTTERWORTH
METHANE-Rough 8/16/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 8/16/2021 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 8/16/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 9/15/2021 Partial Approval KATHRYN BUTTERWORTH
Green Building Final 9/15/2021 Approved KATHRYN BUTTERWORTH
Service/Power Release 9/15/2021 Approved KATHRYN BUTTERWORTH
Smoke Detectors 9/15/2021 Approved KATHRYN BUTTERWORTH
Final 10/5/2021 OK to Issue CofO KATHRYN BUTTERWORTH
Service/Power Release 10/5/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 10/12/2021 Approved KATHRYN BUTTERWORTH