1122 1/2 S 5TH AVE 90019
Certificate Information: 1122 1/2 S 5TH AVE 90019
- Application / Permit
- 19014-10000-06799
- Plan Check / Job No.
- B19LA26443
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO (E) GARAGE FOR NEW ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofO Issued on 10/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 12/26/2019 | FARSHAD ALIMOHAMADI |
| Applicant returned to address corrections | 6/9/2020 | LUKE GONZALES |
| Applicant returned to address corrections | 8/4/2020 | LUKE GONZALES |
| Plan Check Approved | 8/20/2020 | RICARDO RAMIREZ |
| Issued | 9/30/2020 | APPLICANT |
| Building Plans Picked Up | 10/2/2020 | APPLICANT |
| CofO in Progress | 10/6/2021 | KATHRYN BUTTERWORTH |
| Permit Finaled | 10/16/2021 | DEROLD HAUFF |
| CofO Issued | 10/16/2021 | DEROLD HAUFF |
| Permit Finaled | 10/16/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 1/30/2020 | RIDWAN HARDY |
| Address approval | Cleared | 4/13/2020 | CELINA MORENO |
| HPOZ | Cleared | 4/21/2020 | AMANDA KAINER |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2020 | CELINA MORENO |
| Sewer availability | Cleared | 4/28/2020 | CELINA MORENO |
| Low Impact Development | Cleared | 7/24/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/6/2020 | JAMES KHO |
Contact Information
| Contractor | Simcity Construction Inc; Lic. No.: 1027407-B | 1458 S SAN PEDRO ST #312 LOS ANGELES, CA 90019 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/22/2020 | Approved | KATHRYN BUTTERWORTH |
| Excavation/Setback/Form/Re-Bar | 1/6/2021 | Approved | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 1/6/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Barrier | 1/6/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Subgrade | 1/6/2021 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 1/19/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 1/19/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 1/21/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 3/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 3/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 3/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Wood Frame | 3/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Wood Construction | 3/9/2021 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 3/11/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 3/11/2021 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 3/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 3/16/2021 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 3/16/2021 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/16/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 3/16/2021 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 3/18/2021 | Corrections Issued | DAVID FEILER |
| Pre-Inspection | 3/18/2021 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 3/19/2021 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/19/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Wood Frame | 3/19/2021 | Approved | FREDDIE RIVERA |
| Insulation | 3/22/2021 | Approved | KATHRYN BUTTERWORTH |
| Drywall Nailing | 4/6/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 4/6/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Shower Pan | 4/6/2021 | Approved | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 4/15/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/27/2021 | Partial Approval | STUART CHAPMAN |
| Sewer | 4/27/2021 | Partial Approval | STUART CHAPMAN |
| Sewer | 5/6/2021 | Approved | KATHRYN BUTTERWORTH |
| Underground Mechanical | 5/6/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Underground Mechanical | 6/8/2021 | Approved | KATHRYN BUTTERWORTH |
| Gas Test | 7/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 7/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Service/Power Release | 7/14/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/16/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 8/16/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Green Building Final | 8/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| METHANE-Final | 8/16/2021 | Approved | KATHRYN BUTTERWORTH |
| METHANE-Rough | 8/16/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 8/16/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 9/15/2021 | Partial Approval | KATHRYN BUTTERWORTH |
| Green Building Final | 9/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Service/Power Release | 9/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 9/15/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 10/5/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Service/Power Release | 10/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Deputy Drilled-In Anchors | 10/12/2021 | Approved | KATHRYN BUTTERWORTH |