10546 N EL DORADO AVE 91331

Certificate Information: 10546 N EL DORADO AVE 91331

Application / Permit
19014-10000-06698
Plan Check / Job No.
B19LA26038
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO ONE-STORY SFD WITH NEW ATTACHED TWO-CAR GARAGE. RE-FRAME (E) ROOF AND PROVIDE FIRE SPRINKLER THRU-OUT.
Permit Issued
Issued on 3/18/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 FARSHAD ALIMOHAMADI
Corrections Issued 12/27/2019 FARSHAD ALIMOHAMADI
Quality Review Completed 12/28/2019 YOUNG KIM
Building Plans Picked Up 1/2/2020 APPLICANT
Green Plans Picked Up 1/2/2020 APPLICANT
Applicant returned to address corrections 3/10/2020 FARSHAD ALIMOHAMADI
Plan Check Approved 3/18/2020 FARSHAD ALIMOHAMADI
Issued 3/18/2020 LADBS
CofO in Progress 1/30/2026 RAUL OLAGI
Permit Finaled 2/11/2026 RUBEN SALAS
Permit Finaled 2/11/2026 RUBEN SALAS
CofO Issued 2/11/2026 RUBEN SALAS

Permit Application Clearance Information

Green Code Cleared 1/27/2020 VIVIAN LAO
Clean Up Green Up Cleared 1/31/2020 LATANYA ROUX
Trees in Parkway Cleared 1/31/2020 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 2/4/2020 THOMAS LANG
Permit Cleared 2/4/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 2/4/2020 THOMAS LANG
Sewer availability Cleared 2/4/2020 THOMAS LANG
Low Impact Development Cleared 3/17/2020 ORVAL HERNANDEZ-MARCI
Hold Cleared 5/15/2020 JEREMY CORONEL

Contact Information

Contractor Inspyre Home Construction Llc; Lic. No.: 1058662-B 22 S SUNNYSLOPE AVE      PASADENA, CA 91107
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2020 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 5/19/2020 Corrections Issued MICHEL ABAJAN
METHANE-Barrier 5/19/2020 Approved MICHEL ABAJAN
METHANE-Rough 5/19/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Subgrade 5/19/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 5/19/2020 Partial Approval MICHEL ABAJAN
Pre-Inspection 5/19/2020 Partial Approval MICHEL ABAJAN
Deputy Methane Barrier 6/4/2020 No Access for Inspection MICHEL ABAJAN
Deputy Methane Barrier 6/5/2020 No Access for Inspection MICHEL ABAJAN
Deputy Methane Barrier 6/12/2020 No Access for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 6/18/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 6/18/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 6/18/2020 Approved MICHEL ABAJAN
Deputy Methane Barrier 6/19/2020 Conditional Approval MICHEL ABAJAN
BUILDING-Rough-Frame 8/31/2020 Corrections Issued MICHEL ABAJAN
ELECTRICAL-Rough 8/31/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 8/31/2020 Partial Approval MICHEL ABAJAN
Gas Test 8/31/2020 Approved MICHEL ABAJAN
Green Building Rough 8/31/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 8/31/2020 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 8/31/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 9/17/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Rough 9/17/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 9/17/2020 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 9/18/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 9/18/2020 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 9/22/2020 Approved DANIEL ORRANTE
Shower Pan 9/22/2020 Approved DANIEL ORRANTE
BUILDING-Rough-Frame 9/24/2020 Conditional Approval MICHEL ABAJAN
Green Building Rough 9/24/2020 Approved MICHEL ABAJAN
METHANE-Rough 9/24/2020 Approved MICHEL ABAJAN
Insulation 9/30/2020 Approved MICHEL ABAJAN
Drywall Nailing 10/1/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/18/2020 Approved MICHEL ABAJAN
Green Building Final 11/18/2020 Partial Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 11/18/2020 Approved MICHEL ABAJAN
Smoke Detectors 11/18/2020 Partial Inspection MICHEL ABAJAN
BUILDING-Rough-Frame 6/15/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/15/2021 Approved MICHEL ABAJAN
Final 6/15/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 6/15/2021 Approved MICHEL ABAJAN
HVAC-Final 6/15/2021 Approved MICHEL ABAJAN
PLUMBING-Final 6/15/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 6/15/2021 Approved MICHEL ABAJAN
Final 8/12/2021 Corrections Issued MICHEL ABAJAN
Final 9/29/2021 Corrections Issued MICHAEL TEMPLE
Final 1/16/2026 Corrections Issued RAUL OLAGI
Final 1/30/2026 OK to Issue CofO RAUL OLAGI