3590 S INGLEWOOD BLVD 90066
Certificate Information: 3590 S INGLEWOOD BLVD 90066
- Application / Permit
- 19014-10000-06691
- Plan Check / Job No.
- B19LA26002
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 43'X 26' IRR SHAPED GROUND FLOOR ADDITION AND 28'6"X 28' IRR SHAPED 2ND FLOOR ADDITION TO THE EXISTING IRREGUALR SHAPED TWO STORY TYPE "V" SFD WITH ATTACHED TWO CAR GARAGE. INCLUDE THE REMODEL OF EXISTING PORTIONS OF THE SFD AND GARAGE, PER PLAN.
- Permit Issued
- Issued on 9/23/2021
- Issuing Office
- Current Status
- CofO Issued on 3/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2020 | CRYSTEL MAALOUF |
| Corrections Issued | 1/10/2020 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/13/2020 | JASON HEALEY |
| Building Plans Picked Up | 1/28/2020 | APPLICANT |
| Green Plans Picked Up | 1/28/2020 | APPLICANT |
| Applicant returned to address corrections | 3/16/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 5/27/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/9/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/23/2021 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 6/24/2021 | CRYSTEL MAALOUF |
| Plan Check Approved | 9/16/2021 | CRYSTEL MAALOUF |
| Issued | 9/23/2021 | APPLICANT |
| CofO in Progress | 3/17/2023 | JOHNNY MIRANDA |
| Permit Finaled | 3/22/2023 | DANIEL ORRANTE |
| CofO Issued | 3/22/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/22/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/12/2019 | JASON HEALEY |
| Grading Pre-Inspection | Cleared | 10/12/2019 | JASON HEALEY |
| Construction near power lines | Cleared | 3/6/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/1/2020 | CRYSTEL MAALOUF |
| Stormwater Pollution Mitigatn | Cleared | 1/14/2021 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 2/2/2021 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 2/24/2021 | ANTHONY MAINEZ |
| Green Code | Cleared | 9/16/2021 | COLIN LOREDO |
Contact Information
| Contractor | Omega Contractors Inc; Lic. No.: 1026633-B | 8039 FULTON AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Cattan,, Christian George; Lic. No.: C82566 | 8444 OWENSMOUTH AVE CANOGA PARK, CA 91304 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/30/2021 | Conditional Approval | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Partial Approval | JOHNNY MIRANDA |
| Deputy Drilled-In Anchors | 12/21/2021 | Conditional Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 2/1/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| PLUMBING-Rough | 2/1/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 5/4/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2022 | Partial Approval | JOHNNY MIRANDA |
| Rough-Elec/Plmb/HVAC | 6/22/2022 | Corrections Issued | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 6/30/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 6/30/2022 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 6/30/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| HVAC-Rough | 6/30/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/30/2022 | Conditional Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 8/10/2022 | Partial Approval | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 8/15/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 8/15/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 8/15/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 8/23/2022 | Approved | JOHNNY MIRANDA |
| Shower Pan | 8/23/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 8/24/2022 | Approved | ANDREW NAVE |
| Service/Power Release | 11/2/2022 | Approved | JOHNNY MIRANDA |
| Gas Test | 11/21/2022 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 11/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Smoke Detectors | 11/28/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/29/2022 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 12/7/2022 | Approved | JOHNNY MIRANDA |
| Final | 12/12/2022 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 12/12/2022 | Approved | JOHNNY MIRANDA |
| Green Building Final | 12/12/2022 | Approved | JOHNNY MIRANDA |
| Smoke Detectors | 12/12/2022 | Approved | JOHNNY MIRANDA |
| Final | 3/16/2023 | OK to Issue CofO | JOHNNY MIRANDA |