424 E 118TH ST 90061

Certificate Information: 424 E 118TH ST 90061

Application / Permit
19014-10000-06690
Plan Check / Job No.
B19LA25996
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1-STORY ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 1/23/2020
Issuing Office
Metro
Current Status
CofO Issued on 12/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 12/10/2019 ADAM HEGAZI
Corrections Issued 12/10/2019 ADAM HEGAZI
Plan Check Approved 1/22/2020 ADAM HEGAZI
Issued 1/23/2020 LADBS
CofO in Progress 9/24/2020 EUGENE CASSIDY
Permit Finaled 12/16/2020 DEROLD HAUFF
Permit Finaled 12/16/2020 DEROLD HAUFF
CofO Issued 12/16/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/6/2020 EMIL KYUPELYAN
Sewer availability Cleared 1/6/2020 EMIL KYUPELYAN
Community Plan Implem. Overlay Cleared 1/14/2020 JOSE ROMERO-NAVARRO
Low Impact Development Cleared 1/14/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/14/2020 JEANIE LAM

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/27/2020 Conditional Approval WILLIAM ROSE
Footing/Foundation/Slab 2/28/2020 Approved WILLIAM ROSE
PLUMBING-Rough 3/23/2020 Corrections Issued JOHN KLARIN
Wood Frame 3/23/2020 Corrections Issued JOHN KLARIN
Underground Mechanical 3/26/2020 Approved EUGENE CASSIDY
Wood Frame 3/26/2020 Partial Approval EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/31/2020 Partial Approval BRIAN CHRISTIAN
Insulation 3/31/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 4/24/2020 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/12/2020 Approved EUGENE CASSIDY
ELECTRICAL-Rough 5/12/2020 Approved EUGENE CASSIDY
Green Building Rough 5/12/2020 Approved EUGENE CASSIDY
HVAC-Rough 5/12/2020 Approved EUGENE CASSIDY
MERV13>=Rough 5/12/2020 Approved EUGENE CASSIDY
PLUMBING-Rough 5/12/2020 Approved EUGENE CASSIDY
Sewer 5/12/2020 Not Ready for Inspection EUGENE CASSIDY
Underground Mechanical 5/12/2020 Approved EUGENE CASSIDY
Insulation 5/14/2020 Approved BRIAN CHRISTIAN
Drywall Nailing 5/18/2020 Approved BRIAN CHRISTIAN
Interior/Exterior Lathing 5/18/2020 Not Ready for Inspection BRIAN CHRISTIAN
Interior/Exterior Lathing 5/26/2020 Not Ready for Inspection BRIAN CHRISTIAN
Interior/Exterior Lathing 5/27/2020 Approved BRIAN CHRISTIAN
Underground Mechanical 6/23/2020 Approved EUGENE CASSIDY
ELECTRICAL-Final 9/21/2020 Approved EUGENE CASSIDY
Final 9/21/2020 Corrections Issued EUGENE CASSIDY
Gas Test 9/21/2020 Approved EUGENE CASSIDY
Green Building Final 9/21/2020 Approved EUGENE CASSIDY
HVAC-Final 9/21/2020 Approved EUGENE CASSIDY
MERV13>=Final 9/21/2020 Approved EUGENE CASSIDY
PLUMBING-Final 9/21/2020 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/21/2020 SGSOV Approved EUGENE CASSIDY
Service/Power Release 9/21/2020 Approved EUGENE CASSIDY
Smoke Detectors 9/21/2020 Approved EUGENE CASSIDY
Final 9/23/2020 OK to Issue CofO EUGENE CASSIDY