4712 E YORK BLVD 1-5 90042
Certificate Information: 4712 E YORK BLVD 1-5 90042
- Application / Permit
- 19014-10000-06687
- Plan Check / Job No.
- B19LA25984
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- 2 STORY 3 UNIT AND COMMERCIAL SALON ADDITION TO (E) 1 STORY SFD. CREATING 2 STORY MIXED USE 4 UNIT W/ APARTMENT
- Permit Issued
- Issued on 7/13/2021
- Issuing Office
- Current Status
- CofO Issued on 3/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | HERNAN ARREOLA |
| Corrections Issued | 1/17/2020 | HERNAN ARREOLA |
| Green Plans Picked Up | 1/27/2020 | APPLICANT |
| Quality Review Completed | 1/30/2020 | BILL STUTSMAN |
| Building Plans Picked Up | 2/13/2020 | APPLICANT |
| Applicant returned to address corrections | 5/14/2020 | HERNAN ARREOLA |
| Disabled Access Plans Picked Up | 1/28/2021 | APPLICANT |
| Plan Check Approved | 7/8/2021 | HERNAN ARREOLA |
| Issued | 7/13/2021 | APPLICANT |
| CofO in Progress | 3/4/2024 | RAMAZANALI ALMASI |
| Permit Finaled | 3/7/2024 | ERNESTO CORRAL |
| CofO Issued | 3/7/2024 | ERNESTO CORRAL |
| Permit Finaled | 3/7/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Green Code | Cleared | 2/19/2020 | KHEDER ALRAZAA |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2020 | CELINA MORENO |
| Address approval | Cleared | 9/14/2020 | CELINA MORENO |
| Highway dedication | Cleared | 11/4/2020 | CELINA MORENO |
| Sewer availability | Cleared | 11/12/2020 | CELINA MORENO |
| "Q" conditions | Cleared | 2/24/2021 | RUBEN VASQUEZ |
| Frnt yard landscape/Water mgmt | Cleared | 2/25/2021 | RUBEN VASQUEZ |
| Trees in Parkway | Cleared | 4/14/2021 | JOHN KIM |
| DAS Clearance | Cleared | 4/21/2021 | SOMKIAT SUPANYACHOTSKUL |
| Hydrant and Access approval | Cleared | 5/1/2021 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/13/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 5/20/2021 | JEANIE LAM |
| GPI Written Notices | Cleared | 5/25/2021 | HERNAN ARREOLA |
| Grading Pre-Inspection | Cleared | 5/25/2021 | HERNAN ARREOLA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Favro,, Peter Louis; Lic. No.: GE2272 | 36 ROSS DRIVE MORAGA, CA 94556 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/28/2021 | Partial Inspection | LANNY MERRICK |
| Footing/Foundation/Slab | 9/15/2021 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/4/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Footing/Foundation/Slab | 10/18/2021 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 10/25/2021 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/26/2021 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/27/2021 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/29/2021 | Conditional Approval | DANIEL COLLINS |
| Footing/Foundation/Slab | 11/10/2021 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 11/16/2021 | Corrections Issued | MARK FERRARI |
| Footing/Foundation/Slab | 12/1/2021 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 1/12/2022 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 2/9/2022 | Conditional Approval | MARK FERRARI |
| Green Building Rough | 4/5/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 4/5/2022 | Corrections Issued | MARK FERRARI |
| Deputy Wood Construction | 4/15/2022 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2022 | Partial Approval | JONATHAN QUACH |
| Green Building Rough | 4/19/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Green Building Rough | 5/2/2022 | Approved | MARK FERRARI |
| Wood Frame | 5/2/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 5/10/2022 | Partial Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 5/25/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 5/25/2022 | Not Ready for Inspection | MARK FERRARI |
| Special/Order Compliance | 5/26/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 6/6/2022 | Corrections Issued | MARK FERRARI |
| Wood Frame | 8/9/2022 | Partial Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 8/24/2022 | Order to Comply Issued | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2022 | No Access for Inspection | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Approved | RAFAEL ESPINOZA |
| Insulation | 12/15/2022 | Corrections Issued | JEROME BLACKWOOD |
| Insulation | 12/21/2022 | Corrections Issued | RAFAEL CORTES |
| Insulation | 12/27/2022 | Corrections Issued | RAFAEL CORTES |
| Pre-Inspection | 12/27/2022 | Approved | ALAN MORELOS |
| Insulation | 1/19/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Insulation | 1/25/2023 | Approved | RAMAZANALI ALMASI |
| Drywall Nailing | 2/8/2023 | Partial Approval | RAMAZANALI ALMASI |
| Drywall Nailing | 2/14/2023 | Approved | RAMAZANALI ALMASI |
| Interior/Exterior Lathing | 2/14/2023 | Approved | RAMAZANALI ALMASI |
| Final | 7/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 7/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 7/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 7/12/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 7/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 7/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 7/25/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Wood Frame | 7/27/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 8/7/2023 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Special/Order Compliance | 9/1/2023 | Partial Inspection | RAMAZANALI ALMASI |
| Structural Steel Frame | 10/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 10/4/2023 | Approved | RAMAZANALI ALMASI |
| Insulation | 10/5/2023 | Partial Approval | RAFAEL CORTES |
| Final | 12/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 12/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Green Building Final | 12/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 12/12/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Final | 2/27/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Footing/Foundation/Slab | 2/27/2024 | Approved | RAMAZANALI ALMASI |
| Green Building Final | 2/27/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Smoke Detectors | 2/27/2024 | Approved | RAMAZANALI ALMASI |
| Final | 3/4/2024 | OK to Issue CofO | RAMAZANALI ALMASI |
| Green Building Final | 3/4/2024 | Approved | RAMAZANALI ALMASI |