4712 E YORK BLVD 1-5 90042

Certificate Information: 4712 E YORK BLVD 1-5 90042

Application / Permit
19014-10000-06687
Plan Check / Job No.
B19LA25984
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
2 STORY 3 UNIT AND COMMERCIAL SALON ADDITION TO (E) 1 STORY SFD. CREATING 2 STORY MIXED USE 4 UNIT W/ APARTMENT
Permit Issued
Issued on 7/13/2021
Issuing Office
Current Status
CofO Issued on 3/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 HERNAN ARREOLA
Corrections Issued 1/17/2020 HERNAN ARREOLA
Green Plans Picked Up 1/27/2020 APPLICANT
Quality Review Completed 1/30/2020 BILL STUTSMAN
Building Plans Picked Up 2/13/2020 APPLICANT
Applicant returned to address corrections 5/14/2020 HERNAN ARREOLA
Disabled Access Plans Picked Up 1/28/2021 APPLICANT
Plan Check Approved 7/8/2021 HERNAN ARREOLA
Issued 7/13/2021 APPLICANT
CofO in Progress 3/4/2024 RAMAZANALI ALMASI
Permit Finaled 3/7/2024 ERNESTO CORRAL
CofO Issued 3/7/2024 ERNESTO CORRAL
Permit Finaled 3/7/2024 ERNESTO CORRAL

Permit Application Clearance Information

Green Code Cleared 2/19/2020 KHEDER ALRAZAA
Eng Process Fee Ord 176,300 Cleared 9/4/2020 CELINA MORENO
Address approval Cleared 9/14/2020 CELINA MORENO
Highway dedication Cleared 11/4/2020 CELINA MORENO
Sewer availability Cleared 11/12/2020 CELINA MORENO
"Q" conditions Cleared 2/24/2021 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 2/25/2021 RUBEN VASQUEZ
Trees in Parkway Cleared 4/14/2021 JOHN KIM
DAS Clearance Cleared 4/21/2021 SOMKIAT SUPANYACHOTSKUL
Hydrant and Access approval Cleared 5/1/2021 JOHN CONNEALLY
Low Impact Development Cleared 5/13/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 5/20/2021 JEANIE LAM
GPI Written Notices Cleared 5/25/2021 HERNAN ARREOLA
Grading Pre-Inspection Cleared 5/25/2021 HERNAN ARREOLA

Contact Information

Contractor Owner-Builder       ,
Engineer Favro,, Peter Louis; Lic. No.: GE2272 36 ROSS DRIVE      MORAGA, CA 94556
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/28/2021 Partial Inspection LANNY MERRICK
Footing/Foundation/Slab 9/15/2021 Corrections Issued MARK FERRARI
Excavation/Setback/Form/Re-Bar 10/4/2021 Not Ready for Inspection JONATHAN QUACH
Footing/Foundation/Slab 10/18/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 10/25/2021 Not Ready for Inspection MARK FERRARI
Excavation/Setback/Form/Re-Bar 10/26/2021 Corrections Issued MARK FERRARI
Excavation/Setback/Form/Re-Bar 10/27/2021 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 10/29/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 11/10/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 11/16/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 12/1/2021 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 1/12/2022 Approved MARK FERRARI
Deputy Steel/Welding 2/9/2022 Conditional Approval MARK FERRARI
Green Building Rough 4/5/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 4/5/2022 Corrections Issued MARK FERRARI
Deputy Wood Construction 4/15/2022 Conditional Approval MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Approval JONATHAN QUACH
Green Building Rough 4/19/2022 Not Ready for Inspection JONATHAN QUACH
Green Building Rough 5/2/2022 Approved MARK FERRARI
Wood Frame 5/2/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 5/10/2022 Partial Inspection MARK FERRARI
Interior/Exterior Lathing 5/25/2022 Not Ready for Inspection MARK FERRARI
Wood Frame 5/25/2022 Not Ready for Inspection MARK FERRARI
Special/Order Compliance 5/26/2022 Partial Inspection MARK FERRARI
Wood Frame 6/6/2022 Corrections Issued MARK FERRARI
Wood Frame 8/9/2022 Partial Inspection MARK FERRARI
Footing/Foundation/Slab 8/24/2022 Order to Comply Issued MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 8/26/2022 No Access for Inspection MARK FERRARI
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Approved RAFAEL ESPINOZA
Insulation 12/15/2022 Corrections Issued JEROME BLACKWOOD
Insulation 12/21/2022 Corrections Issued RAFAEL CORTES
Insulation 12/27/2022 Corrections Issued RAFAEL CORTES
Pre-Inspection 12/27/2022 Approved ALAN MORELOS
Insulation 1/19/2023 Not Ready for Inspection RAMAZANALI ALMASI
Insulation 1/25/2023 Approved RAMAZANALI ALMASI
Drywall Nailing 2/8/2023 Partial Approval RAMAZANALI ALMASI
Drywall Nailing 2/14/2023 Approved RAMAZANALI ALMASI
Interior/Exterior Lathing 2/14/2023 Approved RAMAZANALI ALMASI
Final 7/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 7/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 7/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 7/12/2023 SGSOV Not Ready RAMAZANALI ALMASI
Smoke Detectors 7/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 7/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 7/25/2023 Not Ready for Inspection RAMAZANALI ALMASI
Wood Frame 7/27/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 8/7/2023 SGSOV Not Ready RAMAZANALI ALMASI
Special/Order Compliance 9/1/2023 Partial Inspection RAMAZANALI ALMASI
Structural Steel Frame 10/3/2023 Not Ready for Inspection RAFAEL CORTES
Wood Frame 10/4/2023 Approved RAMAZANALI ALMASI
Insulation 10/5/2023 Partial Approval RAFAEL CORTES
Final 12/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 12/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 12/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 12/12/2023 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 12/12/2023 Not Ready for Inspection RAMAZANALI ALMASI
Final 2/27/2024 Not Ready for Inspection RAMAZANALI ALMASI
Footing/Foundation/Slab 2/27/2024 Approved RAMAZANALI ALMASI
Green Building Final 2/27/2024 Not Ready for Inspection RAMAZANALI ALMASI
Smoke Detectors 2/27/2024 Approved RAMAZANALI ALMASI
Final 3/4/2024 OK to Issue CofO RAMAZANALI ALMASI
Green Building Final 3/4/2024 Approved RAMAZANALI ALMASI