11522 S WILLOWBROOK AVE 90059

Certificate Information: 11522 S WILLOWBROOK AVE 90059

Application / Permit
19014-10000-06630
Plan Check / Job No.
B19LA25746
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
29' X 28'8" GROUND FLOOR ADDITION TO THE BACK OF THE (E) SFD, WHICH ADD TWO BEDROOMS, ONE BATHROOM, LAUNDRYROOM AND DEN TO THE (E) TWO BED, ONE BATH SFD. AND INTERIOR REMODEL OF THE (E) SFD AND ADD NEW 20'X20' TWO-CAR GARAGE TO THE FRONT.
Permit Issued
Issued on 4/30/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/13/2019 AMIR DANAI
Corrections Issued 12/16/2019 AMIR DANAI
Quality Review Completed 12/17/2019 JASON HEALEY
Building Plans Picked Up 1/22/2020 APPLICANT
Green Plans Picked Up 1/30/2020 APPLICANT
Plan Check Approved 3/12/2020 AMIR DANAI
Plan Check Approved 4/30/2020 HERNAN ARREOLA
Issued 4/30/2020 LADBS
CofO in Progress 3/21/2023 JOHN KLARIN
Permit Finaled 4/13/2023 ANSON MAGLASANG
CofO Issued 4/13/2023 ANSON MAGLASANG
Permit Finaled 4/13/2023 ANSON MAGLASANG

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/19/2020 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 2/26/2020 CELINA MORENO
Green Code Cleared 2/26/2020 KHEDER ALRAZAA
Sewer availability Cleared 2/26/2020 CELINA MORENO
Metro Rail approval Cleared 2/27/2020 AMIR DANAI
Low Impact Development Cleared 3/10/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 3/10/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/8/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/11/2020 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 5/18/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/18/2020 Not Ready for Inspection EUGENE CASSIDY
Piling/Pier/Caisson 5/18/2020 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 5/22/2020 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 5/22/2020 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 5/28/2020 Approved JOHN KLARIN
PLUMBING-Rough 6/9/2020 Corrections Issued BRIAN CHRISTIAN
Insulation 6/10/2020 Partial Approval BRIAN CHRISTIAN
BUILDING-Rough-Frame 6/12/2020 Partial Approval BRIAN CHRISTIAN
PLUMBING-Rough 6/12/2020 Partial Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Corrections Issued BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Corrections Issued EUGENE CASSIDY
Deputy Wood Construction 6/24/2020 Conditional Approval BRIAN CHRISTIAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2020 Partial Approval BRIAN CHRISTIAN
Drywall Nailing 7/1/2020 Partial Approval BRIAN CHRISTIAN
Green Building Rough 7/1/2020 Not Ready for Inspection BRIAN CHRISTIAN
Interior/Exterior Lathing 7/1/2020 Partial Approval BRIAN CHRISTIAN
Excavation/Setback/Form/Re-Bar 6/11/2021 Corrections Issued EUGENE CASSIDY
Insulation 6/29/2021 No Access for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/6/2021 Partial Approval ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 8/11/2021 Not Ready for Inspection EUGENE CASSIDY
Insulation 8/11/2021 Partial Approval EUGENE CASSIDY
Deputy Wood Construction 9/2/2021 Conditional Approval EUGENE CASSIDY
BUILDING-Rough-Frame 9/3/2021 Corrections Issued EUGENE CASSIDY
Green Building Rough 9/3/2021 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 10/25/2021 Order to Comply Issued EUGENE CASSIDY
ELECTRICAL-Rough 10/25/2021 Approved EUGENE CASSIDY
HVAC-Rough 10/25/2021 Approved EUGENE CASSIDY
Insulation 10/25/2021 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/25/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 10/26/2021 Approved EUGENE CASSIDY
HVAC-Rough 10/26/2021 Approved EUGENE CASSIDY
Insulation 10/26/2021 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 10/26/2021 Approved EUGENE CASSIDY
Insulation 10/28/2021 Approved EUGENE CASSIDY
Drywall Nailing 11/2/2021 Approved EUGENE CASSIDY
Green Building Rough 11/2/2021 Approved EUGENE CASSIDY
Gas Test 11/5/2021 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/24/2021 Partial Approval EUGENE CASSIDY
ELECTRICAL-Final 12/29/2022 Not Ready for Inspection JOHN KLARIN
HVAC-Final 12/29/2022 Approved JOHN KLARIN
PLUMBING-Final 12/29/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/20/2023 Approved JOHN KLARIN
ELECTRICAL-Final 3/20/2023 Approved JOHN KLARIN
Final 3/20/2023 OK to Issue CofO JOHN KLARIN
Footing/Foundation/Slab 3/20/2023 Approved JOHN KLARIN
Green Building Final 3/20/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV No Gas JOHN KLARIN
Smoke Detectors 3/20/2023 Approved JOHN KLARIN