10543 N WINNEBAGO AVE 91345

Certificate Information: 10543 N WINNEBAGO AVE 91345

Application / Permit
19014-10000-06607
Plan Check / Job No.
B19LA25687
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ADDITION TO AND CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 2/4/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/5/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 SINA KHOSRAVI
Corrections Issued 12/5/2019 SINA KHOSRAVI
Applicant returned to address corrections 2/4/2020 RACHEL BEYENE
Plan Check Approved 2/4/2020 FARSHAD ALIMOHAMADI
Issued 2/4/2020 LADBS
CofO in Progress 9/8/2020 JENNIFER RABUCHIN
CofO Issued 9/23/2020 MICHAEL SMITH
Permit Finaled 9/23/2020 MICHAEL SMITH

Permit Application Clearance Information

Construction within easement Cleared 1/29/2020 RIDWAN HARDY
Address approval Cleared 2/4/2020 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/4/2020 JEANETTE VONG
Roof/Waste drainage to street Cleared 2/4/2020 JEANETTE VONG
Sewer availability Cleared 2/4/2020 JEANETTE VONG

Contact Information

No Data Available.

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/24/2020 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/5/2020 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 3/5/2020 Not Ready for Inspection JOHN HAYES
METHANE-Barrier 3/5/2020 Not Ready for Inspection JOHN HAYES
METHANE-Subgrade 3/5/2020 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 4/21/2020 Partial Approval JENNIFER RABUCHIN
Sewer 4/21/2020 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 4/23/2020 Approved JENNIFER RABUCHIN
METHANE-Barrier 4/23/2020 Approved JENNIFER RABUCHIN
METHANE-Subgrade 4/23/2020 Approved JENNIFER RABUCHIN
Sewer 4/23/2020 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/17/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/17/2020 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Approval JENNIFER RABUCHIN
Green Building Rough 6/17/2020 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 6/17/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/17/2020 Corrections Issued JENNIFER RABUCHIN
Sewer 6/17/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/19/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/19/2020 Approved JENNIFER RABUCHIN
Green Building Rough 6/19/2020 Approved JENNIFER RABUCHIN
Insulation 6/19/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 6/19/2020 Approved JENNIFER RABUCHIN
Insulation 6/24/2020 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 6/29/2020 Approved DANIEL ORRANTE
Pre-Inspection 7/1/2020 No Access for Inspection JOHN HAYES
Final 8/14/2020 Corrections Issued MICHAEL TEMPLE
Green Building Final 8/14/2020 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 8/14/2020 SGSOV Not Ready MICHAEL TEMPLE
Smoke Detectors 8/14/2020 Approved MICHAEL TEMPLE
Final 8/31/2020 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/31/2020 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 9/4/2020 Approved JENNIFER RABUCHIN
Final 9/4/2020 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 9/4/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 9/4/2020 Approved JENNIFER RABUCHIN