2734 S COCHRAN AVE 90016
Certificate Information: 2734 S COCHRAN AVE 90016
- Application / Permit
- 19014-10000-06595
- Plan Check / Job No.
- B19LA25605
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1 story addition to existing sfd and interior remodel of existing house.
- Permit Issued
- Issued on 1/7/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2019 | ARSALAN SHABESTARI |
| Corrections Issued | 12/10/2019 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/3/2020 | ARSALAN SHABESTARI |
| Issued | 1/7/2020 | LADBS |
| CofO in Progress | 11/9/2021 | SCOTT FINNILA |
| Permit Finaled | 11/15/2021 | DEROLD HAUFF |
| CofO Issued | 11/15/2021 | DEROLD HAUFF |
| Permit Finaled | 11/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2020 | ERIK BEASLEY |
| Low Impact Development | Cleared | 1/3/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/3/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/3/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1608 CENTINELA AVE #13 INGLEWOOD, CA 90302 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2020 | No Access for Inspection | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2020 | Conditional Approval | DAVID CHAN |
| Footing/Foundation/Slab | 4/21/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 5/18/2020 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 5/18/2020 | Not Ready for Inspection | DAVID CHAN |
| Insulation | 5/22/2020 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 5/27/2020 | Partial Approval | DAVID CHAN |
| Deputy Drilled-In Anchors | 10/14/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 10/14/2020 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 10/15/2020 | Not Ready for Inspection | DAVID CHAN |
| Wood Frame | 10/15/2020 | Not Ready for Inspection | DAVID CHAN |
| HVAC-Rough | 10/22/2020 | Not Ready for Inspection | DAVID CHAN |
| PLUMBING-Rough | 10/22/2020 | Corrections Issued | DAVID CHAN |
| ELECTRICAL-Rough | 10/23/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 10/23/2020 | Approved | DAVID CHAN |
| Wood Frame | 10/23/2020 | Corrections Issued | DAVID CHAN |
| HVAC-Rough | 10/27/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 10/27/2020 | Approved | DAVID CHAN |
| Shower Pan | 10/27/2020 | Approved | DAVID CHAN |
| Insulation | 10/29/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 11/12/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/12/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/18/2020 | Approved | DAVID CHAN |
| SGSOV-Seismic Gas S/O Valve | 5/24/2021 | SGSOV Not Ready | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/4/2021 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 6/4/2021 | Corrections Issued | SCOTT FINNILA |
| Final | 6/4/2021 | Corrections Issued | SCOTT FINNILA |
| Green Building Final | 6/4/2021 | Approved | SCOTT FINNILA |
| Green Building Rough | 6/4/2021 | Approved | SCOTT FINNILA |
| SGSOV-Seismic Gas S/O Valve | 6/4/2021 | SGSOV Approved | SCOTT FINNILA |
| Smoke Detectors | 6/4/2021 | Approved | SCOTT FINNILA |
| Pre-Inspection | 7/26/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 8/3/2021 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/17/2021 | Not Ready for Inspection | ALFREDO BALANDRA |
| ELECTRICAL-Final | 10/15/2021 | Corrections Issued | JOSE AVILA |
| Final | 10/15/2021 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 10/15/2021 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 10/15/2021 | Corrections Issued | JOSE AVILA |
| Final | 10/21/2021 | Partial Inspection | SCOTT FINNILA |
| Final | 11/1/2021 | Partial Inspection | SCOTT FINNILA |
| ELECTRICAL-Final | 11/8/2021 | Approved | SCOTT FINNILA |
| Final | 11/8/2021 | OK to Issue CofO | SCOTT FINNILA |
| Green Building Final | 11/8/2021 | Approved | SCOTT FINNILA |
| HVAC-Final | 11/8/2021 | Approved | SCOTT FINNILA |
| PLUMBING-Final | 11/8/2021 | Approved | SCOTT FINNILA |