2734 S COCHRAN AVE 90016

Certificate Information: 2734 S COCHRAN AVE 90016

Application / Permit
19014-10000-06595
Plan Check / Job No.
B19LA25605
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1 story addition to existing sfd and interior remodel of existing house.
Permit Issued
Issued on 1/7/2020
Issuing Office
Metro
Current Status
CofO Issued on 11/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2019 APPLICANT
Assigned to Plan Check Engineer 12/9/2019 ARSALAN SHABESTARI
Corrections Issued 12/10/2019 ARSALAN SHABESTARI
Plan Check Approved 1/3/2020 ARSALAN SHABESTARI
Issued 1/7/2020 LADBS
CofO in Progress 11/9/2021 SCOTT FINNILA
Permit Finaled 11/15/2021 DEROLD HAUFF
CofO Issued 11/15/2021 DEROLD HAUFF
Permit Finaled 11/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/3/2020 ERIK BEASLEY
Low Impact Development Cleared 1/3/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/3/2020 ERIK BEASLEY
Sewer availability Cleared 1/3/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Adefeso,, Wole Dayo; Lic. No.: C63361 1608 CENTINELA AVE #13      INGLEWOOD, CA 90302

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/10/2020 No Access for Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 4/14/2020 Conditional Approval DAVID CHAN
Footing/Foundation/Slab 4/21/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 5/18/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 5/18/2020 Not Ready for Inspection DAVID CHAN
Insulation 5/22/2020 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 5/27/2020 Partial Approval DAVID CHAN
Deputy Drilled-In Anchors 10/14/2020 No Access for Inspection ELMER BLAND
Deputy Wood Construction 10/14/2020 No Access for Inspection ELMER BLAND
BUILDING-Rough-Frame 10/15/2020 Not Ready for Inspection DAVID CHAN
Wood Frame 10/15/2020 Not Ready for Inspection DAVID CHAN
HVAC-Rough 10/22/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 10/22/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 10/23/2020 Approved DAVID CHAN
HVAC-Rough 10/23/2020 Approved DAVID CHAN
Wood Frame 10/23/2020 Corrections Issued DAVID CHAN
HVAC-Rough 10/27/2020 Approved DAVID CHAN
PLUMBING-Rough 10/27/2020 Approved DAVID CHAN
Shower Pan 10/27/2020 Approved DAVID CHAN
Insulation 10/29/2020 Approved DAVID CHAN
Drywall Nailing 11/12/2020 Approved DAVID CHAN
Interior/Exterior Lathing 11/12/2020 Approved DAVID CHAN
Interior/Exterior Lathing 11/18/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 5/24/2021 SGSOV Not Ready STUART CHAPMAN
BUILDING-Rough-Frame 6/4/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 6/4/2021 Corrections Issued SCOTT FINNILA
Final 6/4/2021 Corrections Issued SCOTT FINNILA
Green Building Final 6/4/2021 Approved SCOTT FINNILA
Green Building Rough 6/4/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 6/4/2021 SGSOV Approved SCOTT FINNILA
Smoke Detectors 6/4/2021 Approved SCOTT FINNILA
Pre-Inspection 7/26/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 8/3/2021 Not Ready for Inspection SABAS ALONSO
Final 9/17/2021 Not Ready for Inspection ALFREDO BALANDRA
ELECTRICAL-Final 10/15/2021 Corrections Issued JOSE AVILA
Final 10/15/2021 Corrections Issued JOSE AVILA
HVAC-Final 10/15/2021 Corrections Issued JOSE AVILA
PLUMBING-Final 10/15/2021 Corrections Issued JOSE AVILA
Final 10/21/2021 Partial Inspection SCOTT FINNILA
Final 11/1/2021 Partial Inspection SCOTT FINNILA
ELECTRICAL-Final 11/8/2021 Approved SCOTT FINNILA
Final 11/8/2021 OK to Issue CofO SCOTT FINNILA
Green Building Final 11/8/2021 Approved SCOTT FINNILA
HVAC-Final 11/8/2021 Approved SCOTT FINNILA
PLUMBING-Final 11/8/2021 Approved SCOTT FINNILA