4567 E CATALPA ST 90032
Certificate Information: 4567 E CATALPA ST 90032
- Application / Permit
- 19014-10000-06561
- Plan Check / Job No.
- B19LA25468
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING. INTERIOR/EXTERIOR REMODEL AND RECONFIGURE FLOOR PLAN TO 3 BEDROOM, 2 BATH. ADD (N) WINDOWS.
- Permit Issued
- Issued on 12/5/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/3/2019 | KEVIN MORALES |
| Corrections Issued | 12/3/2019 | KEVIN MORALES |
| Plan Check Approved | 12/4/2019 | ADAM HEGAZI |
| Issued | 12/5/2019 | LADBS |
| CofO in Progress | 11/18/2025 | LILIANA PORTILLO |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
| Permit Finaled | 11/19/2025 | DEROLD HAUFF |
| CofO Issued | 11/19/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| "D" conditions | Cleared | 12/3/2019 | ANNA VAN |
| "Q" conditions | Cleared | 12/3/2019 | ANNA VAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 12/3/2019 | PATRICK MISCHLICH |
| Roof/Waste drainage to street | Cleared | 12/3/2019 | JEANIE LAM |
| ZI | Cleared | 12/3/2019 | ANNA VAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/13/2019 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 1/16/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 1/16/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 1/21/2020 | Partial Approval | ENRIQUE MIRELES |
| Sewer | 1/21/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 3/3/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 3/3/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/3/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/9/2020 | Partial Approval | ENRIQUE MIRELES |
| Shower Pan | 3/9/2020 | Approved | ENRIQUE MIRELES |
| Wood Frame | 3/9/2020 | Approved | ENRIQUE MIRELES |
| Insulation | 3/16/2020 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 3/23/2020 | Partial Approval | ENRIQUE MIRELES |
| Green Building Rough | 3/23/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/31/2020 | Approved | ENRIQUE MIRELES |
| Sewer | 5/4/2020 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 5/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 5/8/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/8/2020 | Approved | ENRIQUE MIRELES |
| Sewer | 5/12/2020 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 5/12/2020 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/28/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 9/28/2020 | Approved | OSVALDO PARAMO |
| Final | 9/28/2020 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 9/28/2020 | Approved | OSVALDO PARAMO |
| Gas Test | 9/28/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Final | 9/28/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 9/28/2020 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 9/28/2020 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 9/28/2020 | No Access for Inspection | OSVALDO PARAMO |
| Final | 10/14/2020 | Corrections Issued | COREY HUPP |
| Gas Test | 10/14/2020 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 10/14/2020 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 10/14/2020 | Approved | COREY HUPP |
| ELECTRICAL-Final | 10/23/2020 | Corrections Issued | SCOTT FINNILA |
| Final | 10/23/2020 | Partial Inspection | SCOTT FINNILA |
| Gas Test | 10/23/2020 | Approved | SCOTT FINNILA |
| Green Building Final | 10/23/2020 | Approved | SCOTT FINNILA |
| HVAC-Final | 10/23/2020 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Final | 10/23/2020 | Approved | SCOTT FINNILA |
| Final | 10/28/2020 | Corrections Issued | SCOTT FINNILA |
| Final | 12/31/2020 | Partial Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 11/17/2025 | Approved | LILIANA PORTILLO |
| Final | 11/17/2025 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 11/17/2025 | Approved | LILIANA PORTILLO |