5601 N ANDASOL AVE 91316

Certificate Information: 5601 N ANDASOL AVE 91316

Application / Permit
19014-10000-06556
Plan Check / Job No.
B19LA25445
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) 2-CAR GARAGE AND CONVERT INTO ACCESSORY DWELLING UNIT PER AB-494 &SB-229. All Work Per Engineer Design
Permit Issued
Issued on 7/28/2020
Issuing Office
Current Status
CofO Issued on 10/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/3/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 ZAW HAN
Corrections Issued 1/2/2020 ZAW HAN
Quality Review Completed 1/9/2020 HERNAN ARREOLA
Building Plans Picked Up 1/10/2020 APPLICANT
Green Plans Picked Up 4/22/2020 APPLICANT
Applicant returned to address corrections 6/2/2020 ZAW HAN
Plan Check Approved 6/11/2020 ZAW HAN
Issued 7/28/2020 APPLICANT
CofO in Progress 8/26/2021 STEVEN BACK
CofO Issued 10/25/2021 MICHAEL SMITH
Permit Finaled 10/25/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/31/2020 JUAN ASHTON
ZI Cleared 1/31/2020 SARAHI ORTEGA
Low Impact Development Cleared 2/26/2020 SARAH YOUSSEF
Green Code Cleared 2/27/2020 ZAW HAN
Eng Process Fee Ord 176,300 Cleared 3/2/2020 EMIL KYUPELYAN
Permit Cleared 3/2/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 3/2/2020 EMIL KYUPELYAN
Sewer availability Cleared 3/2/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/24/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 9/1/2020 Approved STEVEN BACK
Deputy Reinf. Concrete 9/3/2020 Partial Approval STEVEN BACK
Deputy Drilled-In Anchors 9/25/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/20/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 12/29/2020 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/29/2020 Not Ready for Inspection VINCENT HANLEY
Green Building Rough 12/29/2020 Not Ready for Inspection VINCENT HANLEY
MERV13>=Rough 12/29/2020 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 1/19/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 1/22/2021 Not Ready for Inspection JOSEPH SAGEN
HVAC-Rough 1/22/2021 Not Ready for Inspection JOSEPH SAGEN
PLUMBING-Rough 1/22/2021 Not Ready for Inspection JOSEPH SAGEN
ELECTRICAL-Rough 1/28/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 1/28/2021 Approved VINCENT HANLEY
PLUMBING-Rough 1/28/2021 Approved VINCENT HANLEY
Green Building Rough 2/3/2021 Approved STEVEN BACK
HVAC-Rough 2/3/2021 Approved STEVEN BACK
Interior/Exterior Lathing 2/3/2021 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 2/5/2021 Approved STEVEN BACK
MERV13>=Rough 2/5/2021 Approved STEVEN BACK
Shower Pan 2/5/2021 Approved STEVEN BACK
Insulation 2/16/2021 Approved STEVEN BACK
Drywall Nailing 2/24/2021 Approved STEVEN BACK
Interior/Exterior Lathing 2/24/2021 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 3/2/2021 Approved STEVEN BACK
Gas Test 6/22/2021 Approved STEVEN BACK
HVAC-Final 6/22/2021 Corrections Issued STEVEN BACK
PLUMBING-Final 6/22/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Approved STEVEN BACK
ELECTRICAL-Final 6/23/2021 Corrections Issued STEVEN BACK
ELECTRICAL-Final 8/17/2021 Not Ready for Inspection STEVEN BACK
Final 8/17/2021 Corrections Issued STEVEN BACK
Green Building Final 8/17/2021 Approved STEVEN BACK
HVAC-Final 8/17/2021 Approved STEVEN BACK
MERV13>=Final 8/17/2021 Approved STEVEN BACK
Smoke Detectors 8/17/2021 Approved STEVEN BACK
Final 8/20/2021 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 8/26/2021 Approved STEVEN BACK
Final 8/26/2021 OK to Issue CofO STEVEN BACK