1449 W 64TH ST 90047

Certificate Information: 1449 W 64TH ST 90047

Application / Permit
19014-10000-06538
Plan Check / Job No.
B19LA25378
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) ONE STORY ADU PER AB 494 & SB 229 & ADD 11'X 6'8" TRELLIS PATIO COVER AT THE FRONT ENTRY. SEE COMMENTS
Permit Issued
Issued on 11/17/2021
Issuing Office
Current Status
CofO Issued on 8/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Assigned to Plan Check Engineer 12/26/2019 AMIR DANAI
Corrections Issued 1/2/2020 AMIR DANAI
Green Plans Picked Up 1/8/2020 APPLICANT
Quality Review Completed 1/13/2020 JASON HEALEY
Applicant returned to address corrections 6/28/2021 SERGIO GUTIERREZ
Applicant returned to address corrections 9/24/2021 SERGIO GUTIERREZ
Plan Check Approved 10/28/2021 SERGIO GUTIERREZ
Issued 11/17/2021 APPLICANT
Building Plans Picked Up 11/30/2021 APPLICANT
CofO in Progress 6/6/2022 ENRIQUE MIRELES
Permit Finaled 8/17/2022 RONALD MYRICK
CofO Issued 8/17/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 1/31/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 2/7/2020 AVALYN KAMACHI
Sewer availability Cleared 2/7/2020 AVALYN KAMACHI
Low Impact Development Cleared 8/10/2021 MITESH PATEL
Roof/Waste drainage to street Cleared 8/20/2021 STEVE MELGAR
Green Code Cleared 9/24/2021 AMIR DANAI

Contact Information

Contractor Building Blocks Ca Llc; Lic. No.: 1034808-B 180 SOUTH CITRUS AVENUE      LOS ANGELES, CA 90036
Engineer Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 4215 TOLAND WAY      LOS ANGELES, CA 90065

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2022 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 1/21/2022 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 1/31/2022 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/11/2022 Partial Inspection FREDDIE RIVERA
Wood Frame 2/11/2022 Not Ready for Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Approved FREDDIE RIVERA
Sewer 2/16/2022 Approved FREDDIE RIVERA
ELECTRICAL-Rough 2/22/2022 Approved FREDDIE RIVERA
HVAC-Rough 2/22/2022 Corrections Issued FREDDIE RIVERA
Interior/Exterior Lathing 2/22/2022 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 2/28/2022 Approved FREDDIE RIVERA
Green Building Rough 3/2/2022 Approved FREDDIE RIVERA
Wood Frame 3/2/2022 Conditional Approval FREDDIE RIVERA
BUILDING-Rough-Frame 3/7/2022 Approved LILIANA PORTILLO
Insulation 3/7/2022 Approved LILIANA PORTILLO
Drywall Nailing 3/10/2022 Approved FREDDIE RIVERA
HVAC-Rough 3/31/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Final 5/23/2022 Approved HORACE FULTZ
HVAC-Final 5/23/2022 Approved HORACE FULTZ
PLUMBING-Final 5/23/2022 Approved HORACE FULTZ
Final 5/25/2022 OK to Issue CofO HORACE FULTZ
Green Building Final 5/25/2022 Approved HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Approved HORACE FULTZ
Service/Power Release 5/25/2022 Approved HORACE FULTZ
Smoke Detectors 5/25/2022 Approved HORACE FULTZ
Final 6/6/2022 OK to Issue CofO ENRIQUE MIRELES