1449 W 64TH ST 90047
Certificate Information: 1449 W 64TH ST 90047
- Application / Permit
- 19014-10000-06538
- Plan Check / Job No.
- B19LA25378
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ONE STORY ADU PER AB 494 & SB 229 & ADD 11'X 6'8" TRELLIS PATIO COVER AT THE FRONT ENTRY. SEE COMMENTS
- Permit Issued
- Issued on 11/17/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | AMIR DANAI |
| Corrections Issued | 1/2/2020 | AMIR DANAI |
| Green Plans Picked Up | 1/8/2020 | APPLICANT |
| Quality Review Completed | 1/13/2020 | JASON HEALEY |
| Applicant returned to address corrections | 6/28/2021 | SERGIO GUTIERREZ |
| Applicant returned to address corrections | 9/24/2021 | SERGIO GUTIERREZ |
| Plan Check Approved | 10/28/2021 | SERGIO GUTIERREZ |
| Issued | 11/17/2021 | APPLICANT |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| CofO in Progress | 6/6/2022 | ENRIQUE MIRELES |
| Permit Finaled | 8/17/2022 | RONALD MYRICK |
| CofO Issued | 8/17/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | AVALYN KAMACHI |
| Sewer availability | Cleared | 2/7/2020 | AVALYN KAMACHI |
| Low Impact Development | Cleared | 8/10/2021 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 8/20/2021 | STEVE MELGAR |
| Green Code | Cleared | 9/24/2021 | AMIR DANAI |
Contact Information
| Contractor | Building Blocks Ca Llc; Lic. No.: 1034808-B | 180 SOUTH CITRUS AVENUE LOS ANGELES, CA 90036 |
| Engineer | Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 | 4215 TOLAND WAY LOS ANGELES, CA 90065 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/10/2022 | Corrections Issued | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 1/21/2022 | Partial Approval | HORACE FULTZ |
| Footing/Foundation/Slab | 1/31/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2022 | Partial Inspection | FREDDIE RIVERA |
| Wood Frame | 2/11/2022 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2022 | Approved | FREDDIE RIVERA |
| Sewer | 2/16/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/22/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 2/22/2022 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 2/22/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/28/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/2/2022 | Approved | FREDDIE RIVERA |
| Wood Frame | 3/2/2022 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/7/2022 | Approved | LILIANA PORTILLO |
| Insulation | 3/7/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 3/10/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 3/31/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 5/23/2022 | Approved | HORACE FULTZ |
| HVAC-Final | 5/23/2022 | Approved | HORACE FULTZ |
| PLUMBING-Final | 5/23/2022 | Approved | HORACE FULTZ |
| Final | 5/25/2022 | OK to Issue CofO | HORACE FULTZ |
| Green Building Final | 5/25/2022 | Approved | HORACE FULTZ |
| SGSOV-Seismic Gas S/O Valve | 5/25/2022 | SGSOV Approved | HORACE FULTZ |
| Service/Power Release | 5/25/2022 | Approved | HORACE FULTZ |
| Smoke Detectors | 5/25/2022 | Approved | HORACE FULTZ |
| Final | 6/6/2022 | OK to Issue CofO | ENRIQUE MIRELES |