701 N NIMES ROAD 90077
Certificate Information: 701 N NIMES ROAD 90077
- Application / Permit
- 19014-10000-06529
- Plan Check / Job No.
- B19LA25365
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (1)SECOND STORY ADDITION OF 1297SF (2)MAJOR REMODEL TO EXISTING 2-STORY DWELLING AND BASEMENT
- Permit Issued
- Issued on 2/26/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | DEAN LEE |
| Corrections Issued | 12/18/2019 | DEAN LEE |
| Building Plans Picked Up | 1/6/2020 | APPLICANT |
| Quality Review Completed | 1/8/2020 | BILL STUTSMAN |
| Green Plans Picked Up | 1/29/2020 | APPLICANT |
| Applicant returned to address corrections | 1/30/2020 | DEAN LEE |
| Applicant returned to address corrections | 2/6/2020 | DEAN LEE |
| Applicant returned to address corrections | 2/14/2020 | DEAN LEE |
| Applicant returned to address corrections | 2/26/2020 | DEAN LEE |
| Plan Check Approved | 2/26/2020 | DEAN LEE |
| Issued | 2/26/2020 | LADBS |
| CofO in Progress | 7/15/2023 | CHRISTOPHER WILSON |
| CofO in Progress | 7/15/2023 | CHRISTOPHER WILSON |
| Permit Finaled | 7/31/2023 | DANIEL ORRANTE |
| CofO Issued | 7/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/22/2019 | DEAN LEE |
| BHO/Hillside ordinance | Cleared | 1/29/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 1/29/2020 | THOMAS LANG |
| BHO/Hillside ordinance | Cleared | 1/29/2020 | THOMAS LANG |
| CPC | Cleared | 1/29/2020 | JOE LUCKEY |
| Sewer availability | Cleared | 1/29/2020 | THOMAS LANG |
| ZI | Cleared | 1/29/2020 | JOE LUCKEY |
| ZI | Cleared | 1/29/2020 | JOE LUCKEY |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2020 | JUAN ASHTON |
| Distance to fire station | Cleared | 2/6/2020 | ROBERT DUFF |
| Distance to fire station | Cleared | 2/6/2020 | ROBERT DUFF |
| Hydrant and Access approval | Cleared | 2/6/2020 | ROBERT DUFF |
| Green Code | Cleared | 2/10/2020 | NEGAR NEJAD |
| Low Impact Development | Cleared | 2/10/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/13/2020 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 5/7/2020 | Partial Inspection | CHRISTOPHER WILSON |
| Special/Order Compliance | 5/8/2020 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/20/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 10/23/2020 | Partial Approval | CHRISTOPHER WILSON |
| Drywall Nailing | 1/25/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Green Building Rough | 1/25/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 2/5/2021 | Conditional Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/22/2021 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Partial Approval | CHRISTOPHER WILSON |
| Green Building Rough | 3/3/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 3/3/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Pre-Inspection | 6/25/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Inspection | 6/25/2021 | Partial Inspection | ADAM ESCOTO |
| BUILDING-Rough-Frame | 8/6/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/6/2021 | Partial Approval | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 8/6/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 12/20/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/20/2021 | Partial Inspection | CLAYTON GRAHAM |
| PLUMBING-Rough | 12/22/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Special/Order Compliance | 12/22/2021 | Partial Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 1/12/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 1/24/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Gas Test | 2/15/2022 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Rough | 2/15/2022 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Rough | 2/16/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 3/2/2022 | Corrections Issued | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 3/8/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 3/8/2022 | Approved | CHRISTOPHER WILSON |
| HVAC-Rough | 3/8/2022 | Approved | CHRISTOPHER WILSON |
| Insulation | 3/8/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 3/8/2022 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 4/21/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Green Building Rough | 4/21/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Verify Sprinkler Sign Off | 4/21/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Drywall Nailing | 4/27/2022 | Conditional Approval | CHRISTOPHER WILSON |
| Shower Pan | 4/27/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Shower Pan | 4/28/2022 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 5/3/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/6/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/9/2022 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Approved | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 5/9/2022 | Approved | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/16/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 5/23/2022 | Partial Approval | CHRISTOPHER WILSON |
| BUILDING-Rough-Frame | 5/26/2022 | Approved | CHRISTOPHER WILSON |
| Gas Test | 5/26/2022 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 5/26/2022 | Approved | CHRISTOPHER WILSON |
| Special/Order Compliance | 5/27/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Insulation | 6/6/2022 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 6/17/2022 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | CHRISTOPHER WILSON |
| Shower Pan | 9/6/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 9/19/2022 | Partial Approval | CHRISTOPHER WILSON |
| Gas Test | 11/9/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 11/9/2022 | Partial Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 11/16/2022 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Rough | 11/28/2022 | Not Ready for Inspection | DANIEL ORRANTE |
| Pre-Inspection | 12/1/2022 | Partial Approval | CHRISTOPHER WILSON |
| HVAC-Final | 12/21/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| HVAC-Final | 1/3/2023 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 2/15/2023 | Approved | CHRISTOPHER WILSON |
| PLUMBING-Final | 2/15/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 3/6/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/16/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/24/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Service/Power Release | 3/24/2023 | Corrections Issued | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/28/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| PLUMBING-Final | 3/31/2023 | Approved | CHRISTOPHER WILSON |
| HVAC-Final | 4/4/2023 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 4/12/2023 | Corrections Issued | CHRISTOPHER WILSON |
| HVAC-Final | 4/21/2023 | Approved | CHRISTOPHER WILSON |
| Green Building Final | 5/22/2023 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/2/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Service/Power Release | 6/2/2023 | Approved | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/7/2023 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 6/8/2023 | Approved | CHRISTOPHER WILSON |
| Service/Power Release | 6/8/2023 | Approved | CHRISTOPHER WILSON |
| Final | 6/16/2023 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/16/2023 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 6/16/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Not Ready | CHRISTOPHER WILSON |
| Smoke Detectors | 6/16/2023 | Approved | CHRISTOPHER WILSON |
| Pre-Inspection | 6/26/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 6/28/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Not Ready | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/3/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 7/7/2023 | Not Ready for Inspection | CHRISTOPHER WILSON |
| SGSOV-Seismic Gas S/O Valve | 7/7/2023 | SGSOV Approved | CHRISTOPHER WILSON |
| Final | 7/14/2023 | OK to Issue CofO | CHRISTOPHER WILSON |
| Pool/Spa Cover | 7/18/2023 | Partial Inspection | CHRISTOPHER WILSON |