10045 W RIVERSIDE DR 91602
Certificate Information: 10045 W RIVERSIDE DR 91602
- Application / Permit
- 19014-10000-06518
- Plan Check / Job No.
- B19LA25354
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT AND AN 855 SF ADDITION TO AN (E) 12,225 SF OFFICE BLDG.
- Permit Issued
- Issued on 7/27/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2019 | ZAW HAN |
| Corrections Issued | 12/26/2019 | ZAW HAN |
| Quality Review Completed | 12/27/2019 | HERNAN ARREOLA |
| Building Plans Picked Up | 12/31/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/14/2020 | APPLICANT |
| Applicant returned to address corrections | 2/4/2020 | ZAW HAN |
| Applicant returned to address corrections | 3/2/2020 | ZAW HAN |
| Applicant returned to address corrections | 6/4/2020 | ZAW HAN |
| Applicant returned to address corrections | 6/8/2020 | ZAW HAN |
| Green Plans Picked Up | 7/2/2020 | APPLICANT |
| Plan Check Approved | 7/23/2020 | ZAW HAN |
| Issued | 7/27/2020 | APPLICANT |
| CofO in Progress | 2/10/2021 | ROBERT DAVIS |
| Permit Finaled | 3/17/2021 | JEFFREY DURAN |
| CofO Issued | 3/17/2021 | JEFFREY DURAN |
| Permit Finaled | 3/17/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/27/2020 | JASON CHAN |
| CPC | Cleared | 1/27/2020 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 1/27/2020 | NEGAR NEJAD |
| ZA Case | Cleared | 1/27/2020 | JASON CHAN |
| Sewer availability | Cleared | 2/13/2020 | JOHN LIN |
| Highway dedication | Cleared | 3/17/2020 | LEE GUILBEAUX |
| Permit | Cleared | 3/17/2020 | LEE GUILBEAUX |
| DAS Clearance | Cleared | 4/28/2020 | ELIZABETH TOMS |
| Low Impact Development | Cleared | 6/15/2020 | JORGE MEJIA LEMUS |
| Supp. Use District POD/CDO/TDO | Cleared | 6/24/2020 | ANACANY HURTADO |
| Roof/Waste drainage to street | Cleared | 6/26/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Architect | Marmol,, Leonardo Emilio; Lic. No.: C22376 | MARMOL & RADZINER & ASSOCIATES 12210 NEBRASKA AVE LOS ANGELES, CA 90025 |
| Contractor | J R M Construction Management West Llc; Lic. No.: 1013928-B | 959 SOUTH COAST DR #495 COSTA MESA, CA 92626 |
| Engineer | Paniagua,, Cristobal; Lic. No.: C72894 | 1538 W 92ND ST LOS ANGELES, CA 90047 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/4/2020 | Conditional Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 8/6/2020 | Conditional Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 8/13/2020 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 8/14/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 8/18/2020 | Partial Approval | ROBERT DAVIS |
| Masonry Wall/Backfill | 8/19/2020 | Partial Approval | ROBERT DAVIS |
| Reinforced Concrete Frame | 8/21/2020 | Partial Approval | ROBERT DAVIS |
| Reinforced Masonry Frame | 8/21/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 8/31/2020 | Partial Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 8/31/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 9/4/2020 | Conditional Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 9/8/2020 | Conditional Approval | ROBERT DAVIS |
| Light Gage Steel Frame | 9/11/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 9/16/2020 | Conditional Approval | ROBERT DAVIS |
| Green Building Rough | 9/18/2020 | Partial Approval | JOHN KITCKO |
| Wood Frame | 9/18/2020 | Partial Inspection | JOHN KITCKO |
| Drywall Nailing | 9/22/2020 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 9/29/2020 | Partial Approval | ROBERT DAVIS |
| Insulation | 9/29/2020 | Partial Approval | ROBERT DAVIS |
| Deputy Wood Construction | 10/7/2020 | Conditional Approval | ROBERT DAVIS |
| Drywall Nailing | 10/9/2020 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 10/22/2020 | Partial Approval | ROBERT DAVIS |
| T-Bar Ceiling | 11/13/2020 | Conditional Approval | ROBERT DAVIS |
| T-Bar Ceiling | 11/20/2020 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 11/24/2020 | Approved | ROBERT DAVIS |
| Green Building Final | 1/11/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 2/4/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Footing/Foundation/Slab | 2/4/2021 | Approved | ROBERT DAVIS |
| Green Building Final | 2/4/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Rough | 2/4/2021 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/4/2021 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 2/4/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 2/4/2021 | Approved | ROBERT DAVIS |
| Final | 2/8/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Green Building Final | 2/8/2021 | Approved | ROBERT DAVIS |
| Smoke Detectors | 2/8/2021 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 2/10/2021 | OK to Issue CofO | ROBERT DAVIS |
| Smoke Detectors | 2/10/2021 | Approved | ROBERT DAVIS |