10815 W WELLWORTH AVE 90024

Certificate Information: 10815 W WELLWORTH AVE 90024

Application / Permit
19014-10000-06516
Plan Check / Job No.
B19LA25351
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY ACCESSORY DWELLING UNIT PER CA GOV CODE 65852.2(C). FULLY SPRINKLERED.
Permit Issued
Issued on 7/28/2020
Issuing Office
Current Status
CofO Issued on 10/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/2/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 SAMUEL GONZALEZ
Corrections Issued 12/19/2019 SAMUEL GONZALEZ
Quality Review Completed 1/7/2020 LAWRENCE QUIRANTE
Green Plans Picked Up 7/13/2020 APPLICANT
Plan Check Approved 7/20/2020 SAMUEL GONZALEZ
Plan Check Approved 7/20/2020 SAMUEL GONZALEZ
Issued 7/28/2020 APPLICANT
Building Plans Picked Up 7/29/2020 APPLICANT
CofO in Progress 8/31/2021 OGANES TARAKHCHYAN
No Progress 9/14/2021 KENNETH NAGLE
CofO in Progress 9/17/2021 KENNETH NAGLE
No Progress 9/17/2021 KENNETH NAGLE
CofO in Progress 10/7/2021 KENNETH NAGLE
Permit Finaled 10/7/2021 KENNETH NAGLE
CofO Issued 10/7/2021 KENNETH NAGLE
Permit Finaled 10/7/2021 KENNETH NAGLE

Permit Application Clearance Information

Address approval Cleared 1/13/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/13/2020 CELINA MORENO
Sewer availability Cleared 1/13/2020 CELINA MORENO
Green Code Cleared 2/18/2020 DONALD CRICHLOW
Low Impact Development Cleared 2/18/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 2/24/2020 EMIL KYUPELYAN
Grading Pre-Inspection Cleared 3/17/2020 SAMUEL GONZALEZ
Construction near power lines Cleared 4/5/2020 RIDWAN HARDY

Contact Information

Contractor 5 Star G Development & Construction; Lic. No.: 891495-B 2934 1/2 BEVERLY GLEN CIRCLE   #398    LOS ANGELES, CA 90077
Engineer Kim,, Hong Kook; Lic. No.: C64529 839 S MUIRFIELD RD      LOS ANGELES, CA 90005

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/11/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 8/11/2020 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Barrier 8/11/2020 Corrections Issued OGANES TARAKHCHYAN
METHANE-Final 8/11/2020 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Rough 8/11/2020 Not Ready for Inspection OGANES TARAKHCHYAN
METHANE-Subgrade 8/11/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Underground Mechanical 8/11/2020 Corrections Issued OGANES TARAKHCHYAN
Underground Mechanical 8/21/2020 No Access for Inspection OGANES TARAKHCHYAN
Sewer 8/25/2020 Approved OGANES TARAKHCHYAN
METHANE-Rough 9/29/2020 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 9/29/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 9/29/2020 Partial Approval OGANES TARAKHCHYAN
Underground Mechanical 9/29/2020 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 10/6/2020 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/6/2020 Approved OGANES TARAKHCHYAN
METHANE-Barrier 10/6/2020 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 10/6/2020 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/22/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 10/22/2020 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 10/22/2020 Not Ready for Inspection OGANES TARAKHCHYAN
Wood Frame 10/22/2020 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/30/2020 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 11/17/2020 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 11/18/2020 Approved OGANES TARAKHCHYAN
Wood Frame 12/3/2020 Approved OGANES TARAKHCHYAN
Green Building Final 12/8/2020 Approved EVAN COOPER
HVAC-Rough 12/8/2020 Corrections Issued EVAN COOPER
HVAC-Rough 12/15/2020 Corrections Issued EVAN COOPER
Shower Pan 12/15/2020 Corrections Issued EVAN COOPER
Insulation 12/16/2020 Partial Approval EVAN COOPER
Interior/Exterior Lathing 12/18/2020 Partial Approval OGANES TARAKHCHYAN
Shower Pan 12/18/2020 Approved OGANES TARAKHCHYAN
Drywall Nailing 12/21/2020 Approved OGANES TARAKHCHYAN
Green Building Rough 12/21/2020 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/26/2021 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 5/6/2021 Approved OGANES TARAKHCHYAN
HVAC-Final 5/6/2021 Approved OGANES TARAKHCHYAN
PLUMBING-Final 5/6/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Gas Test 6/21/2021 Not Ready for Inspection ADAM ESCOTO
Gas Test 6/22/2021 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 8/6/2021 Approved OGANES TARAKHCHYAN
Final 8/6/2021 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Final 8/6/2021 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/6/2021 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 8/6/2021 Approved OGANES TARAKHCHYAN
Final 8/27/2021 OK to Issue CofO OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 8/27/2021 SGSOV Approved OGANES TARAKHCHYAN