1859 N NOEL PL 90210

Certificate Information: 1859 N NOEL PL 90210

Application / Permit
19014-10000-06485
Plan Check / Job No.
B19LA25295
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. SEE COMMENT.
Permit Issued
Issued on 1/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 4/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 11/27/2019 TSE MING HUANG
Corrections Issued 12/3/2019 TSE MING HUANG
Plan Check Approved 1/13/2020 TSE MING HUANG
Issued 1/14/2020 LADBS
CofO in Progress 4/20/2026 BRIAN SULLIVAN
Permit Finaled 4/20/2026 DEROLD HAUFF
CofO Issued 4/20/2026 DEROLD HAUFF
Permit Finaled 4/20/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/3/2020 ERIK BEASLEY
Roof/Waste drainage to street Cleared 1/3/2020 ERIK BEASLEY
Sewer availability Cleared 1/3/2020 ERIK BEASLEY
Grading Pre-Inspection Cleared 1/13/2020 TSE MING HUANG

Contact Information

Contractor E C Precise Designs Inc; Lic. No.: 934200-B 8802 LA ENTRADA AVE      WHITTIER, CA 90605
Engineer Baich,, Brendon Chad; Lic. No.: C83347 1898 WILDROSE AVE      POMONA, CA 91767

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2020 Approved RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 2/21/2020 Partial Approval RICHARD STEINBACH
Insulation 2/21/2020 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Approved RICHARD STEINBACH
BUILDING-Rough-Frame 3/27/2020 Approved RAUL BARAJAS
ELECTRICAL-Rough 3/27/2020 Approved RAUL BARAJAS
PLUMBING-Rough 3/27/2020 Approved RAUL BARAJAS
Underground Mechanical 3/27/2020 Not Ready for Inspection RAUL BARAJAS
Insulation 3/31/2020 Approved ROBERT CORNELL
Drywall Nailing 4/2/2020 Approved SABAS ALONSO
Interior/Exterior Lathing 4/2/2020 Approved SABAS ALONSO
ELECTRICAL-Final 6/19/2020 Approved RAUL BARAJAS
Final 6/19/2020 Conditional Approval RAUL BARAJAS
HVAC-Final 6/19/2020 Approved RAUL BARAJAS
PLUMBING-Final 6/19/2020 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 6/19/2020 SGSOV Gas Company RAUL BARAJAS
Smoke Detectors 6/19/2020 Approved RAUL BARAJAS
Final 4/20/2026 OK to Issue CofO BRIAN SULLIVAN