1859 N NOEL PL 90210
Certificate Information: 1859 N NOEL PL 90210
- Application / Permit
- 19014-10000-06485
- Plan Check / Job No.
- B19LA25295
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION AND REMODEL TO (E) SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. SEE COMMENT.
- Permit Issued
- Issued on 1/14/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2019 | TSE MING HUANG |
| Corrections Issued | 12/3/2019 | TSE MING HUANG |
| Plan Check Approved | 1/13/2020 | TSE MING HUANG |
| Issued | 1/14/2020 | LADBS |
| CofO in Progress | 4/20/2026 | BRIAN SULLIVAN |
| Permit Finaled | 4/20/2026 | DEROLD HAUFF |
| CofO Issued | 4/20/2026 | DEROLD HAUFF |
| Permit Finaled | 4/20/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2020 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 1/3/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 1/3/2020 | ERIK BEASLEY |
| Grading Pre-Inspection | Cleared | 1/13/2020 | TSE MING HUANG |
Contact Information
| Contractor | E C Precise Designs Inc; Lic. No.: 934200-B | 8802 LA ENTRADA AVE WHITTIER, CA 90605 |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | 1898 WILDROSE AVE POMONA, CA 91767 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/13/2020 | Approved | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2020 | Partial Approval | RICHARD STEINBACH |
| Insulation | 2/21/2020 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 3/27/2020 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 3/27/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 3/27/2020 | Approved | RAUL BARAJAS |
| Underground Mechanical | 3/27/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Insulation | 3/31/2020 | Approved | ROBERT CORNELL |
| Drywall Nailing | 4/2/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/2/2020 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 6/19/2020 | Approved | RAUL BARAJAS |
| Final | 6/19/2020 | Conditional Approval | RAUL BARAJAS |
| HVAC-Final | 6/19/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 6/19/2020 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 6/19/2020 | SGSOV Gas Company | RAUL BARAJAS |
| Smoke Detectors | 6/19/2020 | Approved | RAUL BARAJAS |
| Final | 4/20/2026 | OK to Issue CofO | BRIAN SULLIVAN |