2859 S VICTORIA AVE 90016

Certificate Information: 2859 S VICTORIA AVE 90016

Application / Permit
19014-10000-06483
Plan Check / Job No.
B19LA25288
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
DEMO PORTION OF(E) GARAGE, ADD 400 SF WITH BEDROOM, BATHROOM, KITCHENETTE AND LIVING ROOM AND CONVERT TO ADU.
Permit Issued
Issued on 3/10/2020
Issuing Office
Metro
Current Status
CofO Issued on 2/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/27/2019 APPLICANT
Assigned to Plan Check Engineer 11/27/2019 RACHEL BEYENE
Corrections Issued 12/6/2019 RACHEL BEYENE
Plan Check Approved 2/11/2020 VU NGUYEN
Issued 3/10/2020 LADBS
CofO in Progress 2/1/2023 STUART CHAPMAN
Permit Finaled 2/14/2023 DEROLD HAUFF
CofO Issued 2/14/2023 DEROLD HAUFF
Permit Finaled 2/14/2023 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 12/11/2019 RAHEL BEYENE
Construction within easement Cleared 1/6/2020 WALTER RAMIREZ
Address approval Cleared 1/8/2020 THOMAS LANG
Hydrant and Access approval Cleared 1/8/2020 JEREMY CARTER
Low Impact Development Cleared 1/24/2020 MARTIN FRAGOSO
Eng Process Fee Ord 176,300 Cleared 2/11/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 2/11/2020 THOMAS LANG
Sewer availability Cleared 2/11/2020 THOMAS LANG

Contact Information

Contractor Jas General Construction Inc; Lic. No.: 1026356-B 2625 S BAKER STREET APT D      SANTA ANA, CA 92707
Engineer Wagoner,, William James; Lic. No.: C37365 4006 GUNTREN RD      CHICO, CA 95973

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/21/2020 Approved STUART CHAPMAN
PLUMBING-Rough 4/21/2020 Partial Approval STUART CHAPMAN
Reinforced Concrete Frame 4/21/2020 Not Ready for Inspection STUART CHAPMAN
Sewer 5/1/2020 Approved STUART CHAPMAN
ELECTRICAL-Rough 5/18/2020 Corrections Issued STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Partial Approval STUART CHAPMAN
PLUMBING-Rough 5/18/2020 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 5/27/2020 Not Ready for Inspection STUART CHAPMAN
Deputy Wood Construction 5/27/2020 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 5/27/2020 Partial Approval STUART CHAPMAN
HVAC-Rough 5/27/2020 Approved STUART CHAPMAN
PLUMBING-Rough 5/27/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 6/2/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 6/2/2020 Not Ready for Inspection STUART CHAPMAN
Insulation 7/6/2020 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 7/6/2020 Not Ready for Inspection STUART CHAPMAN
Shower Pan 7/6/2020 Approved STUART CHAPMAN
Insulation 7/9/2020 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 8/4/2020 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 8/4/2020 Approved STUART CHAPMAN
HVAC-Rough 8/4/2020 Not Ready for Inspection STUART CHAPMAN
Interior/Exterior Lathing 8/4/2020 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 8/12/2020 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/12/2020 Partial Approval STUART CHAPMAN
Wood Frame 8/12/2020 Approved STUART CHAPMAN
Drywall Nailing 8/25/2020 Corrections Issued THOMAS LOGRASSO
Interior/Exterior Lathing 8/25/2020 Approved THOMAS LOGRASSO
Drywall Nailing 9/1/2020 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/28/2020 Approved STUART CHAPMAN
Final 10/28/2020 Corrections Issued STUART CHAPMAN
Green Building Final 10/28/2020 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/28/2020 SGSOV Approved STUART CHAPMAN
Smoke Detectors 10/28/2020 Approved STUART CHAPMAN
Final 11/16/2020 Conditional Approval STUART CHAPMAN
Final 5/10/2021 Conditional Approval STUART CHAPMAN
Final 8/19/2022 Corrections Issued STUART CHAPMAN
Final 2/1/2023 OK to Issue CofO STUART CHAPMAN