627 W 102ND ST 90044
Certificate Information: 627 W 102ND ST 90044
- Application / Permit
- 19014-10000-06481
- Plan Check / Job No.
- B19LA25272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD BATH AT REAR OF (e) SFD UNIT OVER RAISED WOOD FLOOR (TOTAL 86 SF NEW ADD. ) PLUS INTERIOR HOUSE REMODEL (KITCHEN AND BEDROOM)
- Permit Issued
- Issued on 12/16/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/15/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2019 | MICHAEL LOPEZ |
| Corrections Issued | 12/6/2019 | MICHAEL LOPEZ |
| Plan Check Approved | 12/16/2019 | KEVIN MORALES |
| Issued | 12/16/2019 | LADBS |
| CofO in Progress | 10/7/2020 | EUGENE CASSIDY |
| Permit Finaled | 10/15/2020 | DEROLD HAUFF |
| CofO Issued | 10/15/2020 | DEROLD HAUFF |
| Permit Finaled | 10/15/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/13/2019 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/20/2019 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/10/2020 | Approved | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 1/16/2020 | Conditional Approval | WILLIAM ROSE |
| Footing/Foundation/Slab | 1/16/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 1/16/2020 | Partial Approval | EUGENE CASSIDY |
| Sewer | 1/16/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 1/28/2020 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 1/31/2020 | Approved | WILLIAM ROSE |
| Drywall Nailing | 2/4/2020 | Not Ready for Inspection | JOHN KLARIN |
| Drywall Nailing | 2/5/2020 | Partial Approval | WILLIAM ROSE |
| ELECTRICAL-Rough | 2/6/2020 | Approved | WILLIAM ROSE |
| PLUMBING-Rough | 2/6/2020 | Not Ready for Inspection | WILLIAM ROSE |
| PLUMBING-Rough | 2/7/2020 | Approved | EUGENE CASSIDY |
| Shower Pan | 2/11/2020 | Approved | JOHN KLARIN |
| Final | 3/5/2020 | Corrections Issued | WILLIAM ROSE |
| SGSOV-Seismic Gas S/O Valve | 3/5/2020 | SGSOV Not Ready | WILLIAM ROSE |
| Smoke Detectors | 3/5/2020 | Approved | WILLIAM ROSE |
| Final | 3/10/2020 | Corrections Issued | WILLIAM ROSE |
| SGSOV-Seismic Gas S/O Valve | 3/10/2020 | SGSOV Approved | WILLIAM ROSE |
| Final | 7/20/2020 | Corrections Issued | EUGENE CASSIDY |
| Final | 8/18/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/6/2020 | Approved | EUGENE CASSIDY |
| Final | 10/6/2020 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/6/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/6/2020 | Approved | EUGENE CASSIDY |