2843 N AVENEL ST 90039

Certificate Information: 2843 N AVENEL ST 90039

Application / Permit
19014-10000-06445
Plan Check / Job No.
B19LA25169
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(35) Condo-Single Family
Work Description
(N) ADDITION TO REAR OF UNIT, INTERIOR REMODEL OF KITCHEN AND BATHROOM, REPLACE WINDOWS, AND REPLACE WATER HEATER.
Permit Issued
Issued on 3/19/2020
Issuing Office
Metro
Current Status
Issued on 3/19/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/26/2019 APPLICANT
Assigned to Plan Check Engineer 12/20/2019 JESSE ARELLANO
Corrections Issued 1/2/2020 MIGUEL JIMENEZ
Quality Review Completed 1/9/2020 BILL STUTSMAN
Green Plans Picked Up 1/9/2020 APPLICANT
Building Plans Picked Up 1/13/2020 APPLICANT
Applicant returned to address corrections 2/12/2020 MIGUEL JIMENEZ
Applicant returned to address corrections 3/11/2020 MIGUEL JIMENEZ
Applicant returned to address corrections 3/17/2020 JESSE ARELLANO
Plan Check Approved 3/18/2020 JESSE ARELLANO
Issued 3/19/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/12/2020 THOMAS LANG
Grading Pre-Inspection Cleared 2/12/2020 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 2/12/2020 THOMAS LANG
Historic monument Cleared 2/20/2020 LAMBERT GIESSINGER
Green Code Cleared 2/26/2020 MIGUEL JIMENEZ
City Hist. Cultural Monument Cleared 3/18/2020 LAMBERT GIESSINGER

Contact Information

Architect Corsini,, Richard Arthur; Lic. No.: C22360 3630 TYBURN STREET      LOS ANGELES, CA 90065
Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/8/2020 Partial Inspection RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 7/24/2020 Conditional Approval RUSSELL BONVOULOIR
Deputy Wood Construction 7/24/2020 Conditional Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 7/27/2020 Corrections Issued RUSSELL BONVOULOIR
Footing/Foundation/Slab 7/30/2020 Approved RUSSELL BONVOULOIR
Green Building Rough 11/5/2020 Approved RUSSELL BONVOULOIR
Wood Frame 11/5/2020 Conditional Approval RUSSELL BONVOULOIR
Insulation 6/1/2021 Approved RUSSELL BONVOULOIR
Interior/Exterior Lathing 6/1/2021 Approved RUSSELL BONVOULOIR
Interior/Exterior Lathing 6/30/2021 Approved RUSSELL BONVOULOIR
Drywall Nailing 7/9/2021 Approved RUSSELL BONVOULOIR
Final 7/27/2021 Partial Inspection RUSSELL BONVOULOIR
Green Building Final 7/27/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Pre-Inspection 7/27/2021 Partial Inspection RUSSELL BONVOULOIR
SGSOV-Seismic Gas S/O Valve 7/27/2021 SGSOV Not Ready RUSSELL BONVOULOIR
Smoke Detectors 7/27/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Wood Frame 7/27/2021 Approved RUSSELL BONVOULOIR
Final 12/22/2021 Partial Inspection SORIN CIRSTOIU
Green Building Final 12/22/2021 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 12/22/2021 Partial Inspection SORIN CIRSTOIU