4037 W EDENHURST AVE 90039
Certificate Information: 4037 W EDENHURST AVE 90039
- Application / Permit
- 19014-10000-06408
- Plan Check / Job No.
- B19LA25020
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO AN ACCESSORY DWELLING UNIT AND ADDITION PER AB 494 AND SB299
- Permit Issued
- Issued on 5/27/2020
- Issuing Office
- Current Status
- CofO Issued on 7/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2019 | MONICA RAMIREZ |
| Corrections Issued | 12/9/2019 | MONICA RAMIREZ |
| Applicant returned to address corrections | 1/9/2020 | JESSE JIMENEZ |
| Plan Check Approved | 2/4/2020 | SINA KHOSRAVI |
| Issued | 5/27/2020 | APPLICANT |
| Building Plans Picked Up | 6/4/2020 | APPLICANT |
| CofO in Progress | 5/24/2021 | HAMIK HARTOUNIAN |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
| CofO Issued | 7/15/2021 | DEROLD HAUFF |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2019 | EMIL KYUPELYAN |
| Roof/Waste drainage to street | Cleared | 12/9/2019 | EMIL KYUPELYAN |
| Construction near power lines | Cleared | 1/3/2020 | TORI CHEN |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2020 | CELINA MORENO |
| Sewer availability | Cleared | 1/9/2020 | CELINA MORENO |
Contact Information
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/21/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Underground Mechanical | 7/21/2020 | Approved | HAMIK HARTOUNIAN |
| Excavation/Setback/Form/Re-Bar | 7/27/2020 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 7/27/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/13/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/13/2020 | Approved | HAMIK HARTOUNIAN |
| Green Building Rough | 10/13/2020 | Approved | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/13/2020 | Approved | HAMIK HARTOUNIAN |
| Underground Mechanical | 10/13/2020 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 10/28/2020 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 10/28/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 10/28/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 10/28/2020 | Partial Approval | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 10/28/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/2/2020 | Approved | HAMIK HARTOUNIAN |
| HVAC-Rough | 11/2/2020 | Approved | HAMIK HARTOUNIAN |
| Insulation | 11/2/2020 | Approved | HAMIK HARTOUNIAN |
| Gas Test | 11/20/2020 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 11/20/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/30/2020 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 5/14/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Green Building Final | 5/14/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/14/2021 | SGSOV Not Ready | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/14/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 5/21/2021 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 5/21/2021 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 5/21/2021 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 5/21/2021 | Approved | HAMIK HARTOUNIAN |