4037 W EDENHURST AVE 90039

Certificate Information: 4037 W EDENHURST AVE 90039

Application / Permit
19014-10000-06408
Plan Check / Job No.
B19LA25020
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO AN ACCESSORY DWELLING UNIT AND ADDITION PER AB 494 AND SB299
Permit Issued
Issued on 5/27/2020
Issuing Office
Current Status
CofO Issued on 7/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2019 APPLICANT
Assigned to Plan Check Engineer 12/9/2019 MONICA RAMIREZ
Corrections Issued 12/9/2019 MONICA RAMIREZ
Applicant returned to address corrections 1/9/2020 JESSE JIMENEZ
Plan Check Approved 2/4/2020 SINA KHOSRAVI
Issued 5/27/2020 APPLICANT
Building Plans Picked Up 6/4/2020 APPLICANT
CofO in Progress 5/24/2021 HAMIK HARTOUNIAN
Permit Finaled 7/15/2021 DEROLD HAUFF
CofO Issued 7/15/2021 DEROLD HAUFF
Permit Finaled 7/15/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/9/2019 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 12/9/2019 EMIL KYUPELYAN
Construction near power lines Cleared 1/3/2020 TORI CHEN
Eng Process Fee Ord 176,300 Cleared 1/9/2020 CELINA MORENO
Sewer availability Cleared 1/9/2020 CELINA MORENO

Contact Information

Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/21/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 7/21/2020 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 7/27/2020 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 7/27/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/13/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/13/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 10/13/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 10/13/2020 Approved HAMIK HARTOUNIAN
Underground Mechanical 10/13/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/28/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/28/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/28/2020 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 10/28/2020 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 10/28/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 11/2/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 11/2/2020 Approved HAMIK HARTOUNIAN
Insulation 11/2/2020 Approved HAMIK HARTOUNIAN
Gas Test 11/20/2020 Approved HAMIK HARTOUNIAN
Shower Pan 11/20/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/30/2020 Conditional Approval HAMIK HARTOUNIAN
Final 5/14/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 5/14/2021 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/14/2021 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 5/14/2021 Corrections Issued HAMIK HARTOUNIAN
Final 5/21/2021 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 5/21/2021 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 5/21/2021 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 5/21/2021 Approved HAMIK HARTOUNIAN