1275-1277 S CLOVERDALE AVE 90019
Certificate Information: 1275-1277 S CLOVERDALE AVE 90019
- Application / Permit
- 19014-10000-06403
- Plan Check / Job No.
- B19LA24999
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- PROPOSED 2-STORY ADDITION AT REAR OF DUPLEX
- Permit Issued
- Issued on 2/21/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | SINA KHOSRAVI |
| Corrections Issued | 12/13/2019 | SINA KHOSRAVI |
| Quality Review Completed | 12/21/2019 | YOUNG KIM |
| Building Plans Picked Up | 12/27/2019 | APPLICANT |
| Green Plans Picked Up | 12/31/2019 | APPLICANT |
| Applicant returned to address corrections | 1/3/2020 | SINA KHOSRAVI |
| Plan Check Approved | 2/21/2020 | SINA KHOSRAVI |
| Issued | 2/21/2020 | LADBS |
| CofO in Progress | 5/7/2024 | RICHARD DOCKUS |
| CofO in Progress | 5/13/2024 | JOAQUIN GREENOUGH |
| CofO in Progress | 5/16/2024 | JOAQUIN GREENOUGH |
| CofO Issued | 5/17/2024 | DEROLD HAUFF |
| Permit Finaled | 5/17/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2020 | ELAINE LEI |
| Roof/Waste drainage to street | Cleared | 1/3/2020 | ELAINE LEI |
| Sewer availability | Cleared | 1/3/2020 | ELAINE LEI |
| Green Code | Cleared | 1/9/2020 | COLIN LOREDO |
| Tenant Habitability Plan | Cleared | 2/19/2020 | PHILLIP MUNGUIA |
| Hold | Cleared | 6/11/2020 | CYNTHIA RYAN |
Contact Information
| Engineer | Christiansen,, Scott; Lic. No.: C37989 | 1003 WILSHIRE BLVD 202 SANTA MONICA, CA 90401 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/15/2020 | Approved | DAVID CHAN |
| METHANE-Barrier | 6/15/2020 | Approved | DAVID CHAN |
| METHANE-Subgrade | 6/15/2020 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 6/22/2020 | Partial Approval | DAVID CHAN |
| Sewer | 9/14/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2020 | Partial Approval | DAVID CHAN |
| BUILDING-Rough-Frame | 10/2/2020 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 10/2/2020 | Approved | STUART CHAPMAN |
| Green Building Rough | 10/2/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 10/2/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 10/28/2020 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 11/4/2020 | Approved | DAVID CHAN |
| Green Building Rough | 11/4/2020 | Approved | DAVID CHAN |
| Insulation | 11/4/2020 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 11/4/2020 | Approved | DAVID CHAN |
| PLUMBING-Rough | 11/4/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 11/9/2020 | Partial Approval | DAVID CHAN |
| Green Building Rough | 11/9/2020 | Approved | DAVID CHAN |
| Drywall Nailing | 11/19/2020 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 4/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/28/2021 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 4/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Final | 4/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| PLUMBING-Final | 4/28/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/28/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 4/28/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 11/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 11/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 11/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 12/12/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 12/12/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 12/12/2023 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 1/11/2024 | Partial Inspection | RONNIE MINDANAO |
| Green Building Final | 1/11/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 1/11/2024 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 1/11/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Final | 3/26/2024 | No Access for Inspection | ENRIQUE MIRELES |
| Green Building Final | 3/26/2024 | No Access for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Not Ready | ENRIQUE MIRELES |
| Smoke Detectors | 3/26/2024 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 4/2/2024 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 4/2/2024 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 4/2/2024 | Approved | RICHARD DOCKUS |
| Final | 4/8/2024 | Corrections Issued | RICHARD DOCKUS |
| Final | 4/23/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 5/16/2024 | OK to Issue CofO | JOAQUIN GREENOUGH |