1428 N OGDEN DR 90046

Certificate Information: 1428 N OGDEN DR 90046

Application / Permit
19014-10000-06396
Plan Check / Job No.
B19LA24964
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL & GROUND FLOOR ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/24/2020
Issuing Office
Metro
Current Status
Issued on 1/24/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/22/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 LAMAR DAVIS
Corrections Issued 12/10/2019 LAMAR DAVIS
Quality Review Completed 12/17/2019 BILL STUTSMAN
Building Plans Picked Up 12/20/2019 APPLICANT
Green Plans Picked Up 12/20/2019 APPLICANT
Applicant returned to address corrections 1/17/2020 LAMAR DAVIS
Plan Check Approved 1/24/2020 LAMAR DAVIS
Issued 1/24/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2020 JEANIE LAM
Sewer availability Cleared 1/8/2020 JEANIE LAM
Green Code Cleared 1/16/2020 COLIN LOREDO
Low Impact Development Cleared 1/16/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/16/2020 ERIK BEASLEY
HPOZ Cleared 1/23/2020 AMANDA KAINER
Miscellaneous Cleared 1/23/2020 AMANDA KAINER

Contact Information

Architect Phakos,, Cynthia; Lic. No.: C23352 9010 RANGELY AVE      WEST HOLLYWOOD, CA 90048
Contractor Jno Construction And Design Inc; Lic. No.: 1051923-B 750 N SAN VICENTE STE 800   WEST RED    WEST HOLLYWOOD, CA 90069
Engineer Jahanpour-Burke,, Hooshmand; Lic. No.: L8230 830 S DURANGO DR STE 100      LAS VEGAS, NV 89145
Engineer Manalo,, Philip Casis; Lic. No.: S3823 9547 WYSTONE AVE      NORTHRIDGE, CA 91324

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/10/2020 Approved RAUL BARAJAS
Footing/Foundation/Slab 2/10/2020 Partial Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/16/2020 Approved RAUL BARAJAS
Underground Mechanical 3/16/2020 Approved RAUL BARAJAS
BUILDING-Rough-Frame 3/23/2020 Not Ready for Inspection RAUL BARAJAS
Green Building Rough 3/23/2020 Not Ready for Inspection RAUL BARAJAS
Underground Mechanical 3/23/2020 Partial Approval RAUL BARAJAS
Wood Frame 3/23/2020 Partial Approval RAUL BARAJAS
Wood Frame 3/25/2020 Partial Approval RAUL BARAJAS
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Approved RAUL BARAJAS
Wood Frame 4/3/2020 Partial Approval RAUL BARAJAS
HVAC-Rough 5/6/2020 Approved RAUL BARAJAS
PLUMBING-Rough 5/6/2020 Approved RAUL BARAJAS
Shower Pan 6/8/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/19/2020 Partial Approval CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 6/22/2020 Approved MATTHEW NUCKOLLS
Underground Mechanical 6/22/2020 Not Ready for Inspection MATTHEW NUCKOLLS
BUILDING-Rough-Frame 8/11/2020 Corrections Issued RAUL BARAJAS
Green Building Rough 8/11/2020 Approved RAUL BARAJAS
Wood Frame 8/11/2020 Conditional Approval RAUL BARAJAS
BUILDING-Rough-Frame 8/17/2020 Approved RAUL BARAJAS
Interior/Exterior Lathing 8/17/2020 Approved RAUL BARAJAS
Wood Frame 8/17/2020 Approved RAUL BARAJAS
Insulation 9/16/2020 Approved COREY HUPP
Drywall Nailing 9/25/2020 Approved RAUL BARAJAS
ELECTRICAL-Final 1/22/2021 Not Ready for Inspection RAUL BARAJAS
Service/Power Release 1/22/2021 Corrections Issued RAUL BARAJAS
Special/Order Compliance 2/19/2021 Approved RAUL BARAJAS
Final 2/26/2021 Corrections Issued RAUL BARAJAS
Footing/Foundation/Slab 2/26/2021 Approved RAUL BARAJAS
Green Building Final 2/26/2021 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved RAUL BARAJAS
Smoke Detectors 2/26/2021 Approved RAUL BARAJAS
Special/Order Compliance 9/19/2023 Corrections Issued STUART CHAPMAN